FORM 1 ARCHITECT’S CERTIFICATE (As on 30/09/2025) Date : 07.10.2025 To, M/S REAL HOMES DEVELOPERS 311, Omega Business Park, Opp. Esic Hospital, Rd. No. 33, Wagle Estate, Thane (W) – 400604. Subject : Certificate of Percentage of Completion Work of Redevelopment Project of SOLANKI CO-OP. HSG. SOC. LTD., having MahaRERA Registration number P51700076642, being developed by M/S REAL HOMES DEVELOPERS. Sir, I AR. JITENDRA MUKADAM, Partner in GODBOLE MUKADAM & ASSO. have undertaken assignment as Architect of certifying Percentage of Completion of Construction Work of Redevelopment Project of Solanki Co-Op. Hsg. Soc. Ltd., having MahaRERA Registration number P51700076642, being developed by M/s Real Homes Developers. Based on Site Inspection, with respect to Layout / each of the Building / Wing of the aforesaid Real Estate Project, I certify that as on the date of this certificate, the Percentage of Work done for each of the Building / Wing of the Real Estate Project under MahaRERA is as per Table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in table B. TABLE A Building ‘A’ Percentage of Actual Work Sr. No. Task / Activity Done (1) (2) (As on date of the certificate) (3) 1. Excavation 100 % 2. Basements (if any) N.A. 3. Podiums (if any) N.A. 4. Plinth 100 % 5. Stilt Floor 100 % 6. Slabs of Super Structure (9 out of 11 nos.) 82 % Internal walls, Internal Plaster, Flooring, Doors 7. 0% and windows within Flats / Premises 8. Sanitary Fittings within the Flat / Premises 0% Staircase, Lift Wells and Lobbies at each Floor 9. 0% level, Overhead and Underground Water tanks External plumbing and external plaster, 10. elevation, completion of terraces with 0% waterproofing of the Building / Wing. Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions of environment / CRZ NOC, Finishing to entrance lobby/s, plinth 11. 0% protection, paving of areas appurtenant to Building / Wing. Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. Any other activities. TABLE B Common Areas (Internal and External Development Works) in respect of the Registered Project Percentage of Actual Sr. Common areas and Proposed Work Done Details No. Facilities (Yes / No) (As on date (5) (1) (2) (3) of the Certificate) (4) 1. Internal Roads & Footpaths No - - Will be connected 2. Water Supply Yes 0% to TMC water supply line. Will be Sewerage (Chamber lines, connected 3. Yes 0% Septic Tank, STP) to TMC sewer line. Will be connected 4. Storm Water Drains Yes 0% to TMC storm water drains. No landscaping. Landscaping & Tree Trees will be 5. No 0% Planting planted as per Garden dept. NOC. Campus 6. Street Lighting No - lighting only Society office, Fitness 7. Community Buildings Yes 0% Centre proposed. Will be connected Treatment and disposal of 8. No - to TMC sewer sewage and sullage water line without treatment. Solid Waste management 9. No - - & Disposal Bore-well Water conservation / Rain recharging 10. Yes 0% water harvesting with filtration pits. Solar water heating 11. Energy management Yes 0% system will be proposed. Fire protection and fire As per CFO 12. Yes 0% safety requirements norms. Electrical meter room, sub- Meter room 13. Yes 0% station, receiving station proposed. Yours Faithfully, AR. Jitendra Mukadam (License No. CA/92/14751) Agreed and Accepted by : Signature pf Promoter Name : M/s Real Homes Developers Date : 07.10.2025