Er. Darshan Kasture SAAD Chartered Engineer I.E.I., L0.V., L.S.S.E. CONSULTANT M-Tech Structural B.E. (CIVIL), DIPLOMA 9370444659/9967T73610 "UDYAM- MH-33-0276843" Form - 2 ENGINEER'S CERTIFICATE DATE: 31/03/2026 To, M/S. SAIRAJCONSTRUCTION, Through It's Partner Mr. Dattatray WalkuMhase Mr.Mahesh Janardhan Vishe 303,Krupasindhu Building, Opp. Mahalaxmi Mandir, Near Bus Depot, Badlapur(W)Dist-Thane 421503 Date:-01/01/2026 to 31/03/2026 Subject : Certificate Of Percentage Of Completion Of Construction Work Of "Om Guru Krupa Co Op Housing Society Ltd". Building Of The Single Phase Project(Maha RERA Registration No.P51700056339) Situated On The Survey No-20, Hisaa No -7/8, Plot No-10 Demarcated By Its Boundaries (Latitude And Longitude Of The End Points) Plot No-8 &9 To The North,Hissa No-3 To The South Plot No . 5 &6 To The East,9.0 ,Mtr Wide Road To The West Of Division -Konkan Village - Kulgaon ,Taluka - Ambernath ,District- Thane , Pin No- 421503 Measuring 512.35 Sg.Mts. Area Being Developed By M/S SAIRAJ CONSTRUCTION. Ref: MahaRERA Registration Number P51700056339. Sir, /We Mr. Darshan A. Kasture Have Undertaken Assignment Of Certifying Estimated Cost For The Subject Real Estate Project Proposed To Be Registered Under (Maha RERA No.P51700056339), Of The Project Of "Om Guru Krupa Co-Op Housing Society Ltd". Building Of The Single Phase Project Situated On The Survey No-20, Hisaa No -7/8 Plot No-10 Division-Konkan Village - Kulgaon Taluka - Ambernath ,District- Thane,Pin No- 421503 Measuring 512.35 Sq.Mts. Area Being Developed By M/s SAIRAJ CONSTRUCTION. stitute indian Authorised Sigrature Darsha Kasture Office 1: 102,Radheya Paradise, Pokharkar Nagar, Badlapt Wa 421 503, Office 2: Gala No 6, fourth Floor , building B1,Gami Industrial Park, Pawne MIDC Turbhe, Navi Mumbai,PIN 400 710,State: Maharashtra - email ID :saadengineer2223 @gmail.com SAIRAJ CONSTRVCTION CGARTNER 1. Following technical professionals are appointed by the Owner: (0 Mr.Bhupendra Mhase &Associates As L.S. Architect. Mr. Darshan kasture as Structural Consultant. (ii) Miss. Anjali Siddhartha Bharhe as MEP Consultants. (iv) Mr. Sanchit Sandanand Mhase as Site Supervisor. 2. We have estimated the cost of the completion to obtain Ocupation Certificate/ Completion Certificate, of the Civil, MEP and Allied works, of the Building(s) of the Project. Our estimated cost calculations are based on the Drawings/plans made Available to us for the project under reference by the Developer and Consultants and the Schedule of items and quantity for the entries work as calculate by Mr. Sanchit Sandanand Mhase quantity Surveyor* appointed by Developer/Engineer, and the Assumption of the cost material, labour and other inputs made by developer, and the site inspection carried out by us. 3 We estimate Total Estimated Cost of completion of the building(s) of the aforesaid Project under reference as Rs 5,25,00,000 /-(Total of Table A and B.). The Estimated Total Cost of project is with reference to the Civil, MEP and allied works Required to be completed for the purpose of obtaining occupation certificate /Completion certificate for the building(S) from the Kulgaon Ballarpur Municjpal Council being the Planning Authority under whose jurisdiction the aforesaid project is being implemented. 4. The Estimated Cost Incurred tilldate is calculated at Rs 4,54,50,000/- [total of table A and B). The amount of estimated cost Incurred is calculation on the base of amount of Total estimated Cost. 5. The Balance cost of Completion of the Civil, MEP and Allied works of the Building(s) of the subject project to obtain Occupation Certificate /Completion Certificate from Kulgaon Badlapur Municipal Council is estimated at Rs.70,50,000/-(Total of Table A and B). 