Date:-30/09/2025 ARCHITECT'S CERTIFICATE To, M/S SAIRAJ CONSTRUCTION Through It’s Partner Mr. Dattatray Walku Mhase Mr. Mahesh Janardhan Vishe 303, Krupasindhu Building, Opp. Mahalaxmi Mandir, Near Bus Depot, Badlapur (W), Dist – Thane 421503. Subject: Certificate of Percentage of Completion of Construction Work of “Om Guru Krupa Co- Op Housing Society Ltd.”. having MahaRERA Registration Number P51700056339 being developed by M/S SAIRAJ CONSTRUCTION. Sir, I am Ar. Bhupendra Dattatrey Mhase, have undertaken assignment as Architect of certifying Percentage of Completion of Construction Work of the “Om Guru Krupa Co-Op Housing Society Ltd.” having MahaRERA Registration Number P51700056339 being developed by M/S SAIRAJ CONSTRUCTION. (i) Ar. Bhupendra Mhase & Associates (Ar. Bhupendra Mhase) as a L.S./Architect (ii) Saad Consultant (Mr. Darshan Kasture) as Structural Consultant (iii) Miss. Anjali Siddharth Bharhe as MEP Consultant (iv) Mr. Sanchit Sandanand Mhase as Site Supervisor Based on Site Inspection, with respect to the Building of the aforesaid Real Estate Project, I certify that as on the date of this certificate, the Percentage of Work done for building of the Real Estate Project is as per table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. TABLE – A S+6th Floor Sr. No Tasks /Activity Percentage of work done 1 Excavation work has been completed 100% 2 Basement N.A. 3 Podiums N.A. 4 Plinth work has been completed 100% 5 Stilt Floor work has been completed 100% 6 Number of Slabs of Super Structure 100% 7 Internal walls has been Completed, Internal Plaster work is 35% in progress, Floorings, Doors and Windows to each of the Flat/ Premises 8 Sanitary Fittings within the Flat/Premises, 10% 9 Staircases, Lifts Wells and Lobbies at each Floor level 70% Overhead and Underground Water Tanks 10 External plumbing and external plaster work is in 5% progress, plaster, elevation, completion of terraces with waterproofing of the Building/ Wing, 11 Installation of lifts, water pumps, Fire Fighting Fittings and 10% Equipment as per CFO NOC, Electrical fittings work is in progress, mechanical equipment, Compliance to conditions of environment /CRZ NOC, finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specification in agreement of Sale. Any other activities. TABLE - B Internal & External Development Works in Respect of the entire Registered Phase Sr. Common areas and Facilities, Proposed Percentage Details No Amenities (Yes/No) of Work done 1 Internal Roads & Footpaths No 0% N.A. 2 Water Supply Yes 0% Work not start yet 3 Sewerage (chamber, lines, Yes 0% Work not start yet Septic Tank , STP) 4 Storm Water Drains No 0% N.A. 5 Landscaping & Tree Planting No 0% N.A. 6 Street Lighting No 0% N.A. 7 Community Buildings No 0% N.A. 8 Treatment and disposal of No 0% N.A. sewage and sullage water 9 Solid Waste management & No 0% N.A. Disposal 10 Water conservation, Rain water No 0% N.A. harvesting 11 Fire protection and fire safety No 0% N.A. requirements 12 Electrical Meter Room, Sub Yes 0% Work not start yet Station, Receiving Room 13 Open Parking No 0% N.A. Agreed & accepted by: Yours Faithfully Signature of Promoter Name: Ar.Bhupendra Mhase Date: Architect Consultant Licence No- CA/2020/118792