/ 2ND FLOOR, NAKSHATRA, WING A, NEAR TMC, ALMEIDA ROAD, PANCHPAKHADI, THANE (W) - 400 601 TEL.: (022) 2537 8701/2536 4700' saakaararchitects@yahoo.co.in • saakaar@saakaar.co.in ARCHITECTS • FORM 1 ARCHITECT'SCERTIFICATE 31/3/2021 To M/s. Bright Sky Heights Builders & Developers Pvt. Ltd., 59/1A, GO/1, GO/2A, 2B, Near Millennium Toyota Showroom, village Padale, Kalyan Shil Road, Thane - 421204. Subject: Certificate of Percentage of Completion of Construction Work of Residential cum Commercial building type C (Wing 5) of the 2nd Phase of the Project [MahaRERA Registration Number (P51700009788)] situated on the Plot bearing Survey No. 59/1A + 2B, 59/18, 60/1, 60/2A, 28, 61/1, 61/4, 61/5, 62, 67, demarcated by its boundaries (latitude 'and longitude of the end points) 19°9'6.31 "N, 73°3'15.27"E to the North west, 19° 9'7.43"N, 73°3'21.17"E to the North East, 19° 9'2.76"N, 73° 3'21.S0"E to the South East, 19°9'l.07"N, 73°3' 19.62"E to the South West of Division Konkan village Padle, Tal. & Dist. Thane admeasuring 15779.62 sq.m. area being developed by M/s. Bright Sky Heights Builders & Developers Pvt. Ltd. Sir, I Makarand Parange, Partner M/s. SAAKAAR have undertaken assignment as Architect /Licensed Surveyor of certifying Percentage of Completion of Construction Work of the Residential cum Commercial building C (Wing 5) of the 2nd Phase of the Project [MahaRERA Registration Number P51700009788] situated on the Plot bearing Survey No.S9/1A + 2B, 59/18, 60/1, 60/2A, 28, 61/1, 61/4, 61/5, 62, 67 village Padle, Tal. & Dist. Thane admeasuring 15779.62 sq.mts. area being developed by M/s. Bright Sky Heights 8uilders & Developers Pvt. Ltd. Following technical professionals are appointed by Owner / Promoter:- (i) M/s SAAKAARas an Architect (ii) Mr. R.C. Tipnis as Structural Consultant (iii) Engineering Creations Public Health Consultancy Pvt. Ltd. as MEP Consultant. (iv) Shri. Ranganathan Acharya as Site Supervisor. .. Page I 1 , Based on Site Inspection, with respect to each of the Building/Wing of the aforesaid Real Estate Project, I certify that as on the date of this certificate, the Percentage of Work done • for each of the building/Wing of the Real Estate Project as registered vide number (P51700009788) under MahaRERA is as per table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. TABLE-A Building /Wing Number 5 , Sr. Tasks/Activity Percentage of No. work done 1 Excavation 100% 2 1 number of Plinth (Stilt) 100% 3 o number of Podiums NA 4 17 number of Slabs of Super Structure 90% 5 Internal wa lis, Internal Plaster, Floorings within Flats/Premises, 19% Doors and windows to each of the Flat/Premises. 6 Sanitary fittings within the Flat/Premises, Electrical Fittings 0% within the Flat/Premises 7 Staircase, Lifts Wells and Lobbies at each floor level connecting 55% Staircases and Lifts, Overhead and Underground Water Tanks 8 The external plumbing and external plaster, elevation, 33% completion of terraces with waterproofing of the Building/Wing 9 Insta IIation of lifts, water pumps, Fire Fighting Fitti ngs and 0% Equipment as per CFO NOC, Electrical fittings to common Areas, electro, mechanical equipment, Compliance to conditions of environment/CRZ NOC, Finishing to entrance lobbv/s, plinth protection paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate. Page I 2 , , """') TABLE-B Internal & External Development Works in Respect of the entire Registered Phase • S. Common areas and Facilities, Proposed Percentage of Details No Amenities (Yes/No) Work done 1. Internal Roads & Footpaths Yes 100% Work Completed 2. Water Supply Yes 0% Water connection will be given by Thane Municipal Corporation after Occupation Certificate. 3. Sewerage (chamber, lines, Yes 35% Work in progress. • Septic Tank) 4. Storm Water Drains Yes 0% Work to commence. 5. Tree Planting Yes 0% As per Tree Authority requirement. 6. Street Lighting No NA 7. Community Buildings No NA 8. Treatment and disposal of Yes 100% Work Completed. sewage and sullage water 9. Solid Waste management & Yes . 0% Organic waste composter for on Disposal site composting of biodegradable waste is provided. Output will be . used as manure and work completed. 10. Water Conservation, Rain Yes 0% Work to commence water harvesting 11. Energy management Yes 0% Solar water heaters to be installed before Occupation Certificate. 12. Fire Protection and fire safety Yes 0% Work to commence requirements 13. Electrical meter room, sub- Yes 0% Work to commence station, receiving station 14. Open Parking Yes 0% Work to commence 15. Club House Yes 15% Work completed upto plinth. Yours Faithfully For SAAKAAR Page I 3