§9 lele building better future mandar jayant lele Ref No- ML/2024-25/069 Date- 20.07.2024 Annexure-A FORM-1 CONSULTING ENGINEER'S CERTIFICATE To, The M/s. Nirmiti Builders & Developers Through Its Partner. Mr. Vishal Vijay Patil Add:- 209, Konark Arcade, Beside BNCMC Head, opp. Tahsildar Office, Tai- Bhiwandi, Dist.-Thane. Subject : Certificate of Percentage (Upto 30th Jun 2024) of Completion of Construction Work of Residential/Commercial (Stilt/GR+ 4 Floor) Project Name SURAJ ORCHID Land bearing on Surve. No. 115/6/116/3/A/ Plot No.3, Mouje Asangaon, Taluka Shahapur, District Thane. having Maha RERA Registration Number PS1700055323 being developed by M/s. Nirmiti Builders & Developers Sir. I Mr. Mandar Jayant Lele have undertaken assignment as Consulting Engineer of certifying Percentage of Completion of Construction Work of SURAJ ORCHID having Maha RERA Registration Number P51700055323 being developed by M/s. Nirmiti Builders & Developers, Based on Site Inspection, with respect to Layout/ each of the Building/Wing of the aforesaid Real Estate Project. I certify this certificate upto 30th Jun 2024 (i.e. 1st Apr 2024 to 30th Jun 2024), the Percentage of Work done for each of the building/Wing of the Real Estate Project under Maha RERA is as per Table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. TABLE-A Building Name called SURAJ ORCHID Sr.No Tasks/ Activity Percentage of Actual Work Done (Upto 30th Jun 2024) 1 Excavation 100% 2 Basements (if any) -NA- 3 Podiums (if any) -NA- 4 Plinth 100% 5 Stilt Floor - 100% /4tJav~~ 6 Slab of Super Structure . f~fi"'l :~~t, 100% ig~:7~jl ~~".°"' - ~~~ Office No. 209 & 210, 2nd Floor, Konark Arcade, Next to B N C Municipal Corporation, Opp. Tahslldar Office, Bhlwandl, Dist.- Thane - 421308 +912522 238100 I lnfo@)lelegroup.org ---------- • ~- 7 Outer Wall, Internal walls, Internal Plaster, Floorings, Doors 30% and windows within Flats/Premises. 8 Sanitary Fitting within the Flat/Premises 0% 9 Staircases. Lifts Wells and Lobbies at each Floor level 50% Overhead and Underground Water Tanks 10 External plumbing and external plaster, elevation, 0% completion of terraces with waterproofing of the Building/Wing. 11 Installation of Lifts, water pumps, Fire Fighting Fittings and 0% Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions of environment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing. Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. Any other activities. TABLE-B Common Areas (Internal and External Developments Works) In respect of the Registered Phase/ Project Number Sr.No Common Areas and Facilities Proposed Percentage Details (Yes/ of Actual No) Work Done (Upto 30th Jun 2024) 1 Internal Roads & Footpaths No -NA- 2 Water Supply Yes 0% 3 Sewerage (Chamber, lines, Septic Tank, Yes 0% STP). 4 Storm Water Drains Yes 0% 5 Landscaping & Tree Planting Yes 0% 6 Street Lighting No -NA- 7 Community Buildings No -NA- 8 Treatment and disposal of sewage and No -NA- sullage water. 9 Solid Waste management & Disposal No -NA- 10 Water conservation/Rain water YMs r;~'< J1 ~~,0% harvesting -~1/ r--!!!C. I '~ill-\'(;\ *8~ =1 - -w t ~1'll)g C\'4\\~<'- - i 11 Energy management Yes 0% 12 Fire protection and fire safety No -NA- requirements 13 Electrical meter room, sub-station, Yes 0% receiving station. 14 Others (Option to Add more). No -NA- Yours Faithfully _/ -= MANDARJAYAN~LELE t Consulting Civil Engineer Lie: No. STATE/R/2~22/APU~014~ F.ar Nlrmltl.Bullders & Developer . ~ PilUl< Agreed and Accepted By: M/s. Nirmiti Builders & Developers Through Its Partner. Mr. Vishal Vijay Patil