202, Second Floor, Roonglo Arcode, Opp, Kulkorni Gorden, Shoronpur Rood, Noshik422OO'l . Ph : 0253 - 2232575. e-moil : jodhovponkoj02@gmoil,com Ar, Ponkoj Jodhov FORM 1 ARCH ITECT'S CERTIFICATE Date:30-09-2023 To, M/s. KalantriAnd Musale Realcon LLP Shop No.2,Building No. F/10. Shreeram Kunj, Tigrania Road, Dwarka, Nashik-422011 Subject: Certificate of Percentage of Completion of Construction work BALAII PARK having 11 buildings named A,B,C,D, E,F,G, H, l, J & K having Maha RERA Registration Number P51600023182 being developed by M/s, KalantriAnd Musale Realcon LLP Sir, l, Ar. Pankaj Jadhav have undertaken assignment as Architect of certifylng Percentage of Completion of construction work BALAJI PARK having 11 buildings named A, B, C ,O, E, F, G, H, l, J & K having Maha RERA Registration Number P51600023182 being developed by M/s. KalantriAnd Musale Realcon LLP, situated on the bearing Survey No. Gut No. 449, Village Satpur, Taluka & District Nashik. Based on Site lnspection, with respect to Layout / each of the Building/ Wing of the aforesaid Real Estate Project, I certify that as on the date of this certificate, the Percentage of Work done for each of the Building / Wine of the Real Estate Project under MahaRERA is as per Table A herein below. The pe of the executed with respect to each of the activity of the entire phase is \ detailed n Table B. Ar. Fa kaj P. Jadhav B.Arch. Reg. tJo. CAI 2014 I 64783 ffice No. 206 to 210, Roongta Supremus, Near chandak Circte, ,[,f|f IXffi: a Table A BALAJI PARK "A" Building Sr. Task / Activity Percentage No. ofwork done 1 Excavation 100 o/o 2 I Number of Plinth t00 % J 0 Number Of Podiums 0 4 0 Stilt Floor 0 5 2 Number of slabs of super structure t00 % 6 Internal walls, Intemal Plaster, Floorings within flats / premises, Doors, t00 % Windows to each of the Flat / Premises 7 Sanitary fitting within the flat / premises, Electrical fitting within the flat 100 % / premises 8 Staircase, Lift well and Lobbies at each floor level connecting staircase 100 % and lift, Overhead and underground water tanks. 9 External plumbing and external plaster, elevation, completion of terrace t00 % with water proofing of the Building / Wing 10 Installation of lift, water pumps, fire fighting fitting and equipments as 100 o/o per CEO NOC, Electrical fitting to common areas, electro mechanical equipments, Compliance to conditions of environmenUCRZ NOC, Finish to entrance lobby, Plinth protectiorg Paving to areas appurtenant to building / wing, Compound wall and all other requirements as may be required to obtain Occupation / Completion certificate \ $*$ Ar. Pankaj P. rTXfil Reg. No. CNZAL4l64783 Office No. 206 to 210, Roongta Supremus, Near chandak Grcte, rl:l;fl IX,ffi?: Table A BALAJI PARK'8" Building Sr. Task / Activity Percentage No. ofwork done 1 Excavation 100 % 2 1 Number of Plinth t00 % 3 0 Number Of Podiums 0 4 0 srilt Floor 0 5 2 Number of slabs of super structure 100 % 6 Internal walls, Internal Plaster, Floorings within flats / premises, Doors, t00 % Windows to each of the Flat / Premises 7 Sanitary fitting within the flat / premises, Electrical fitting within the flat 100 % / premises 8 Staircase, Lift well and Lobbies at each floor level connecting staircase 100 % and lift, Overhead and underground water tanks. 9 External plumbing and extemal plaster, elevation, completion of terrace 100 o/o with water proofing of the Building / Wing 10 Installation of lift, water pumps, fire fighting fiuing and equipments as 100 o/o per CEO NOC, Electrical fitting to common areas, electro mechanical equipments, Compliance to conditions of environmentlCRZ NOC, Finish to entrance lobby, Plinth protectiorl Paving to areas appurtenant to building / wing, Compound wall and all other requirements as may be required to obtain Occupation / Completion certificate \A rTXr:X Ar. Pankaj P. Reg. No. CAl20L4l54783 Office No. 206 to 210, Roongta Supremus, Near chandak circre, t[i;,[iX!ffi: Table A BALAJI PARK "C" Building Sr. Task / Activity Percentage No. of work done I Excavation t00 % 2 I Number of Plinth t00 % J 0 Number Of Podiums 0 4 0 Stilt Floor 0 5 2 Number of slabs of super structure 100 o/o 6 Internal walls, Internal Plaster, Floorings withrn flats i premises, Doors, r00 % Windows to each of the Flat / Premises 7 Sanitary fitting within the flat / premises, Electrical fitting within the flat 100 % / premises 8 Staircase, Lift well and Lobbies at each floor level connecting staircase 100 % and lift, Overhead and undergound water tanks. 