FORM 1 ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account) Date: 04.09.2019 To The SHINDE AND SHINDE, Builders & Developers (Name & Address of Promoter), Subject: Certificate of Percentage of Completion of Construction Work of 2 No. of Buildings / 3 Wings of the ENTIRE Phase of the Project [MahaRERA Registration Number (To be applied)] situated on the Plot bearing CTS No. 3572, Survey no. 65/1/1A demarcated by its boundaries (latitude and longitude of the end points) Goda Park & Godavai River to the North, 24.00 M wide D. P. Road to the South, S. No. 66 to the East, Approach Road & Darga and to the West of Division ______, Village Anandwali, Taluka Nashik, District Nashik, PIN ______, admeasuring 3,114.27 square meter area being developed by SHINDE AND SHINDE, Builders & Developers [Promoter’s Name] Sir, I, SANJAY RAMESH NAIK have undertaken assignment as Architect of certifying Percentage of Completion of Construction Work of the 2 No. of Buildings / 3 Wings of the ENTIRE Phase of the Project situated on the Plot bearing CTS No. 3572, Survey no. 65/1/1A of Division ______, Village Anandwali, Taluka Nashik, District Nashik, PIN ______, admeasuring 3,114.27 square meter area being developed by SHINDE AND SHINDE, Builders & Developers [Promoter’s Name] 1. Following technical professionals are appointed by Owner / Promoter:- (i) Shri SANJAY RAMESH NAIK as Architect; (ii) Shri PRASHANT SUBHASHCHANDRA BACHHAV as Structural Consultant (iii) M/s /Shri / Smt ________________________ as MEP Consultant (iv) Shri SAGAR SHASHIKANT SHINDE as Site Supervisor Based on Site Inspection, with respect to each of the Building / Wing of the aforesaid Real Estate Project, I certify that as on the date of this certificate, the Percentage of Work done for each of the building/Wing of the Real Estate Project as registered vide number ________________ under MahaRERA is as per table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. Table A Building 1 / Wing Number A & B (To be prepared separately for each Building / Wing of the Project) Sr. No Tasks /Activity Percentage of work done 1 Excavation 0% 2 1 number of Basement(s) and Plinth 0% 3 0 number of Podiums 0% 4 Stilt Floor 0% 5 7 number of Slabs of Super Structure 0% 6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat / Premises 0% 7 Sanitary Fittings within the Flat/Premises, Electrical Fittings within the Flat/Premises 0% 8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks 0% 9 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing, 0% 10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0% Table A Building 2 / Wing Number C (To be prepared separately for each Building / Wing of the Project) Sr. No Tasks /Activity Percentage of work done 1 Excavation 0% 2 1 number of Basement(s) and Plinth 0% 3 0 number of Podiums 0% 4 Stilt Floor 0% 5 7 number of Slabs of Super Structure 0% 6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat / Premises 0% 7 Sanitary Fittings within the Flat/Premises, Electrical Fittings within the Flat/Premises 0% 8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks 0% 9 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing, 0% 10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0% TABLE-B Internal & External Development Works in Respect of the entire Registered Phase S.No Common areas and Proposed Percentage Details Facilities, Amenities (Y/N) of Work Done Internal Roads & N 0% Foothpaths 2. Water Supply Y 0% 3. Sewerage (chamber, lines, Septic Tank , STP) Y 0% 4. Storm Water Drains N 0% 5. Landscaping & Tree Planting Y 0% 6. Street Lighting N 0% 7. Community Buildings N 0% 8. Treatment and disposal of sewage and sullage water N 0% 9. Solid Waste management & Disposal N 0% 10. Water conservation, Rain water harvesting Y 0% 11. Energy management N 0% 12. Fire protection and fire safety requirements Y 0% 13. Electrical meter room, sub-station, receiving station Y 0% 14. Others (Option to add more) Yours Faithfully SANJAY RAMESH NAIK Signature & Name of Architect (License NO.: CA2001/27211)