SAMARTHYA SAMARTHYA ENGINEERS ENGNEGAS JITENDRA S. PATEL B.E.Civil FORM 1 Date 3)-Dec-2024 [see Regulation 3] ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account) To M/S. ATREE REALTORS THROUGH IT'S PARTNER: Shri Kailas B. Mhaskar PLOT NO.1, S. NO. 73, H. NO. 4, Near Shreeji Nisarg, YERANJAD, BADLAPUR (W), PIN. - 421503 Subject: Certificate of Percentage of Completion of Construction Work of 1No. of Buildings, which is shown on sanctioned plan as "Building No. 2 of the 2D Phase forming a part of Project Named as *KRISHNA DHAM-2" having MahaRERA Registration Number- P51700055326 being developed by *M/S. ATREE REALTORS". Sir, I JITENDRA S. PATEL (SAMARTHYA ENGINEERS) have undertaken assignment as Licensed Engineer of certifying Percentage of Completion of Construction Work of the "KRISHNA DHAM-2, BLDG. NO.2", having MahaRERA Registration Number- P51700055326 being developed by M/S. ATREE REALTORS. Based on Site Inspection, with respect to Layeut/ each of the Building/Wing of the aforesaid Real Estate Project. Icertify that as on the date of this certificate, the Percentage of Work done for each of the building/Wing of the Real Estate Project as under MahaRERA is as per Table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. Contnc +91 9702401122 9 F-001, Nikanth Hills Upvan, Off Badlapur Ambernath Road, Near Shree Complex, Belavli -Badlapur (W) samarthyaengineers@gmail.conm Table -A Layout/ Building /Wing Number (to be prepared separately for each Layout/ Building /Wing of the Project) (KRISHNA DHAM-2, Building No.- 2) Percentage of Sr. Actual Work No. Task/Activity Done (As On Date of the Certificate) (1) (2) (3) 1 Excavation 100 2 One Plinth /Stilt 100 08 Number of Slabs of Super Structure 100 4 Internal Walls, external walls 100 5 Internal plaster,external plaster 20 6 Flooring, Doors & Windows within Flats / Premises 7 Sanitary Pittings within the Flat/ Premises Staircases, Lifts Wells and Lobbies at each Floor level, Overhead and Underground Water Tanks 9 The External plumbing and elevation, completion of terraces with waterproofing of the Building/Wing Installation of lifts, water pumps, fire Fighting and Equipment as per CFO, NOC, Electrical fittings mechanical equipment/ CRZ NOC, finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to building/wing, compound wall and all other requirements as may be required to complete project as per specification in agreement of Sale. Any other activities. TABLE-B Date: Common Areas (Internal & External Development Works) in Respect of the Registered Phase /Project Number Percentage of Sr. Common Areas and Facilities Proposed Actual Work done Details No. (Yes/No) (As On Date of the Certificate) (1) (2) (3) (4) (5) 1 Internal Roads & Footpaths NO N.A. TO BE 2 Water Supply YES PROVIDED BY M.J.P. 3 Sewerage (chamber Lines, Septic YES Tank,STP) 4 Storm Water Drains NO 5 Tree Planting YES 100 6 Street Lighting NO N.A. 7 Soc. Office, Community Hall, YES 50 Driver's Room Treatment and disposal of sewage NO and Sullage Water Solid Waste Management and YES Disposal RAIN WATER 10 Water Conservation, Rain Water YES 100 HARVESTING harvesting PROPOSED. 11 Energy management NO N.A. 12 FireProtection and Fire safety NO N.A. requirements 13 Electrical Meter Room YES 50 Meter Room 14 Transformer YES 100 Transformer Proposed 15 Aggregate Area of Recreational N.A. N.A. Open Space Specify if any further facility is 16 provided (other than above mentioned) Yours Faithfully Agreed and Accepted by SAMARTHYA ENGINEERS JITENDRAS. PATEL (B.E.CIVIL Signature of Promoter STATE/RI2025/APLI15590 M/S M/S. ATREE REALTORS Name : +9197024011 22 9F-001, Nilkonth Hills Upvan, Off Badlapur Ambernath Road, Near Shree Complex, Belavli - Badlapur (W) samarthyaengineers@gmail.com