Ar. Nilesh Mahangade B.Arch Architect IInterior Designer | GRIHA Ar. Pranjali Mahangade M.Arch - Digital Architecture GRIHA consultant ARCHSIGND Info@archsignoarchitects.co.in ARC HITECTS +9173 0404 7878 IMPRoVING UNIMPROVED Annexure A FORM 1 ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account) DATE - 01-07-2025 (Period: 01-04-2025 To 31-06-2025) To, M/s PNR GROUP DEVELOPERS ShriNilesh Bapurao Kadam Room No. 505, D1 Wing, Ushakiran Residency, Kharvai naka, Badlapur East- 421503. Subject: Certificate of Percentage of Completion of construction work of Om Sumukh Darshan Co-op. Hsg. Soc. Having MahaRERA Registration Number P51700077321 being developed by M/s PNR Group Developers Sir, I, Mr. Nilesh V. Mahangade have undertaken assignment as Architect of certifying Percentage of Completion of construction work of Om Sumukh Darshan Co-op. Hsg. Soc. Having MahaRERA Registration Number P51700077321 being developed by M/s PNR Group Developers. Based on Site Inspection, with respect to Layout/ each of the Buildings /Wing of the aforesaid Real Estate Project, Icertify that as on the date of this certificate, the Percentage of Work done for each of the Buildings /Wing of the Real Estate Project under MahaRERA is as per Table Aherein Below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. www.archsignoarchitects.co.in Ar. Nilesh Mahangade B.Arch Architect IInterlor Designer | GRIHA Ar. Pranjali Mahangade MArch - Digital Architecture GRIHA consultant ARCHSIGN ARG H I T E C T S Info@archsignoarchitects.co.in 491 73 0404 7878 IMPRoVING UNIM PROVED Table - A Percentage of Actual Work Done Sr. No. Task/Activity (As on date of the (1) (2) Certificate) (3) 1 Excavation 100% 2 Zero number of Basement N.A. 3 One number of Podiums N.A. 4 Plinth 100% Stilt/ground Floor 100% 6 6_number of Slabs of Super Structure (All SLAB COMPLETED) 100% Internal walls 100% Internal Plaster 100% 7 Flooring within the flats/premises 90% Doors and Windows to each flat/premises 50% Sanitary Fittings within the Flat/Premises 70% Staircases (RCC Work) 100% Lift Wels (RCC Work) and Lobbies at each Floor level 90% Overhead Water Tank 85% Underground Water Tanks 100% External plumbing 90% External plaster 100% 10 Elevation 100% Completion of terraces with waterproofing of the Building /Wing. 100% Installation of lifts 90% Water pumps 0% Fire Fighting Fittings and Equipment's as per CFO NOC N.A. Electrical fittings 60% Mechanical equipment N.A. Compliance to conditions of environment / CRZ NOC N.A. 11 S0% Finishing to entrance lobby's Plinth protection 100% Paving of areas appurtenant to Building/Wing 0% Compound Wall and all other requirements as may be required to complete project as per specification in agreement of sale, Any 0% other activities www.archsignoarchitects.co.in Ar. Nilesh Mahangade B.Arch Architect | Interior Designer | GRIHA Ar. Pranjali Mahangade M.Arch - Digital Architecture ARCHSIGNO Info@archsignoarchitects.co.in GRIHAconsultant ARC HITE CTS +91 73 0404 7878 IMPRoviNG UNIMPROVED Table B Common Areas (internal &External Development Works) in Respect of the Entire Registered Phase Percentage of Actual Proposed Work done SNo Common Areasand Facilities (Yes/No) Details (As on date of the (1) (2) (5) (3) certificate) (4) 1 Internal Roads & Footpaths No 0% N.A. 0% MJP get connection 2 Water Supply Yes after O.C Sewerage (chamber, lines, Yes 0% Work not started Septic Tank, STP) 4 Strom Water Drains No 0% N.A. 5 Landscaping &Tree Planting No 0% N.A. 6 Street Lighting Yes 0% Provided by KBMC 7 Community Buildings No 0% N.A. Treatment and disposal of No 0% N.A. sewage and sullage water 9 Solid Waste management & No 0% N.A. Disposal Water conservation, Rain Water harvesting 10 No 0% Rainwater harvesting Work not yet started 11 Energy management No 0% N.A. Fire protection and fire safety No 0% N.A. 12 requirements Electrical meter room, sub Meter room provided 13 Yes 0% station, receiving station Work not yet started Aggregate area of 0% N.A. 14 No recreational open space 15 Open parking No 0% N.A. Specify if any further facility is 16 provided (other than above No 0% N.A. mentioned) Yours Faithfully Agreed and Accepted by: AOARCIS ARCHTECTS AR. N0LESH V. MAHANGADE Name: MR. NILESH BAPURAO KADAM. ANG CA/2017/s9343 Date: - www.archsignoarchitects.co.in