9 External plumbing and extemal plaster, elevation, completion of terrace 100 % with water proofing of the Building / Wing l0 Installation of lift, water pumps, fire fighting fitting and equipments as 100 o/o per CEO NOC, Electrical fitting to common areas, electro mechanical equipments, Compliance to conditions of environmentlCRZ NOC, Finish to entrance lobby, Plinth protectiorl Paving to areas appurtenant to building / wing, Compound wall and all other requirements as may be required to obtain Occupation / Completion certificate Ar. Pa kai P. ,"#X'.?X. Reg. No. CA/20 t4164783 Office No. 206 to 210, Roongta Supremus, Near Ctandak Circle, Shrihari Kute Marg, Nashik - 422 001" Table A BALAJI PARK "D" Building Sr. Task / Activity Percentage No. ofwork done 1 Excavation t00 % 2 I Number of Plinth t00 % J 0 Number Of Podiums 0 4 0 Stilt Floor 0 5 2 Number of slabs of super structure 100 o/o 6 Intemal walls, Internal Plaster, Floorings within flats / premises, Doors, 100 % Windows to each of the Flat / Premises 7 Sanitary fitting within the flat / premises, Electrical fitting within the flat 100 % / premises 8 Staircase, Lift well and Lobbies at each floor level connecting staircase 100 o/o and lift, Overhead and underground water tanks. 9 External plumbing and extemal plaster, elevation, completion of terrace 100 % with water proofing of the Building / Wing t0 Installation of lift, water pumps, fire fighting fitting and equipments as t00 % per CEO NOC, Electrical fitting to common areas, electro mechanical equipments, Compliance to conditions of environmentlCM NOC, Finish to entrance lobby, Plinth protection, Paving to areas appurtenant to building / wing, Compound wall and all other requirements as may be required to obtain Occupation / Completion certificate \ U.t$\ .1 \ Ar. Pankaj P. Jadhav Res. No. c^tzorli{[i!; Office No. 206 to 210, Roongta Supremus, Near chandak circte, .Hiffi iX,rrtT?: Table A BALAJI PARK "E" Building Sr. Task / Activity Percentage No. of work done 1 Excavation t00 % 2 I Number of Plinth rc0% J 0 Number Of Podiums 0 4 0 Stilt Floor 0 5 2 Number of slabs of super structure r00 % 6 Internal walls, Internal Plaster, Floorings within flats / premises, Doors, t00 % Windows to each of the Flat / Premises 7 Sanitary fitting within the flat / premises, Electrical frtting within the flat t00 % / premises 8 Staircase, Lift well and Lobbies at each floor level connecting staircase 100 % and lift, Overhead 4nd underground water tanks. 9 External plumbing and external plaster, elevation, completion of terrace t00 % with water proofing of the B uilding/ Wing t0 Installation of lift, water pumps, fire fighting fiuing and equipments as t00 % per CEO NOC, Electrical fiuing to common areas, electro mechanical equipments, Compliance to conditions of environment/CRZ NOC, Finish to entrance lobby, Plinth protection, Paving to areas appurtenant to buildrng / wing, Compound wall and all other requirements as may be required to obtaiqOccupation / Completion certificate \$ Ar. Plnkai P, Jadhav B.Arch. Reg. No. CA|2014154783 ffie No.206 to 210, Roongta SuPremus, Near Chandak Circle, Shrihari Kute Marg, Nashik - 422 00L. Table A BALA,I PARK "F" Building Sr. Task / Activity Percentage No. of work done 1 Excavation 100 % 2 1 Number of Plinth 100 % 3 0 Number Of Podiums 0 4 0 Stilt Floor 0 5 I Number of slabs of super structure 100 % 6 Internal walls, Internal Plaster, Floorings within flats / premises, Doors, 100 % Windows to each of the Flat / Premises 7 Sanitary fitting within the flat / premises, Electrical fitting within the flat 100 % / premises 8 Staircase, Lift well and Lobbies at each floor level comecting staircase 100 % and lift, Overhead and underground water tanks. 