ATUL WAGH & ASSOCIATES CONSULTING ENGINEER # ARCHITECTS # VALUER FLAT NO.3, VISE MALA NILIMA APARTMENT CANADA COURNER ,NASHIK. MOB. NO -9325577665 Annexure A FORM 1 [See Regulation 3] ARCHITECT’S CERTIFICATE {To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from designated Account} Date :- 05/01/2021 To, The Trimurti Construction Partnership Firm Through Partner Mr. Bhausaheb P. Matale. Subject : Certificate of Percentage of Completion of Construction Work of SAPTSHRUNGI CLASSIC having MahaRERA Registration Number P51600023195 (Only Applicable after project Registration) being developed by Trimurti Construction Partnership Firm Through Partner Mr. Bhausaheb P. Matale. Sir, I/We ATUL T. WAGH have undertaken assignment as Architect/Licensed Surveyor of certifying Percentage of completion of Construction Work of SAPTSHRUNGI CLASSIC having MahaRERA Registration Number P51600023195 (Only Applicable after project Registration, being developed by Trimurti Construction Partnership Firm Through Partner Mr. Bhausaheb P. Matale. Based on Site Inspection, with respect to Layout/each of the Building/Wing of the aforesaid Real Estate Project. I certify that as on the date of this certificate, the 75% Percentage of Work done for each of the building/Wing of the Real Estate Project under is as per Table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. TABLE – A Layout/Building/Wing Number ______ (to be prepared separately for each Layout/Building/Wing of the Project) Sr. No. Tasks / Activity Percentage of Actual Work Done (1) (2) (As on date of the Certificate) (3) 1. Excavation 100 2. Basements (if any) - 3. Podiums (if any) - 4. Plinth 100 5. Stilt Floor - 6. Slabs of Super Structure 100 7. Internal walls, Internal Plaster, Floorings, Doors and windows 80 withing Flats/Premises 8. Sanitary Fittings withing the Flat/Premises 0 9. Staircase, Lifts Wells and Lobbies at each Floor Level 100 Overhead and Underground Water Tanks 10. External plumbing and external plaster, elavation, completion 50 of terraces with waterproofing of the Building / Wing. 11. Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical Fittings, mechanical equipment, compliance to conditions of environment/CRZ NOC, Finishing to entrance lobbys, plinth protection. Paving 0 of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. Any other activities. TABLE – B Common Areas (Internal and External Development Works) in respect of the Registered Phase/Project Number Sr. No. Common areas and Facilities Proposed Percentage of Actual Details (Yes/No) Work Done (As on date of the Certificate) (1) (2) (3) (4) (5) 1. Internal Roads & Footpaths N. A. - - 2. Water Supply YES 100 - 3. Sewerage (Chamber, lines, Septic Tank, YES 100 - STP). 4. Storm Water Drains N. A. - - 5. Landscaping & Tree Planting YES 100 6. Street Lighting N.A - - 7. Community Buildings N.A - - 8. Treatment and disposal of sewage and YES 100 sullage water. 9. Solid Waste management & Disposal N.A - - 10. Water Conservation / Rain water YES 100 harvesting 11. Energy management N.A - - 12. Fire protection and fire safety N.A - - requirements 13. Electrical meter room, sub-station, YES 100 reeiving station. 14. Others (Option to Add more). - - - Yours Faithfully, Signature & Name (IN BLOCK LETTERS) of L.S / Architect {License No. 00812} Agreed and Accepted by : MR. ATUL TUKARAM WAGH Signature of Promoter Name : Trimurti Construction Partnership Firm Through Partner Mr. Bhausaheb P. Matale. Date :05/01/2021