BEFORE THE MAHARASHTRA REAL ESTATE REGULATORY AUTHORIT'Y MUMBAI. COMPLAINT NO: CC006000000012036 Anirucldha Jagdish Keer Complainant. Versus Mateshwari Realtors Respondent MahaRERA Regn; 51700010188 Coram: Hon'ble Shri Madhav Kulkarni Appearance: Complainanti Present a/w Adv Naik Respondent: C.A. Kirit Gada Final Order 21't November 2019 1. The complainant/allottee who had booked a flat with the respondent/ promoter seeks withdrawal from the project and refund of his amount with interest under Section 18 of Real Estate (Regulation & Development) Act, 2016 (RERA for the sake of brevity) as the resPondent failed to deliver possession as per agreement. 2. The complainant has alleged that he booked flat No C-804 vide agreement registered in November 2015. The name of the project and its location are missing in the complaint for the reasons best known to the complainant. In the first instance the complainant did not prorJuce the whole of the agreement. Now, it is placed on record. Accordingly, the name of the project is Mateshwari Altura and is at Khidkali, Taluka, Dist. Thane. The agteed price was Rs. 34,57,000/-. Complainant till this date paid Rs.27,65,600/-, i.e. 80%. Proposed date for completion was 31.72.201,6. It was revised to 31.12.2018 and then to 31.03.2019. Agains:__ i-o' the first demand complainant paid Rs.70,73,600/- on"l212 2015 Second demand letter was issued on April, 2016 and complainant refused to pay -As it. , clate for delivery of possession was slipped by respondent' Complainant has allege