9 External plumbing and extemal plaster, elevation, completion of terrace 100 % with water proofing of the Buildine / Wing l0 Installation of lift, water pumps, fire fighting fitting and equipments as t00 % per CEO NOC, Electncal fitting to common areas, electro mechanical equipments, Compliance to conditions of environment/CRZ NOC, Finish to entrance lobby, Plinth protectiorq Paving to areas appurtenant to building / wing, Compound wall and all other requirements as may be required to obtain Occupation / Completion certificate $$ Ar. Pasdkaj P. Jadhav B.Arch. Reg. tio. CAI 20t4 I 64783 Office No. 206 to 210, Roongta Supremus' Near chandak circre, tl:iffi ll,ffi?: Table A BAIAJI PARK "G" Building Sr. Task / Activity Percentage No. of work done 1 Excavation 100 o/o 2 1 Number of Plinth 100 o/o J 0 Number Of Podiums 0 4 0 Stilt Floor 0 5 2 Number of slabs of super structure 100 o/o 6 Internal walls, Intemal Plaster, Floorings within flats / premises, Doors, t00 % Windows to each of the Flat / Premises 7 Sanitary fitting within the flat / premises, Electrical fitting within the flat 100 % / premises 8 Staircase, Lift well and Lobbies at each floor level connecting staircase 100 % and lift, Overhead and underground water tanks. 9 External plumbing and external plaster, elevation, completion of terrace 100 o/o with water proofing of the Building / Wing 10 Installation of lift, water pumps, fire fighting fitting and equipments as 100 % per CEO NOC, Electrical fitting to common areas, electro mechanical equipments, Compliance to conditions of environment/CRZ NOC, Finish to entrance lobby, Plinth protection, Paving to areas appurtenant to building / wing, Compound wall and all other requirements as may be required to obtain Occupation / Completion certificate tlP\ Ar. PdnEcaj P, Jadhav B.Arch. Reg. llo. CAI 20t4 | 647 83 office No. 206 to 210, Roongta Supremus, Near Chandak Circle, Shrihari Kute Marg, Nashik - 422 001. Table A BALAJI PARK "H" Building Sr. Task / Activity Percentage No. ofwork done 1 Excavation 100 % 2 1 Number of Plinth 100 % J 0 Number Of Podiums 0 4 0 Stilt Floor 0 5 2 Number of slabs of super structure 100 o/o 6 Intemal walls, Internal Plaster, Floorings within flats / premises, Doors, 100 % Windows to each of the Flat / Premises 7 Sanitary fitting within the flat / premises, Electrical fitting within the flat 100 % / premises 8 Staircase, Lift well and Lobbies at each floor level connecting staircase 100 % and lift, Overhead and underground water tanks. 9 Extemal plumbing and external plaster, elevation, completion of tenace 100 % with water proofing of the Building / Wing 10 Installation of lift, water pumps, fire fighting fitting and equipments as 100 % per CEO NOC, Electrical fitting to common areas, electro mechanical equipments, Compliance to conditions of environmentlCRZ NOC, Finish to entrance lobby, Plinth protection, Paving to areas appurtenant to building / wing, Compound wall and all other requirements as may be required to obtain Occupation / Completion certificate u$ Ar , Pdrul'ai P. Jadnav B Arch. Reg. No. CAl20t4164783 Office No. 206 to 210, Roongta Suprenrus, ]tsar chandak circle, t[:l..T iX!ffi : Table A BALAJI PARK "1" Building Sr. Task / Activity Percentage No. of work done 1 Excavation t00 % 2 I Number of Plinth 100 % 3 0 Number Of Podiums 0 4 0 Stilt Floor 0 5 2 Number of slabs of super structure t00 % 6 Internal walls, lnternal Plaster, Floorings within flats / premises, Doors, 100 o/o Windows to each of the Flat / Premises 7 Sanitary fitting within the flat / premises, Electrical fitting within the flat t00 % / premises 8 Staircase, Lift well and Lobbies at each floor level connecting staircase 100 % and lift, Overhead and underground water tanks 9 External plumbing and external plaster, elevation, completion of terrace 100 o/o with water proofing of the Building/ Wing 10 Installation of lift, water pumps, fire fighting fitting and equipments as t00 % per CEO NOC, Electrical fitting to common areas, electro mechanical equipments, Compliance to conditions of environment/CRZ NOC, Finish to entrance lobby, Plinth protectioq Paving to areas appurtenant '$ to