UC ASSOCIATES A/202, Sarvoday Aangan Soc., Pandurang Wadi, Street No. 2, Near Sai Baba Temple, Dombivli (E) 421 201 Architect &Interior Designer Email: uCassociates29@gmail.com | 7666283 484 FORM 1 [see Regulation 3] ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account) Date: 30/06/ 2025 To, Mr. Hasmukh Patel& Milan Patel M/S. Milan Associates Dombivli (E). Subject:Certificate of Percentage of Construction Work of Milan Heights having MahaRERA Registration Number P51700076985 (Only Applicable after project Registration) being developed by M/S. Milan Associates. Sir, I/We Ar. Uday Mansukhlal Chopda have undertaken assignment as Architect /Licensed Surveyor of certifying Percentage of Completion of Construction Work of Milan Heights having MahaRERA Registration Number P51700076985 (Only applicable after project Registration, being developed by M/S. Milan Associates. Based on site Inspection, with respect to Layout/ each of the Building/Wingof the aforesaid Real Estate Project. I certifythat as on the date of this certificate, the Percentage of Work done for each of the building/VWing of the Real Estate Project under MahaRERA is as per Table Aherein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. UDAY M. CHOPDA \CA/2017/86339 UC ASSOCIATES A/202,Sarvoday Aangan Soc.,Pandurang Wadi, Street No. 2, Near Sai Baba Temple, Dombivli (E) 421 201 Architect &Iterior Designer Email : ucassociates29@gmail.com l 7666 283 484 Table A Layout /Building /Wing Number 1 (to be prepared separately for each Layout /Building /Wing of the Project) % of work Sr.No. Tasks/Activity done 100 1 Excavation number of Basement(s) and Plinth 100 2 1Plinth 3 number of Podiums 4 Stilt Floor 50 5 11 number of Slabs of Super Structure 6 Internal Walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to 15 each of the Flat/Premises. 7 Sanitary Fittings within the Flat/Premises, Electrical Fittings within the Flat/Premises. Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing. 10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and allother requirements as may be required to obtain Occupation / Completion Certificate. Table B Common Areas (Internal and External Development Works) in respect of the Registered Phase/ Project Number Sr. Common areas and Facilities, Amenities Proposed % of work Details No. (Yes/No) done 1. Internal Roads & Foot paths. No. N.A. 2. Water Supply Yes 3 Sewerage (chamber, lines, Septic Tank, STP). Yes 0 4 Storm Water Drains Yes 5 Landscaping &Tree Planting. Yes 0 6 Street Lighting No. N.A. 7 Community Buildings No. N.A. 8 Treatment and disposal of sewage and sullage water. No. N.A. 9 Solid Waste management &Disposal. No. N.A. 10. Water conservation, Rain water harvesting. Yes 11. Energy management Yes N.A. 12. Fire protection and fire safety requirements Yes 13. Electrical meter room, sub-station, receiving station. Yes 14. Others ( Option to Add more). M/s. Milan Associates Yours Faithfull SOC Agreed ant Accepted by: UDAY Partners M. CHOPDA m UCASSOCIATES CA/2017/88339 Name : Hasmukh Patel & Milan Patel AR. UDAY M. CHOPDA Date :30/06/2025 (License No. CA/2017/88339)