BEFORE THE MAHARASHTRA REAL ESTATE REGULATORY AUTHORITY MUMBAI COMPLAINT NO: CC006000000000703 Pradeep Rawat ... Complainant COMPLAINT NO: CC006000000012673 Chandragupta Maurya Complainant COMPLAINT NO: CC006000000012804 Anil Kumar Singh Sandeep K. Vanmali Sivasubramania Raja Gaurishankar Gupta Complainants Versus RNA Corporation Pvt. Ltd. Respondent MahaRERA Regn.No. P51700008296 Coram: Shri. Gautam Chatterjee, Chairpersoru MahaRERA Complainants were represented by Mr. Charudatta Dhamapurkar, Adv. Respondent was represented by Mr. Subit Chakrabarti, Adv. and Mr. Samir Chikhaikar. Order 27th February 2018 1. The Complainants have purchased apartments, in the Respondent's project titled as 'RNA Viva' situated at Mira Road (East), Dist. Thane and registered with MahaRERA with Registration No. P51700008296 through registered agreements. The registered agreements do not bear any possession date. However, the Complainants alleged that the date of possession comrnurricated by the Respondent, separately, was December 2016. Further, the Complainants alleged that till date the Respondent has neither handed over the possession nor given any compensation. t/2 2. The advocate for the Respondent explained that there has been no delay in accordance with the terms and conditions of the registered agleements for sale. The inability to complete the project and hand over possession of the said apartment, till date, has been due to mitigating cireumstances beyond the control of the Respondent and which are well stipulated for in the said agreement. 3. On review of the respondent's MahaRERA registration it is observed that the respondent has put 31"t July 2018 as the revised proposed date of compietion and the Respondent committed to handing over possession of the said apartments on or before 31* July 2018. The Complainants agreed to the date of possession of 31* July 2018. 4. In view of the above facts, the Respondent is directed to handover the possession of the said apartment to the Complainants on or before 31't July 2018, with OC, failing which the Respondent shall be liible to pay interest to the Complainants from August 1, 2018 till the actual date of possession, on the entire amount paid by the Complainants to the Respondent. The said interest shall be at the rate as prescribed under Rule 18 of the Maharashtra Real Estate (Regulation and Development) (Registration of Real Estate Projects, Registration of ReaI Estate Agents, Rate of Interest and Disclosures on Website) Rules, 2017. 5. Consequently, the matter is hereby disposed of. Chatterjee) Chairper MahaRERA 2/2