building / wing, Compound wall and all other requirements as may be required to obtain Occupation / Completion certificate Ar. Pahkaj P. Jadhav B.Arch. Reg. No. CA120t4164783 ffice No. 206 tO 210, Roongta supremus' Near chandak circte, r[:lrT/ Ix,r"rffii: a Table A BALAJI PARK "J" Building Sr. Task / Activity Percentage No. ofwork done I Excavation 100 o/o 2 I Number of Plinth 100 % J 0 Number Of Podiums 0 4 0 Stilt Floor 0 5 I Number of slabs of super structure 100 % 6 Internal walls, Intemal Plaster, Floorings within flats / premises, Doors, 100 % Windows to each of the Flat / Premises 7 Sanitary fitting within the flat / premises, Electrical fitting within the flat t00 % / premises 8 Staircase, Lift well and Lobbies at each floor level connecting staircase 100 Yo and lift, Overhead and underground water tanks. 9 External plumbing and external plaster, elevation, completion of terrace 100 % with water proofing of the Building / Wing 10 Installation of lift, water pumps, fire fighting fitting and equipments as t00 % per CEO NOC, Electrical fitting to common areas, electro mechanical equipments, Compliance to conditions of environmentlCRZ NOC, Finish to entrance lobby, Plinth protection, Paving to areas appurtenant to building / wing, Compound wall and all other requirements as may be required to obtain Occupation / Completion certificate Ar. P n!'ai o. ,";|X:f. Reg. t'to. CA120L4 I 647 83 office No. 206 to 210, Roongta supremus' - neai oanaak circle, t[:H iX,rffi : I a Table A BAIAJI PARK "K" Building Sr. Task / Activity Percentage No. of work done 1 Excavation 100 o/o 2 1 Number of Plinth 100 o/o J 0 Number Of Podiums 0 4 0 Stilt Floor 0 5 1 Number of slabs of super structure 100 % 6 Internal walls, Internal Plaster, Floorings within flats / premises, Doors, r00 % Windows to each of the Flat / Premises 7 Sanitary fitting within the flat / premises, Electrical fiuing within the flat 100 % / premises 8 Staircase, Lift well and Lobbies at each floor level connecting staircase 700 o/o and lift, Overhead and underground water tanks. 9 External plumbing and external plaster, elevation, completion of terrace 100 % with water proofing of the Buildine / Wine 10 Installation of lift, water pumps, fire fighting fiuing and equipments as t00 % per CEO NOC, Electrical fitting to common areas, electro mechanical equipments, Compliance to conditions of environment/CRZ NOC, Finish to entrance lobby, Plinth protection, Paving to areas appurtenant to building / wing, Compound wall and all other requirements as may be required to obtain Occupation / Completion certificate -$ Ar. Pan leai F. Jadi,?n". Reg. No. CAl20t4l64783 Office No. 206 to 210, Roongta Supremus, rllear Chandak Circle, Shdhal IX!"rH?: ? \ TABLE - B BALAJIPARK (11 Buildings A to K) lnternal & External Development Work in Respect of the project Sr. Common areas, Propesed Percentage Details No. Facilities & Amenities (Yes / No) of work done I Intemal roads & No 100 o/o Not Applicable footpaths 2 Water supply Yes 100 % To be obtaines from NMC on completion of the proiect 3 Sewage (chamber Yes 100 % Will be Provided only if lines,septic tank,STP) required by NMC DC Rules 4 Storm water drains No 100 o/o N.A. 5 Landscaping and tree No 100 o/o Will be Provided only if planting required by NMC DC Rules 6 Street lights No 100 o/o N.A. 7 Community Buildings No 0 N.A. 8 Treafinent and disposal Yes 0 Will be Provided only if of sewage and sullage required byNMC DC water Rules 9 Solid waste management No 0 N.A. and disposal 10 Water conservation, Rain Yes 100 o/o Will be Provided only if water harvesting required by NMC DC Rules ll Energy management No 0 N.A. t2 Fire protection and fire Yes 0 Will be Provided only if safety requirements required byNMC DC Rules 13 Electric meter room, Sub No 0 Indiviual Electric Meter station, Receiving station Provided after Completion Yours Faithfully Ar. P:N$ r.r,gX,?N Agreed and Accepted by: Reg. No. CA12014154783 Office No. 206 to 210, Roongta Suprenrus, Signature of Promoter r{ear chandak circre, rll$; ilf M/s. KalantriAnd Musale Realcon LLP tJi: LLP fuiUSA''E REALCU{ KALAI.IIRI AiO @4 Plii?T|!ER