Annexure A FORM 1 [see Regulation 3] ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account) Date: 30-06-2025 To, BLISSFUL BUILDCON LLP THANE, MAHARASHTRA, 421302 Subject : Certificate of percentage of Work of completion of construction work of JOGANI PRIDE having MahaRERA Registration Number P51700055327 (Only Applicable after project Registartion) being developed by BLISSFUL BUILDCON LLP Sir, I/We H K DESIGN CONSULTANTS have undertaken assignment as Architect /Licensed Surveyor of certifying Percentage of completion of Construction Work of JOGANI PRIDE having MahaRERA Registration Number P51700055327 (Only Applicable after project Registration, being developed by BLISSFUL BUILDCON LLP ) Based on Site Inspection,with respect to Layout / each of the Building/Wing of the aforesaid Real Estate Project I certify that as on the date of this certificate, the Percentage of Work done for each of the building/Wing of the Real Estate Project under MahaRERA is as per Table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. Table A Layout/Building/Wing Number: JOGANI PRIDE/NA Sr. No. Tasks/Activity Percentage of Actual Work Done (As on date of the Certificate) (1) (2) (3) 1 Excavation 100.00 2 Basements (if any) 100.00 3 Podiums (if any) 0.00 4 Plinth, 100.00 5 Stilt Floor 0.00 6 Slabs of Super Structure 3.00 7 Internal walls, Internal plaster, Floorings, Floors and windows within 0.00 Flats/Premises Page 1 of 3 8 Sanitary Fitting within the Flat/Premises 0.00 Sr. No. Tasks/Activity Percentage of Actual Work Done (As on date of the Certificate) 9 Staircases, lifts Wells and Lobbies at each Floor level Overhead and 13.63 Underground Water Tanks 10 External plumbing and external plaster, elevation, completion of terraces with 0.00 waterproofing of the Building/wing. 11 Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per 0.00 CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions of environment/CRZ NOC, Finishing to entrance lobby/s, plinth protection,paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. Any other activities. Page 2 of 3 Table B - Common Areas (Internal and External Development Works) in respect of Registered Phase / Project Number) Sr.No Common areas and facilities Proposed Percentage of Actual Details (Yes / No) Work Done (As on date of the Certificate) (1) (2) (3) (4) (5) 1 Internal Roads & Footpaths No 0.00 NA 2 Water Supply Yes 0.00 NA 3 Sewerage (Chamber, Lines, Septic Tank , STP) Yes 0.00 NA 4 Storm Water Drains Yes 0.00 NA 5 Landscaping & Tree Planting No 0.00 NA 6 Street Lighting No 0.00 NA 7 Community Buildings No 0.00 NA 8 Treatment And Disposal Of Sewage And Sullage Water No 0.00 NA 9 Solid Waste Management And Disposal No 0.00 NA 10 Water conservation /Rain water harvesting Yes 0.00 NA 11 Energy managemcnt No 0.00 NA 12 Fire protection and fire safety requirements Yes 0.00 NA 13 Electrical meter room, sub-station, receiving station No 0.00 NA 14 Aggregate area of recreational Open Space No 0.00 NA 15 Open Parking No 0.00 NA Yours Faithfully H K DESIGN CONSULTANTS Signature & Name (IN BLOCK LETTERS) of L.S/ Architect ( License No: STATE/R/2025/APL/16598) Date of Certificate: 30-06-2025 Agreed and accepted by: Signature of Promoter Name: BLISSFUL BUILDCON LLP Date:30-06-2025 Page 3 of 3