6. I cetify that the Cost of the Civil, MEP and allied work for the aforesaid Project as Completed on the date of this certificate is as given in Table A and B below. Yours faithfully, Institute Authorised \ Sigraturs Darshan Kasture ine r DARSHANA. KASTURE IEl.M.147058-7 147058 SAJRAJCONSTRUCTION PARTNER TABLE A Sr. No Particulars Amount TotalEstimated cost of the building/Wing Rs. 5,05,00,000/ As on 31/03/2026 date of Registration is 2 Cost incurred as on 31/03/2026 Rs. 4,54,50,000/ (Based on the estimated cost) 3 Work done in Percentage 90% (as Percentage of the estimated cost) 4 Balance Cost to be Incurred Rs.50,50,000/ (Based on Estimated Cost) 5 Cost Incurred on Additional/Extra Items NIL As on 31/03/2026 not included in The Estimated Cost (Annexure A) stitute Yours faithfully, SAIRAJ CONSTRUCTION 1g1ner DARSHĂŇ A. KASTURE IEl.M.147058-7 PARTNER TABLE B Sr. No Particulars Amount 1 Total Estimated cost of the Internal and External Rs.20,00,000/ Development Work including amenities and Facilities in the layout as on 31/03/2026 Date of Registration is NIL Cost incurred as on 31/03/2026 (based on the Estimated cost) Work done in percentage 0% (as Percentage of the estimated cost) 4 Balance Cost to be Incurred Rs. 20,00,000/ (Based on Estimated Cost) Cost Incurred on Additional / Extra Items NIL 5 As on 31/03/2026 not included in The Estimated Cost (Annexure A) Yours faithfully, Institute Authorised Signature Darshan DARSHAN A. KASTURE Kasture IEI.M.147058-7 753 SAIRAJ CONSTRUCTION PARTNER Limitation :-there by confirmand state that I have done the calculation based on the information and data available as per market condition and a guideline given by the promoters. In case of any fluctuations in the amount given in this certification by the government authority it is compulsion to follow the same and do the needful correction in Amount. Local Authority License No.: IEl.M.147058-7 Agreed and Accepted by: Signature of Promoter SAIRAJ CONSTRUCTION Name: Date: PARTNER Note: 1. The scope of work is to complete entire Real Estate Project as per drawings approved from time to time so as to obtain Occupation Certificate /Completion Certificate. 2. (*)Quantity survey can be done by office of Engineer or can be done by an independent Quantity Surveyor, whose certificate of quantity calculated can be relied upon by the Engineer. In case of independent quantity surveyor being appointed by Developer, the name has to be mentioned at the place marked (*) and in case quantity are being calculated by office of Engineer, the narme of the person in the office of Engineer, who is responsible for the quantity calculated should be mentioned at the place marked (*). 3. The estimated cost includes all labor, material, equipment and machinery required to carry out entire work. 4. As this is an estimatedcost, any deviation in quantity required for development of the Real estate Project will result in amendment of the cost incurred/to be incurred. 5. All components of work with specifications are indicative and not exhaustive 6. Please specify if there are any deviation/qualifications. Example: Any deviation in input material used from specification in agreement of sale. Table C List of Extra/Additional/Deleted Items considered in cost (Which were not part of the original Estimate of Total cost) Sr. No. List of Extra Additional / Deleted Items Amount (In Rs.) Cost Incurred on Additional/Extra ltems NIL SAIRAJ CONSTRUCTION PARTNER Tndia 7958