202, Second Floor, Roongto Arcode, Opp. Kulkorni Gorden, Shoronpur Rood, Noshik422OOl . Ph : 0253 -2232575. e-moil :jodhovponkoj02@gmoit.com Ar. Ponkoj Jodhov FORM 1 ARCHITECT'S CERTIFICATE Date:31-03-2024 To, M/s. KalantriAnd Musale Realcon LLP Shop No.2,Building No. F/10. Shreeram Kunj, Tigrania Road, Dwarka, Nashik-422011 Subject: Certificate of Percentage of Completion of Construction work BALAJI PARK having 11 buildings named A,B,C,D, E, F, G, H, l, J & K having Maha RERA Registration Number P51500023182 being developed by M/s, KalantriAnd Musale Realcon LLP Sir, l, Ar. Pankaj Jadhav have undertaken assignment as Architect of certifying Percentage of Completion of construction work BALAJI PARK having 11 buildings named A, B, C ,D, E, F, G, H, l, J & K having Maha RERA Registration Number P51600023182 being developed by M/s. KalantriAnd Musale Realcon LLP, situated on the bearing Survey No. Gut No. 449, Village Satpur, Taluka & District Nashik. Based on Site lnspection, with respect to Layout / each of the Building/ Wing of the aforesaid Real Estate Project, I certify that as on the date of this certificate, the Percentage of Work done for each of the Building / Wing of the Real Estate Project under MahaRERA is as per Table A herein below The of the executed with respect to each of the activity of the entire phase is detailed e Table B. \ .\ \$\(\ Ar. Pankaj P. Iadhav B"Arch. Reg. No. CA|2014154783 O'ffice No. 206 to 210, Roongta Supremus, Near chandak circte, rl:Hil iX,ffi?: Table A BALAJI PARK "A" Building Sr. Task / Activity Percentage No. of work done 1 Excavation 100 % 2 I Number of Plinth t00 % J 0 Number Of Podiums 0 4 0 Stilt Floor 0 5 2 Number of slabs of super structure 100 o/o 6 Internal walls, Intemal Plaster, Floorings withrn flats / premises, Doors, t00 % Windows to each of the Flat / Premises 7 Sanitary fitting within the flat / premises, Electrical fitting within the flat 100 % / premises 8 Staircase, Lift well and Lobbies at each floor level connecting staircase r00 % and lift, Overhead and underground water tanks. 9 External plumbing and external plaster, elevation, completion ofterrace 100 % with water pqqfing of the Building / Wing l0 Installation of lift, water pumps, fire fighting fitting and equipments as 100 % per CEO NOC, Electrical fitting to common areas, electro mechanical equipments, Compliance to conditions of environment/CRZ NOC, Finish to entrance lobby, Plinth protection, Paving to areas appurtenant to building / wing, Compound wall and all other requirements as may be required to obtain Occupation / Completion certificate \s\ \ Ar. Pankaj P. Jadhav Res. No. cenorf,r*;Tj Offioe fVo. 206 to 210, Roongta Supremus, Near chandak circre, ,Hiffi iX!1tT?: Table A BAIAJI PARK "B" Building Sr. Task / Activity Percentage No. ofwork done 1 Excavation 100 o/o 2 1 Number of Plinth 100 % J 0 Number Of Podiums 0 4 0 Stilt Floor 0 5 2 Number of slabs of super structure r00 % 6 Internal walls, Internal Plaster, Floorings within flats / premises, Doors, 100 % Windows to each of the Flat / Premises 7 Sanitary fitting within the flat / premises, Electrical fitting within the flat 100 % / premises 8 Staircase, Lift well and Lobbies at each floor level connecting staircase t00 % and lift, Overhead and underground water tanks. 9 Extemal plumbing and external plaster, elevation, completion of terrace 100 o/o with water proofing of the / Wing 10 Installation of lift, water pumps, fire fighting fitting and equipments as r00 % per CEO NOC, Electrical fitting to common areas, electro mechanical equipments, Compliance to conditions of environmentJCRZ NOC, Finish to entrance lobby, Plinth protection, Paving to areas appurtenant to building / wing, Compound wall and all other requirements as may be required to obtain Occupation / Completion certificate Ar, Pa P. Jadhav B.Arch' Reg. No. CA120L4164783 Office No. 206 to 210, Roongta Supremus, Near chandak circte, tffil;,i iX,r.rfri: Table A BALAJI PARK "C" Building Sr. Task /Activity Percentage No. of work done 1 Excavation 100 o/o 2 1 Number of Plinth t00 % J 0 Number Of Podiums 0 4 0 Stilt Floor 0 5 2 Number of slabs of super structure 100 o/o 6 Internal walls, Intemal Plaster, Floorings within flats / premises, Doors, 100 % Windows to each of the Flat / Premises 7 Sanitary fitting within the flat / premises, Electrical fitting within the flat 100 o/o / premises 8 Staircase, Lift well and Lobbies at each floor level connecting staircase 100 % and lift, Overhead and underground water tanks. 