Annexure A FORM 1 ARCHITECTS CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account) Date : 30-09-2024 To, Rustagi Estates Pvt.Ltd., Atul Baug, Near saraswat bank, Syndicate, Kalyan-Murbad Road, Kalyan- 421301. Subject : Certificate of Percentage of Completion of Construction Work of RUSTTAGI AARAMBHA 2.0 having MahaRERA Registration Number P51700076932 being developed by RUSTAGI ESTATES PRIVATE LIMITED Based on Site Inspection, with respect to each of the Building/Wing of the aforesaid Real Estate Project, I certify that a son of the date of this certificate, the Percentage of Work done for each of the building/Wing of the Real Estate Project as registered vide Number P51700076932 under MahaRERA is as per table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. TABLE-A Layout / Building/wing Number4 -Residential & Commercial Sr. Tasks / Activity Percentage of Actual Work No. Done (As on date of the Certificate) 1 Excavation 100% 2 Basements (if any) N.A 3 Podiums (if any) N.A 4 Plinth 85% 5 Stilt Floor 00% 6 Slabs of Super Structure 0% 7 Internal walls, Internal Plaster, Floorings within 0% Flats/Premises, Doors and Windows to each of the Flat/Premises 8 Sanitary Fittings within the Flat/Premises 0% 9 Staircases, Lifts Wells and Lobbies at each Floor 0% level connecting Staircases and Lifts, Overhead and Underground Water Tanks 10 External plumbing and external plaster, \ 0% Elevation, completion of terraces with water proofing of the Building/Wing. 11 Installation of lifts, water pumps, Fire Fighting 0% Fittings and Equipment as per CFONOC, Electrical fittings, mechanical equipment, Compliance to conditions of environment/CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. Any other Activities. Office: 602-B, 11 Sarvoday, Kher Nagar, Bandra (East), Mumbai – 400051. | Tel: +91 22 2647 7036 TABLE-B Common Areas (Internal &External Development Works)in Respect of the entire Registered Phase / Project Number Sr.No Common areas Proposed Percentage of Details And Facilities, Amenities (Yes/No) Work done 1. Internal Roads & Footpaths YES 10% 2. Water Supply YES 0% 3. Sewarage(chamber, lines, Septic Tank, YES 0% STP) 4. Storm Water Drains YES 0% 5. Landscaping &Tree Planting YES 0% 6. Street Lighting YES 10% 7. CommunityBuildings YES 0% 8. Treatment and disposal of sewage and YES 0% sullage water 9. Solid Wastemanagement& Disposal YES 0% 10. Waterconservation, Rain water YES 10% harvesting 11. EnergyManagement YES 0% 12. Fire protectionAnd fire safety YES 0% requirements 13. Electrical meterroom, sub-station, YES 0% receiving station 14. Others (Option toAddmore) YES 0% Yours Faithfully For UB Architects, Digitally signed by UJWAL UJWAL SATISH BHOLE SATISH BHOLE Date: 2024.12.25 17:30:32 +05'30' Ar. Ujwal Bhole (License NO. CA/2010/47919) Agreed and accepted by: Signature of Promoter Name: Rustagi Estate Pvt. Ltd., Date : 30.09.2024. Office: 602-B, 11 Sarvoday, Kher Nagar, Bandra (East), Mumbai – 400051. | Tel: +91 22 2647 7036