FORM 1 ARCHITECT’S CERTIFICATE Date: 31/03/2026 To SRI BALAJI DEVELOPER, Promoter :Shri Vikram Jain, Shri Nilesh Shah Tropical Elite, Office No. 104, 1st floor, Naupada, Thane (W.) Subject: Certificate of Percentage of Completion of Construction Work of building No. Type 01B– B1 Wing (building no. 13 & 14) of the Project ATLANTA RESIDENCY PHASE 2. situated on the Plot bearing S.No. 124/5 (pt), 124/6, 124/7, 124/9, 124/10, 125/8, 125/10, (pt), 159/6, 161/5, (PT), (PLOT NO. 7,9&10), 161/8 & 161/14, 160/5 (P), Old S. No. 124/125/159/161. At Village:Kamatghar, Taluka: Bhiwandi, Dist: Thane,admeasuring 23963.80sq.mts.,area being developed by M/S SRI BALAJI DEVELOPER. (Mr. Vikram Jain) Sir, I/We Shraddha A. Paranjpe have undertaken assignment as Architect of certifying Percentage of Completion of Construction Work of the building No. Type 01 B – B1 Wing (buiding no.13 & 14) of the Project ATLANTA RESIDENCY PHASE 2. situated on the Plot bearing S. No. 124/5 (PT), 124/6, 124/7, 124/9, 124/10, 125/8, 125/10, (pt), 159/6, 161/5, (pt.), (PLOT NO. 7,9&10), 161/8 & 161/14, 160/5 (P), Old S. No. 124/125/159/161.At Village Kamatghar, Taluka:Bhiwandi, Dist: Thane, admeasuring 23963.80sq.mts. Area being developed by M/S SRI BALAJI DEVELPOR. (Mr. VikramJain) 1. Following technical professionals are appointed by Owner / Promoter:- (i) Smt.SHRADDHA A PARANJPE(Navrachana) as Architect Consultant (ii) MR. AJAY MAHALE (DSS_Consultants)as Structural Consultant Based on Site Inspection, with respect to each of the Building of the aforesaid Real Estate Project,I certify that as on the date of this certificate, the Percentage of Work done for each of the building of the Real Estate Project as registered vide number under RERA is as per table A herein below. The percentage of the work executed with respect to each of the major activity of the Building / Wing and Overall Percentage of the work done with respect to each Building / Wing is detailed in the Table B. Digitally signed by Shraddha Shraddha Aniruddha Paranjpe Aniruddha Paranjpe Date: 2026.04.11 16:25:11 +05'30' Table A ATLANTA RESIDENCY PHASE 2 Building No. Type 01 B Wing (Building No. 13) Sr.No Tasks / Activity Percentage 1 Excavation 100% 2 1 Number of Plinth 100% 3 0 Number of Podiums 0% 4 Stilt Floor 100% 5 Slabs of Super Structure [Lower gr.+ Upper gr. + 1 st to 85% 15th flr ] 6 Internal Walls,Internal Plaster,Floorings Within Flats, 10% Doors and windows to each of the flat/Premises 7 Sanitary Fitting within the Flats / Premises- Electrical 0% Fitting within the Flats / Premises, 8 Staircases, Lifts Wells and Lobbies at eachFloor level 0% connecting Staircases and LiftsOverhead and Underground Water Tanks 9 The External Plumbing and External 0% Plaster,Elevation,Completion of terraces with Waterproofing of the Buidding 10 Installation of lifts, waterpumps, Fire Fighting and 0% Equipment as per CFO NOC,Electrical fittings to common areas, electro, mechanicalequipment’s,compliance to conditions of environment /CRZ,NOC,finishing of entrance lobby, Plinthprotection, paving of area apparent to building, Compound wall and all other Requirements as may be required to obtain Occupation/Completion Certificate Shraddha Digitally signed by Shraddha Aniruddha Aniruddha Paranjpe Date: 2026.04.11 16:25:27 Paranjpe +05'30' Table A ATLANTA RESIDENCY PHASE 2 Building No. Type 01 B1 Wing (Building No.14) Sr.No Tasks / Activity Percentage 1 Excavation 100% 2 1 Number of Plinth 100% 3 0 Number of Podiums 0% 4 Stilt Floor 100% 5 Slabs of Super Structure [Lower gr.+ Upper gr. + 1 st to 85% 15th flr ] 6 Internal Walls,Internal Plaster,Floorings Within Flats, 10% Doors and windows to each of the flat/Premises 7 Sanitary Fitting within the Flats / Premises- Electrical 0% Fitting within the Flats / Premises, 8 Staircases, Lifts Wells and Lobbies at eachFloor level 0% connecting Staircases and LiftsOverhead and Underground Water Tanks 9 The External Plumbing and External 0% Plaster,Elevation,Completion of terraces with Waterproofing of the Buidding 10 Installation of lifts, waterpumps, Fire Fighting and 0% Equipment as per CFO NOC,Electrical fittings to common areas, electro, mechanicalequipment’s,compliance to conditions of environment /CRZ,NOC,finishing of entrance lobby, Plinthprotection, paving of area apparent to building, Compound wall and all other Requirements as may be required to obtain Occupation/Completion Certificate Shraddha Digitally signed by Shraddha Aniruddha Aniruddha Paranjpe Date: 2026.04.11 Paranjpe 16:25:42 +05'30' TABLE – B Internal & External Development Works in Respect of the project S. No. Common Roads and Facilities, Proposed (Yes/No) Percentage Details Amenities of Work done 1 Internal Roads And Footpaths NO N.A N.A. 2 Water Supply YES 0% Municipal Corporation Supply 3 Sewerage (chamber, sewage lines), YES 0% Septic Tank Storm Water Drains 4 Storm Water Drains YES 0% Surface Drain System 5 Landscaping & Tree Planting NO N.A. N.A 6 Street Lighting NO N.A. N.A 7 Community Buildings NO N.A. N.A 8 Treatment and disposal of Sewage NO N.A. N.A and Sullage Water 9 Solid Waste Managment & Disposal YES 0% WIP 10 Water Conservation,Rain Water YES 0% Rain Water Harvesting Harvesting Pits 11 Energy managment YES 0% Solar water Heating System 12 Fire Protection and Fire Safety YES 0% As per CFO Requirments NOC 13 Electrical meter Room,Sub-Station YES 0% As per Torrent Receivng Station Power NOC 14 Others(Option to Add More) NA N.A. Yours Faithfully Shraddha Digitally signed by Shraddha Aniruddha Paranjpe Aniruddha Date: 2026.04.11 16:25:56 Paranjpe +05'30' SHRADDHA A PARANJPE (License No. CA/2008/41812) Agreed and Accepted by:- Digitally signed by Name : Vikram Jain NILESH NILESH KANTILAL SHAH KANTILAL SHAH Date: 2026.06.01 Date : 31/03/2026 15:42:10 +05'30'