FORM 1 (See Regulation 3) ARCHITECT’S CERTIFICATE (To be submitted at the time of registration of Ongoing Project and for withdrawal of Money from Designated Account) Date: 10.02.2023 To, PTR Universal 406, La MagasinBuilding , S V Road , Santacruz (West). Mumbai-400054. Sub : Certificate of Percentage of Construction Work of the Building situated on the Plot bearing CTS No. G/231, F.P. No. 29 of Village Bandra-G, at Santacruz (W), Mumbai, demarcated by its boundaries (19°04'43.76104"'N-72°50'1140167"E, 19°04'44.25334"N-72°50'11.55051"E, 19°04'44.45989"N - 72°50'11.83394"E, 19°04'44.32819"N - 72°50'12.76896"E, 19°04'43.62951"N - 72°50'12.71776"E, ) 13.00 Mtr Gujjar Road to the North, F.P.No. 34 on South, 12.20 Mtr wide Andrew Road (Jain Derasar Marg ) on West, F.P. No. 30 on East, Taluka Andheri , H/W Ward, of Mumbai Suburban District, admeasuring 864.60 square mtrs. area Being developed by M/s. PTR Universal. Sir, I, Ghanshyam S. Mistry of M/s. The Design Core, Architects & designers ,have undertaken assignment as Architect of certifying Percentage of Construction Work of the the Building situated on the Plot bearing CTS No. G/231, F.P. No. 29 of Village Bandra-G, at Santacruz (W), Mumbai, demarcated by its boundaries (19°04'43.76104"'N-72°50'1140167"E, 19°04'44.25334"N-72°50'11.55051"E, 19°04'44.45989"N - 72°50'11.83394"E, 19°04'44.32819"N - 72°50'12.76896"E, 19°04'43.62951"N - 72°50'12.71776"E, ) 13.00 Mtr Gujjar Road to the North, F.P.No. 34 on South, 12.20 Mtr wide Andrew Road (Jain Derasar Marg ) on West, F.P. No. 30 on East, Taluka Andheri , H/W Ward, of Mumbai Suburban District, admeasuring 864.60 square mtrs. area Being developed by M/s. PTR Universal. Following technical professionals are appointed by Promoter :- (i) Shri. Ghanshyam S. Mistry of M/s. The Design Core, Architects & designers as Architect. (ii) Shri. Sunil Shah as Structural Consultant (iii) Shri. Vidya Singh of M/s VCE Consulting as MEP Consultant (iv) Shri. Sanjay N. Shah as Site Supervisor Based on site Inspection, with respect to each of the Building/Wing of the aforesaid Real Estate Project, I certify that as on the date of this certificate, the Percentage of Work done for each of the building/Wing of the Real Estate Project as registered vide number P51800020732 under MahaRERA is as per Table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. Table A 204, Rose Residency, Dixit X Road Off Shraddhanand Road, Vile Parle (E), Mumbai - 400 057. Tel: +91 22 26125965 Email: arch.tdc@gmail.com Sr .No. Tasks/Activity Percentage of work done 1 Excavation 100% 2 One No of Basement(s) and Plinth 100% 3 2 Nos Number of Podium 100% 4 Stilt Floor 100% 5 12 Number of Slabs of Super Structure 100% 6 Internal wall, Internal Plaster, Floorings within Flats/Premises, 100% Doors and Windows to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical Fittings 100% within the Flat/Premises 8 Staircase, Lifts Wells and Lobbies at each Floor level 100% connecting Staircase and Lifts, Overhead and Underground Water Tanks 9 The external plumbing and external plaster, elevation, 100% completion of terraces with waterproofing of the Building/Wing 10 Installation of lifts, water pumps, Fire Fighting Fittings and 100% Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, compliance to conditions of environment/CRZ BOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation/Completion Certificate Table B Internal & External Development Works in Respect of the entire Registered Phase Sr. No. Common Areas and Facilities, Proposed Percentage of Details Amenities (Yes/No) Work Done 1 Internal Roads & Footpaths No N.A. N.A. 2 Water Supply Yes 100% __ 3 Sewerage(Chamber, Lines, Septic Yes 100% __ Tank, STP) 4 Storm Water Drains Yes 100% __ 5 Landscaping & Tree Planting Yes 100% __ 6 Street Lighting No N.A. N.A. 7 Water Conservation, Rain Water Yes 100% __ Harvesting 8 Energy Management No N.A. N.A. 204, Rose Residency, Dixit X Road Off Shraddhanand Road, Vile Parle (E), Mumbai - 400 057. Tel: +91 22 26125965 Email: arch.tdc@gmail.com 9 Fire Protection and Fire Safety Yes 100% __ requirements 10 Electrical Meter Panel / Room, Sub- Yes 100% __ station, receiving station 11 Aggregate area of recreational Open No 0 N.A. Space 12 Open Parking No 0 N.A. 13 Community Buildings No N.A. N.A. 14 Treatment and Disposal of sewage and No N.A. N.A. sullage water 15 Solid Waste Management & Disposal No N.A. N.A. 16 Others (Option to Add more) - a) Society Office Yes 100% b) Gymnasium Yes 100% Yours faithfully For, The Design CORE Architects & Designers Digitally signed by GHANSHYAM SHIVLAL GHANSHYAM SHIVLAL MISTRY MISTRY Date: 2023.02.11 11:05:27 +05'30' Mr. Ghanshyam S. Mistry C.A. - 2003/ 31880 204, Rose Residency, Dixit X Road Off Shraddhanand Road, Vile Parle (E), Mumbai - 400 057. Tel: +91 22 26125965 Email: arch.tdc@gmail.com