SHARAD SONAWANE (D.C. E.) Address: Sagar Laxmi Aprt. Flat No. 20, Dhatrak Phata, Panchavati, Nashik FORM-2 [See Regulation 3] ENGINEER'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account - Project wise) To, Date: The Century Builders, New Pandit Colony, Nashik Subject: Certificate of Cost Incurred for Development of building(s)Sing!e PhaseWing(s) of the Single Phase situated on the Plot bearing C.N. No./eTS No./Survey No. _163/2/2_ Final Plot NO.18_ demarcated by its boundaries Plot N019 to The North Plot NO.17 the South Plot no.n to East plot nO.12 M Wide Road To the West of Division Nasik Village Nasik Taluka Nasik District Nasik PIN 422003 admeasuring 708.22sq.mts. area being developed by promoter Century Builders and Developers.Nashik Ref :Maha-RERA Registration Number PS16oo02321S Sir, 1/ We Sharadf'opatsonawane have undertaken assignment of certifying Estimated Cost for the Subject Real Estate Project proposed to be registered under Maha-RERA, being v n Residency Building(s)/ Wing(s) of the Single Phase situated on the plot bearing C.N. No./CTS No.r Survey NO._163/2/2 Final Plot NO.__ 18__ of Division Nashik Village_Nashik Taluka nashik District _Nashik PIN _422003 admeasuring __ sq.mts.area being developed by promoter _ 1. Following technical professionals are appointed by Owner / Promoter: - (i) M/s /Shri/SmtMadhurakulkarnias L.S. / Architect; (ii) M/s /Shri/ YoginKulkarni as Structural Consultant (iii) M/s /Shri/Smt as MEP Consultant SHARAD SONAWANE (D.C. E.) Address: Sagar Laxmi Aprt. .Flat No. 20, Dhatrak - Phata, Panchavati, Nashik .- - (iv) M/s /Shri/Smt as Quantity Surveyor .lE- 2. We have estimated the cost of the completion to obtain Occupation Certificate/ Completion Certificate, of the Civil, MEP and Allied works, of the Building(s) of the project. Our estimated cost calculations are based on the Drawings/plans made available to us for the project under reference by the Developer and Consultants and the Schedule of items and quantity for the entire work as calculated by quantity Surveyor" appointed by Developer /Engineer, and the assumption ofthe cost of material, labour and other inputs made by developer, and the site inspection carried out by us. 3. We estimate Total Estimated Cost of completion of the building(s) of the aforesaid project under reference as Rs.2,55,75,6S4/-. The estimated Total Cost of project is with reference to the Civil, MEP and allied works required to be completed for the purpose of obtaining occupation certificate / completion certificate for the building(s) from the being the Planning Authority under whose jurisdiction the aforesaid project is being implemented. 4. The Estimated Cost Incurred till date is calculated at Rs. 1,67,61,602. The amount of Estimated Cost Incurred is calculated on the base of a mount of Total Estimated Cost ..2,55,75,654/- 5. The Balance cost of Completion of the Civil, MEP and Allied works of the Building(s) of the subject project to obtain Occupation Certificate / Completion Certificate from is estimated at Rs. _ 6. I certify that the Cost of the Civil, MEP and allied work for the aforesaid Project as completed on the date of this certificate is as given in Table A and B below: TABLE A Building /Wing hearing Number called V X Residency (to be prepared separately for each Building /Wing of the Real Estate Project) Sr. Particulars Amounts in No (2) INR (1) (3) 1 Total Estimated cost of the building/wing as on .2,55,75,654/- date of Registration is 2 Cost incurred as on (based on the Estimated cost) Work done in Percentage ----:_-- %(as Percentage of - 60% 3 the estimated cost) SHARAD SONAWANE (D.C. E.) Address: Sagar Laxmi Aprt. Flat No. 20, Dhatrak Phata, Panchavati, Nashik 4 BalanceCost to be Incurred(Based on Estimated Cost) 88,1.1.05_2i- 5 Cost Incurred on Additional/Extra Items as on not included in the Estimated Cost (Annexure A) TABLEB (to be prepare ort e en Ire regis tere d p.h ase 0fth e Rea IE state Pro~ect d [i h . ) Sr. Particu lars Amounts in No (2) INR (1) (3) 1 Total Estimated cost of the Internal and External Development Works including amenities and Facilities in the layout as on date of Registration 2 Cost incurred as on (based on the Estimated cost). I 3 Work done in Percentage(as Percentage of the estimated % I cost). 4 BalanceCost to be Incurred(Based on Estimated Cost). 5 Cost Incurred on Additional/Extra Items as on not included in the Estimated Cost (Annexure A). Yours Faithfully, Signature of Engine!r Name: - Sha=ra.d- BoQ4UJQ1\e (License No. ----=--) SHARAD SONAWANf! ~, Civil Engineer