ENTECH ENGINEERS Talao"Milap Nauar, M.l-8. C , , t, i , '1. :. FORM-2 [see Regulation 3] ENGINEER'S CERTIFICATE {To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account- Project wise) Date: 15.07.2024 To M/s. Radhika Construction Company RP26, Near GanpatiVisarjan Talao, MIDC, Milapnagar, Dombivli East. Pin- 421203. Subject: Certificate of Cost Incurred for Development of TRINITY (Shashank Saptshrung.l By 'Radhika Construcdon Company." for Construction of building, situated on the on plot bearing C.T.S. nos.3o84, Surve no.65, Hissa No 5. Situated at Mouje Dombivli, Dombivli West, Taluka Kalyan, Dist - Thane, Sir, We have undertaken assignment of certifying Estimated Cost for the Subiect Real Estate Project Maha REM, Registration No -P5170fi)55300, ln the Name "TRIN|TY (Shashank Saptshrung.) situated on the on plot bearing C.T.S. nos.3084, Surve no.65, Hissa No 5. Situated at Mouje Dombivli, Dombivli West, Taluka Kalyan, Dist -Thane, being developed by M/s. Radhika Construction Company. Following technical professionals are appointed by Owner / Promoter: - (a) M/s/Shri Ankur Shetye as L.S. / Architec$ (ii) M/s /S,hri Girlsh.S. Marathe as Structural Consultant; (iii) M/s /Shri Mandar Padhye as MEP Consultant (iv) M/s /Shri / as quantity Surveyor * We have estimated the cost of the completion to obtain Occupation Certificate/ Completion cost Certificate, of the Civil, MEP and Allied works, of the buildings of the project. Our estimated calculations are based on the Drawingslplans made available to us for the project under reference by the Developer and Consultants and the Schedule of items and quantity for the entire work as calculated by Shri Girish.S. Marathe as Struchral Consultant Quantity Surveyor*appointed made by by Developer / Engineer. The assumption of the cost of material. labour and other inputs confirm the above analysis given developer. and the site inspection carried out by us to ascertain / to us. project under 3. We estimate Total Estimated Cost of completion of the building(s) of the aforesaid project is reference as Rs.1G,19,61,143.0O (Total of Table A and B). The estimated Total Cost of with reference to the Civil, MEp and allied works required to be completed for the purpose of obtaining occupation. 4. On certificate 1 comptetion certificate for the buildings from the Kalyan llombivli Municipal project is being Corporation being the planning Authority under whose jurisdiction the aforesaid implemented. 5. The Estimated Cost tncurred tall3OlOGl2O24 is calculated at Rs. 1,08,83,803.00 Total of Table A and B). The amount of Estimated Cost lncurred is calculated on the base of amount of Total Estimated Cost. 6. The Balance cost of Completion of the Civil, MEP and Allied works of the building(s) of the subject projectto obtain occupation Certificate / Completion Certificatefrom Kalyan [lombivll Munidpal Corporatlon (planning Authority) is estimated Rs.15,1O77,3{t.00 (Total of Table A and B}. 7- I certify that the Cost of the Civit, MEP and allied work for the aforesaid Proiect as completed on the date of this certificate is as given in Table A and B below: TABLE A Building /Wing bearing Number- or called 'TRNITY (shashank Saptshrunt')' Cost for altotted flats to society members by Radhika Construstion Company Promoter (To be prepared separately for each Building /Wing of the Real Estate Project) Sr. No Particulars Amounts Total Estimated cost of the building Rs 16,19,61,143.00 as on- date of Registration is 2 Cost incurred as on 3O/OG|2O24. Rs. 1,08,83,803.00 (Based on the Estimated cost) 3 Work done in Percentage 5.72% (As Percentage of the estimated cost) 4 Balance Cost to be lncurred Rs 15,10,77,340.m (Based on Estimated Cost) Cost lncurred on Additional /Extra ltems Rs. Nil as on not included in the Estimated Cost (Annexure A) TABLE B (lnternal & External Development Works in respect of Registered Phase) Sr. No Particulars Amounts Total Estimated cost of the lnternal and External Rs Nil Development Work including amenities and Facilities in the layout as on date of Registration is-. 2 Cost incurred as on 3010612024- Rs. Ni! (Based on the Estimated cost) 3 Work done in Percentage (As Percentage of the estimated cost) Balance Cost to be lncurred Rs Nil (Based on Estimated Cost) Cost lncurred on Additional/Extra ltems Rs. - Nil ason- not included in the Estimated Cost (Annexure A) e-J Yoyrpraith{Yrry GIRISH S. MARATHE prg^re.I ,g- Accq{ /A \"2 sTRUcTURAL coilsuLTAt{u K.D.it.C.Liccnm ilo.tl9$ For MDllItrA G0XSTll Signature of Engineei ii ,l I (structuraI Engineer- 495) t;Timn * Note L. The scope of work is to complete entire Real Estate Projest as per drawings approved from time to time so as to obtain Occupation Certificate /Completion Certificate' Z. (*) euantity survey can be done by office of Engineer or can be done by an independent Quantity Surveyor, quantity whose certificate of quantity calculated can be relied upon by the Engineer. ln case of independent place marked (*) and in case surveyor being appointed by Developer, the name has to be mentioned at the quantity are being calculated by office of Engineer, the name of the person in the office of Engineer, who is responsible for the quantity calculated should be mentioned at the place marked (*). 3. The estimated cost includes all labour, material, equipment and machinery required to carry out entire work' 4. As this is an estimated cost, any deviation in quantity required for development of the Real estate Project will rosult in amendment of the cost incurred/to be incurred' S. All components of rvsrk wit*r speeifications are indieative and not exhaustive' Annexure A List of Extra / Additional ltems executed with Cost (Which were not part of the original Estimate of Total Cost)