9 External plumbing and external plaster, elevation, completion of terrace 100 % with water proofing of the Building / Wine 10 Installation of lift, water pumps, fire fighting fitting and equipments as t00 % per CEO NOC, Electrical fitting to common areas, electro mechanical equipments, Compliance to conditions of environment/CRZ NOC, Finish to entrance lobby, Plinth protection, Paving to areas appurtenant to building / wing, Compound wall and all other requirements as may be required to obtain Occupation / Completion certificate Ar. Pan kai P. Jadhav B.Arch, Reg. No. CA|Z|L4l64783 Offioe No. 206 to 210, Roongta Supremus, Near Chand.:k Circle, Shriharl Kute Marg, Nashik - 422 001. Table A BALAJI PARK "D" Building Sr. Task / Activity Percentage No. of work done I Excavation 100 o/o 2 I Number of Plinth 100 o/o J 0 Number Of Podiums 0 4 0 Stilt Floor 0 5 2 Number of slabs of super structure 100 o/o 6 Intemal walls, Internal Plaster, Floorings within flats / premises, Doors, 100 % Windows to each of the Flat / Premises 7 Sanitary fitting within the flat / premises, Electrical fitting within the flat 100 o/o / premises 8 Staircase, Lift well and Lobbies at each floor level connecting staircase 100 % and lift, Overhead and underground water tanks. 9 External plumbing and external plaster, elevation, completion of terrace 100 % with water proofing of the Building / Wing 10 Installation of lift, water pumps, fire fighting fitting and equipments as 100 % per CEO NOC, Electrical fitting to common areas, electro mechanical equipments, Compliance to conditions of environmentlCRZ NOC, Finish to entrance lobby, Plinth protectiorq Paving to areas appurtenant to building I wing, Compound wall and all other requirements as may be required to obtain Occupation / Completion certificate Ar, Pankaj P. Jadhav B.Arch. Reg. ltlo. CAI 20L4 I 647 83 office No. 206 to 210, Roongta Supremus, Near chandak circre, r[:H,? iXt! %Ti: Table A BALAJI PARK "E" Building Sr. Task / Activity Percentage No. of work done 1 Excavation 100 o/o 2 1 Number of Plinth 100 o/o 3 0 Number Of Podiums 0 4 0 Stilt Floor 0 5 2 Number of slabs of super structure 100 o/o 6 Internal walls, Internal Plaster, Floorings within flats / premises, Doors, t00 % Windows to each of the Flat / Premises 7 Sanitary fitting within the flat / premises, Electrical fitting within the flat t00 % / premises 8 Staircase, Lift well and Lobbies at each floor level connecting staircase 100 o/o and lift, Overhead and underground water tanks. 9 External plumbing and external plaster, elevation, completion of terrace 100 o/o with water proofing of the Building / Wing l0 Installation of lift, water pumps, fire fighting fitting and equipments as 100 % per CEO NOC, Electrical fitting to common areas, electro mechanical equipments, Compliance to conditions of environmentlCRZ NOC, Finish to entrance lobby, Plinth protectiorq Paving to areas appurtenant to building / wing, Compound wall and all other requirements as may be required to obtain Occupation / Completion certificate $$.\ Ar , Ralta; P. Jadhav B.Arch. Reg. No. CA|2014164783 Offie No. 206 to 210, Roongta Supremus, Near Chandak CircJe, Shrihari Kute Marg, Nashik - 422 00L. Table A BAIA,l PARK "F" Building Sr. Task / Activity Percentage No. of work done 1 Excavation t00 % 2 I Number of Plinth 100 % 3 0 Number Of Podiums 0 4 0 Stilt Floor 0 5 I Number of slabs of super structure 100 o/o 6 Internal walls, Internal Plaster, Floorings within flats / premises, Doors, 100 o/o Windows to each of the Flat / Premises 7 Sanitary fitting within the flat / premises, Electrical fitting within the flat 100 o/o / premises 8 Staircase, Lift well and Lobbies at each floor level connecting staircase 700 o/o and lift, Overhead and underground water tanks. 9 External plumbing and extemal plaster, elevation, completion of terrace 100 % with water proofing of the Building / Wing 10 Installation of lift, water pumps, fire fighting fitting and equipments as t00 % per CEO NOC, Electrical fitting to common areas, electro mechanical equipments, Compliance to conditions of environment/CRZ NOC, Finish to entrance lobby, Plinth protection, Paving to areas appurtenant to buildrng / wing, Compound wall and all other requirements as may be required to obtain Occupation / Completion certificate \$ Ar . Pdnkaj P, Iadhav B.Arch. Reg. No. CA12014164783 Offie No. 206 to 210, Roongta SuPremus, Near Chandak Circle, Shrihari Kute Marg, Nashik - 422 001. Table A BALAJI PARK "G" Building Sr. Task / Activity Percentage No. of work done 1 Excavation 100 % 2 I Number of Plinth 100 o/o J 0 Number Of Podiums 0 4 0 Stilt Floor 0 5 2 Number of slabs of super structure 100 % 6 Internal walls, Internal Plaster, Floorings within flats / premises, Doors, 100 % Windows to each of the Flat / Premises 7 Sanitary fiuing within the flat / premises, Electrical fitting within the flat r00 % / premises 8 Staircase, Lift well and Lobbies at each floor level connecting staircase 100 % and lift, Overhead and underground water tanks. 9 External plumbing and external plaster, elevation, completion of terrace t00 % with water proofing of the Building / Wing l0 Installation of lift, water pumps, fire fighting fitting and equipments as 100 o/o per CEO NOC, Electrical fitting to common areas, electro mechanical equipments, Compliance to conditions of environmentlCRZ NOC, Finish to entrance lobby, Plinth protection, Paving to areas appurtenant to building / wing, Compound wall and all other requirements as may be required to obtain Occupation / Completion certificate )s\ Ar, PinE