Al i m F o u zi (B. E. Ci vi l ) Fouzi & Associates Consulting Licensing & Planning engineer Office: 101 & 102, 1st Floor, Konark Arcade, Beside new Municipal Corporation, Opp. Tahsildar Office, Bhiwandi – 421302. Email: fouziandassociates@gmail.com Ref Date:15/11/20 24 FORM 1 ARCHITECT'S CERTIFICATE To Moonshine Realtors Pvt. Ltd. B-909, Central Tower, Kohinoor Square, Near Shiv-Sena Bhavan, Dadar-W, Mumbai. Subject: Certificate of Percentage of Completion of Construction Work of Saniya Heights having Maha RERA R e g i st r a t i o n N um b e r P51700008927 situated on the Plot Bearing/CTS/Survey/Final Plot No.: PLOT NO. 14, 15, 19, 20 ,21, 22, 23, 24 CTS NO. 4037 P, 4039 P, S. NO. 32/2, 36/2, 36/3, 37, 38, 74/3, demarcated by its boundaries (latitude 19.31295 and longitude 73.071096 of the points) CTS no.- 4036 to the North, DP Road 24.0 meter to the South, CTS no.- 4038 & 4033 to the East ,CTS no.-4039/P & 4035 to the West of village Nizampur taluka Bhiwandi District Thane PIN 421302 admeasuring 6865.13 sq.mts. area being developed by Moonshine Realtors Pvt. Ltd. Sir, I/ We Alim A.K. Fouzi have undertaken as an Architect assignment of Certificate of Percentage of Completion of Construction Work of single Building 2 Wings of the 1st Phase of the Project SANIYA HEIGHTS (MahaRERA Registration No. P51700008927) situated on the Plot No. 14, 15,19, 20, 21, 22, 23, 24 CTS No. 4037 (P), 4039 (P), S. No. 32/2, 36/2, 36/3, 37, 38, 74/3 demarcated by its boundaries ((latitude 19.31295 and longitude 73.071096 of the points) CTS no.- 4036 to the North, DP Road 24.0 meter to the South, CTS no.- 4038 & 4033 to the East ,CTS no.-4039/P & 4035 to the West of village Nizampur taluka Bhiwandi District Thane PIN 421302 admeasuring 6865.13 sq.mts. area being developed by Moonshine Realtors Pvt. Ltd. Following technical professionals are appointed by Owner/Promoter (as applicable):  Alim A.K.Fouzi : Architect/Licensed Engineer  Z.Z.Consultants : Structural Consultant  Lah Green India Pvt. Ltd. : MEP Consultant  Momin Hunaif Niyaz : Site Supervisor Based on Site Inspection by undersigned on 30/09/2024 date with respect to each of the Building/Wing of the aforesaid Real Estate Project, I certify that as on the date of this certificate, the percentage of Work done for each of the building/Wing of the Real Estate project as registered vide number – P51700008927 under MAHARERA is as per table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table A and B. Al i m F o u zi (B. E. Ci vi l ) Fouzi & Associates Consulting Licensing & Planning engineer Office: 101 & 102, 1st Floor, Konark Arcade, Beside new Municipal Corporation, Opp. Tahsildar Office, Bhiwandi – 421302. Email: fouziandassociates@gmail.com Ref Date:15/11/20 24 Based on Site Inspection by undersigned on 30/09/2024 date with respect to each of the Building/Wing of the aforesaid Real Estate Project, I certify that as on the date of this certificate, the percentage of Work done for each of the building/Wing of the Real Estate project as registered vide number – P51700008927 under MAHARERA is as per table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table A and B. TABLE-A Building – 01 (Wing – A & B) Sr. Tasks / Activity Percentage of Percentage of No. Work Done Work Done Wing A Wing B 100 100 1 Excavation 100 100 2 1 number of Basement and Plinth NA NA 3 Number of Podiums 100 100 4 Stilt Floor 100 100 5 16 number of Slabs of Super Structure Internal walls, Internal Plaster, Floorings 85 85 6 within Flats/Premises, Doors and Windows to each of the Flat/Premises. 50 50 7 Sanitary Fittings within the Flat/Premises Staircases, Lifts Wells and Lobbies at 90 90 8 each Floor level Overhead and Underground Water Tanks External plumbing and external plaster, 70 70 9 elevation, completion of terraces with waterproofing of the BuildingiWing, 35 35 Installation of Lifts, water pumps, Electrical fittings to Common Areas, electro, mechanical equipment, Finishing to entrance lobby/s, plinth 10 protection, paving of areas appurtenant to Building, Compound Wall and all other requirements as may be required to Obtain Occupation/Completion Certificate. Al i m F o u zi (B. E. Ci vi l ) Fouzi & Associates Consulting Licensing & Planning engineer Office: 101 & 102, 1st Floor, Konark Arcade, Beside new Municipal Corporation, Opp. Tahsildar Office, Bhiwandi – 421302. Email: fouziandassociates@gmail.com Ref Date:15/11/20 24 TABLE-B Internal and External Development Works in respect of the Registered Phase Sr. No. Common areas and Facilities Amenities Proposed Percentage of Actual Work (Yes /No) Done 1. Internal Roads & Footpaths No NA 2. Water Supply Yes 50% 3. Sewerage (Chamber, lines, Septic Tank, SIP). Yes 30% 4. Storm Water Drains Yes 20% 5. Landscaping & Tree Planting Yes 25% 6. Street Lighting Yes 00% 7. Community Buildings No NA Treatment and disposal of sewage and sullage 8. No NA water/STP 9. Solid Waste management &Disposal No NA Water conservation / Rain water harvesting, 10. Yes 00% Percolating Well/Pit. 11. Energy management No NA 12. Fire protection and Fire safety requirements Yes 30% Electrical meter room, sub-station, Receiving 13. Yes 00% Station. 14. Fire Fighting Facilities Yes 20% 15. Drinking Water Facilities No NA 16. Emergency Evacuation Services No NA 17. Use of Renewable Energy No NA 18. Security using CCTV Surveillance. No NA 19. Latter Box No NA Yours Faithfully, Alim A.K.Fouzi