ARCHITECT'S CERTIFICATE Date- 31.12.2024 To, M/S Rudraa Devlopers through Partner Mr. Namish Nandkumar Jage & Other 2 Address - Flat No 4 First Floor Arya Krushna Apartment, Near Talathi Office, Kulgaon Badlapur East, Tal-Ambernath Dist Thane. Contact No. 9881007100 Subject: Certificate of Percentage of Completion of Construction Work of Redevelopment of "LAXMIDEEP CHSL "Proposed Ground+6 Floors Residential cum Commercial building on Land Survey No 32 Hissa No 1/A Plot No 13 Village- Shirgaon Tai. Ambernath Dist. Thane having MahaRERA registration number PS1700055227 being developed by M/S Rudraa Devlopers Sir, I Sarthak Subhash Chilakwad have undertaken assignment as Architect of certifying percentage of Completion of Construction Work of Redevelopment of "L.AXMIDEEP CHSL" having MahaRERA Registration Number P51700055227 being developed by M/S Rudraa Devlopers. Based on Site inspection, with respect to layout/ each of the Building /wing of the aforesaid Real estate Project ,I certify that as on the date of this certificate, the Percentage of Work done for each of the building/Wing of the Real Estate Project under Maha RE RA is as per Table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. Email: skyvisionarchitectsOgmail.com I +91-7798129981, +91-88500458581 Address- 102, Mohfni Apartment, Ghorpade Chowk, Katrap, Badlapur [E] 421503 SKYVISION ARCHITECTS ~ Ar. Sarthak S. Chllakwacl I Ar. Akaah B. Thakre TABLE A - Redevelopment of "LAXMIDEEP CHSL" Proposed Ground-16 Floors Residential cum Commerdal building Percentage of Actual Sr. Work Done No Tasks/ Activity (As on date of the (1) (2) certificate) (3) 1 Excavation 100% 2 Basements (if any) N.A. 3 Podiums (if any) N.A 4 One number of Plinth work 100% ·5 Stilt floor 70% 6 SEVEN number of Slabs of super structure 100% [Ground+6 Floors= 7 slabs] 7 ■ Internal walls ■ Internal plaster 50% ■ Floorings ■ Doors and windows within flats/premises 8 Sanitary fittings with in flats/premises 0% 9 ■ Staircases ■ Lifts wells ■ Lobbies at each floor level 70% ■ Overhead water tanks ■ Underground water tanks 10 • External plumbing • External plaster • Elevation, 50% ■ Completion of terraces with waterproofing of the building 11 • Installation of lifts. • Water pumps, • Firefighting fittings and equipment as per CFO NOC, • Electrical fittings, ; • Mechanical equipment, • Compliance to conditions of environment/CRZ NOC. 0% • Finishing to entrance lobby/s. ■ Plinth protection , • Paving of areas appurtenant to building • Compound wall • All other requirements as may be required to complete project as per specifications In agreement of sale. ■ Any other activities. Email: skyvisionarchltectsdPonail.com I +91-7798129981, ~1-885004585~ 1 Address- 102, Mohini Apa~nt, Ghorpade Chowk, Katrap,, . . . ' ', Badlapur [E] 421503