AJIT KULKARNI ARCHITECTS, INTERIOR & LANDSCAPE DESIGNERS. 7/B NiwasMaitriAppt, Behind HDFC Sharanpur Road. Nashik. Ph 2575704. FORM 1 ARCHITECT’S CERTIFICATE DATE:30/09/2020 To, SAI HOME BUILDERS THR PART MILIND M. GAMBHIR SANDIP S. DHANDE, NILIMA H. DHAKE, SANKET C. WANI SITE- OMKARA HEIGHTS DASAK,JAIL ROAD, NASHIK ROAD, NASHIK-422101 Subject: Certificate of Percentage of Completion of Construction Work of OMKARA HEIGHTS Residential Building situated on the Plot bearing C.N. No / CTS No. / Survey no.65/3/1 ,PLOT NO9+10 demarcated by its boundaries (latitude and longitude of the end points) ADJ SNO 65(PT)to the North ,9.00m WIDE ROAD to the South, ADJ SNO 64(PT) to the East and ADJ PLOT NO 8 to the West at village DASAK taluka NASHIK District NASHIK PIN 422101 admeasuring 598.98sq.mts. Area being developed by SAI HOME BUILDERS THR PART MILIND M. GAMBHIR SANDIP S. DHANDE, NILIMA H. DHAKE, SANKET C. WANI Sir, IAJIT SKULKARNI have undertaken assignment as Architect / Licensed Surveyor of certifying Percentage of Completion of Construction Work of OMKARA HEIGHTS Residential Building situated on the Plot bearing C.N. No / CTS No. / Survey no. 65/3/1,Plot no 9+10demarcated by its boundaries (latitude and longitude of the end points) ADJ SNO 65(PT)to the North ,9.00m WIDE ROAD to the South ,ADJ SNO 64(PT) to the East and ADJ PLOT NO 8tothe West at village DASAK taluka NASHIK District NASHIK PIN 422101 admeasuring 598.98sq.mts. Area being developed by SAI HOME BUILDERS THR PART MILIND M. GAMBHIR SANDIP S. DHANDE, NILIMA H. DHAKE, SANKET C. WANI 1. Following technical professionals are appointed by Owner / Promoter:- (i) Mr. Ajit Kulkarni as Architect ; (ii) Mr. Sunil Patel as Structural Consultant Based on Site Inspection, with respect to each of the Building / Wing of the aforesaid Real Estate Project, I certify that as on the date of this certificate, the Percentage of Work done for each of the building / Wing of the Real Estate Project is as under RERA is as per table A herein below. The percentage of the work executed with respect to each of the major activity of the Building / Wing and Overall Percentage of the work done with respect to each Building / Wing is detailed in the Table B. Table A Sr.No Tasks / Activity Percent âge 1 Excavation 100 2 Plinth 100 3 8 number of Slabs of SuperStructure 60 4 Masonry/ walls 15 5 Internal Plaster 00 6 External Plaster, elevation- In progress 00 7 Flooring within Flats / Premises-In progress on 2nd floor 00 8 Door and Windows to each of the Flat / Premises 00 9 External plumbing down take lines ,CP/ Sanitary Fitting 00 within the Flats / Premises- Electrical Fitting within the Flats / Premises, 10 Electrical switches and wiring inside apartment 00 11 Painting 0 12 Staircases, Lifts Wells and Lobbies at each Floor level 20 connecting Staircases and LiftsOverhead and Underground Water Tanks 13 Completion of terraces with waterproofing of the Building 00 14 Installation of lifts 0 16 Fire Fighting Fittings and Equipment’s as per CFO NOC NA 17 Electrical fittings to Common Areas, water pumps,electro - 00 mechanical equipment’s 18 Finishing of entrance lobby/s, paving of areas appurtenant to 20 Building, Compound Wall and all other requirements as may be required to obtain Occupation / Completion Certificate Above mentioned work is 40 % of entire work TABLE – B Internal & External Development Works in Respect of the project S. No. Common Roads and Facilities, Amenities Proposed Percentage of Details (Yes/No) Work done 1 Side margin pavement YES 00 Will be completed at the time of completion 2 Water Supply YES 00 Will be completed at the time of completion 3 Sewerage (chamber, sewage lines), YES 00 Will be completed Storm Water Drains at the time of completion 4 Landscaping & Tree Planting NO NA NA 5 Common area Lighting NA NA NA 6 Water conservation, Rain water YES 0 Will be completed harvesting at the time of completion 7 Fire protection and fire safety NA NA NA requirements 8 Electrical meter room, sub-station, NA NA NA receiving station Above mentioned work is 40 % of entire work CARPET AREA STATEMENT FLOOR NAME CARPETAREA NAME CARPET AREA(SQ. MTR) OPEN BALCONY AREA(SQ. MTR) FIRST FLOOR FLAT NO 1 59.00 14.25 FLAT NO 2 78.78 6.04 SECOND FLOOR FLAT NO 3 59.00 14.25 FLAT NO 4 78.78 6.04 THIRD FLOOR FLAT NO 5 59.00 14.25 FLAT NO 6 38.78 6.15 FLAT NO 7 38.80 6.04 FORTH FLOOR FLAT NO 8 59.00 14.25 FLAT NO 9 38.78 6.15 FLAT NO 10 38.80 6.04 FIFTH FLOOR FLAT NO 11 59.00 14.25 FLAT NO 12 38.78 6.15 FLAT NO 13 38.80 6.04 SIXTH FLOOR FLAT NO 14 59.00 14.25 FLAT NO 15 38.78 6.15 FLAT NO 16 38.80 6.04 SEVENTH FLOOR FLAT NO 17 59.00 14.25 FLAT NO 18 78.78 6.04 TOTAL 959.66 166.63 Ar. Ajit Kulkarni. B.Arch. CA/2002/29073