FORM 1(See Regulation No. 3) Date:- 30/06/2026. To, M/s. Siddh Enterprise, Shop no 15, New Zunzarao Building, Shivaji Path, Station Road, Kalyan W. Pin code- 421 301. Sub:- Certificate of percentage of completion of construction work of Building ROYAL MEADOWS (Maha RERA Registration Number P51700066576) situated on the plot bearing C.T.S. No. 1721/B, Vill:- Kalyan, Taluka:- Kalyan , District:- Thane, Pin- 421301, being developed by M/s. SIDDH ENTERPRISE. Sir, I, Shobhana Deshpande, Proprietor, CREATIONS, have undertaken assignment as an Architect of certifying of percentage of completion of construction work of Building ROYAL MEADOWS (Maha RERA Registration Number P51700066576) situated on the plot bearing C.T.S. No. 1721/B, Vill:- Kalyan, Taluka:- Kalyan , District:- Thane, Pin- 421301, being developed by M/s. SIDDH ENTERPRISE. Based on Site Inspection, with respect to each of the Building of the aforesaid Real Estate Project, I certify that as on the 30/06/2026, the Percentage of work done for each of the Wing of the Real Estate Project as registered vide number P51700066576) under MahaRERA is as per table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. Table – A Building: Sr. No. Tasks/ Activity Percentage of work done as on 30/06/2026. 1. Excavation 100% 2. Number of Basement(s) and Plinth 100% Basement not proposed 3. 0 Number of podiums 0% 4. Stilt Floor 100% 5. 8 number of slabs of super structure 100% 8th slab is completed. 6. Internal walls, Internal Plaster, Flooring within Flats/ Premises 100% Doors and Windows to each of the Flat/Premises 7. Sanitary Fittings within the Flat/Premises 100% Electrical Fittings within the Flat/Premises 8. Staircase, Lifts Wells and Lobbies at each Floor level connecting Staircase and Lifts, 100% Overhead and Underground Water Tanks 9. The external plumbing and external plaster, elevation, 100% completion of terraces with waterproofing of the Building/Wing 10. Installation of lifts, water pumps, Fire Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, 100% Compliance to conditions of environment/CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation/Completion Certificate. Note: - The work percentage mentioned above is as per the number of floors sanctioned vide letter no. KDMCC / RB/ 2024/APL/00096, Dated – 13/11/2024. Table - B Internal & External Development Works in Respect of the entire Registered Phase Common areas and Facilities, Proposed Percentage of Sr. Amenities (Yes/ No) work done as Details No. on 30/06/2026. 1. Internal Roads & Footpaths No -- -- 2. Water Supply Yes 100% Water Supply to be provided by KDMC 3. Sewerage (Chamber, lines, -- Septic Tank) Yes 100% 4. Storm Water Drains Yes 100% -- 5. Landscaping & Tree Planting Yes 100% -- 6. Street Lighting No -- -- 7. Community Buildings No -- -- 8. Treatment and disposal of No -- -- sewage and sullage water 9. Solid Waste management & No -- -- Disposal 10. Water conservation Rain water Yes 100% -- harvesting 11. Energy management No -- -- 12. Fire protection and fire safety Yes 100% -- requirements 13. Electrical meter room, sub- Yes 100% -- station, receiving station 14. Club House No 100% -- Ar.Shobhana Deshpande (Reg. No. CA/ 87/10647) For CREATIONS