ARCHITECT'S CERTIFICATE Date: 14/09/2023 To, M/s. Lambodar Infra Dombivli East Subject: Certificate of Percentage of Completion of Construction Work of ‘Manuprasad’ project. [MahaRERA Registration Number ____________ ] situated on the Plot bearing CTS no. 301 (A) & 302 to 309 mouje: Ayare Dombivli (E), Tal. Kaylan. Admeasuring 854.90 sq.mts. Area being developed by Lambodar Infra. Sir, I Akash D.Sonawane. have undertaken assignment as Architect of Certifying Percentage of Completion of Construction Work of ‘Manuprasad’ Building of the Project [MahaRERA Registration Number ____________ situated on the Plot bearing CTS no. 301 (A) & 302 to 309 mouje: Ayare Dombivli (E), Tal. Kaylan. Admeasuring 854.90 sq.mts. Area being developed by Lambodar Infra. 1. Following technical professionals are appointed by Promoter:- (i)Shri. Akash D. Sonawane as Architect; (ii)Shri. Aaditya Deshmukh as Structural Consultant (iii) Shri. Harshal More as Site Supervisior Based on Site Inspection, with respect to each of the Building of the aforesaid Real Estate Project , I certify that as on the date of this certificate, the Percentage of Work done for each of the building of the Real Estate Project as registered vide number ___________ under MahaRERA is as per table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. Table A Building Sr. No Tasks /Activity Percentage of work done 1 Excavation 0 2 Basement NA 3 Podiums NA 4 Plinth 0 5 Stilt Floor 0 6 Slabs of Super Structure 0 7 Internal walls, Internal Plaster, Floorings within 0 Flats/Premises,Doors and Windows to each of the Flat/Premises 8 Sanitary Fittings within the Flat/Premises, Electrical Fittings 0 within the Flat/Premises 9 Staircases, Lifts Wells and Lobbies at each Floor level 0 connecting Staircases and Lifts, Overhead and Underground Water Tanks. 10 The external plumbing and external plaster, elevation, 0 completion of terraces with waterproofing of the Building/Wing. 11 Installation of lifts, water pumps, Fire Fighting Fittings and 0 Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of sale. Any other activities. TABLE-B Internal & External Development Works in Respect of the entire Registered Phase S.No Common areas Proposed Percentag Details and Facilities, (Yes/No) e of Work Amenities done 1. Internal Roads &Footpaths NA NA NA 2. Water Supply YES 0 Water connection will be given by KDMC after OC 3. Sewerage (chamber, lines, YES 0 Sewerage Shall be Septic Tank ,STP) carried out as per NOC 4. Storm Water Drains YES 0 Shall be carried out as per NOC 5. Landscaping & Tree Planting YES 0 Shall be carried out as per NOC 6. Street Lighting NO NA NA 7. Community Buildings NO NA NA 8. Treatment and disposal of NO NA NA sewage and sullage water. 9. Solid Waste management & NO NA NA Disposal 10. Water conservation, Rain YES 0 Shall be carried out water harvesting as per NOC 11. Energy management NO NA NA 12. Fire protection and fire safety YES 0 Shall be carried requirements out as per NOC 13. Electrical meter room, sub- YES 0 As instructed By station receiving station MSEB 14. Others ( Option to Add more) - - - Yours Faithfully, Agreed and Accepted by: Signature of Promoter Name: Date: