Vijaya Consultants • BUILDING CONSULTING ENGINEERS 10. SIDOHI PARK. PLANNERS NEW PANDIT COLONY. NASHIK . • STRUCTURAL Ph.: (0) 2574602. Mob. : 98220 20644. Email :. ashokjamdar@yahoo com CONSULTANTS ASHOKJAMOAR FORM 1 Certificate. NO.00110/2021 CERTIFICATE Date. 04/05/2021 To, Mis. Jay Padmavati Builders Partnership Firm Th. Partner Shri. Prasanna V. Kankaraj & Other. Nashik - 422001 Subject: Certificate of Percentage of Completion work of building name "PADMA-VISHWA DREAM SQUAR'E" for Construction Work of Building of the Project [ Maha RERA Registration Number P51600022190] situated on the Plot No. 15 bearing Survey. No. 391N5/1 demarcated by its boundaries (latitude and longitude of the end points) 18.00 M.W. Road to the North, 9.00 M.W. Road to the South, Plot. No. 14 to the East, S.No. 39/A16 to the West, of Division Nasik, Village Wadala Taluka Nashik, District Nashik, PIN 422001 admeasuring 630.04 Sqrn. Mtrs .area being developed by Mis. Jay Padmavati Builders Partnership Firm Th. Partner Shri. Prasanna V. Kankaraj & Other, Sir, I Er. Ashok Jamdar have undertaken assignment as Licensed Engineer of certifying Percentage of Completion of construction work of the project "PADMA-VISHWA DREAM SQUARE" Building of the Project [ Maha RERA Registration Number P51600022190] situated on the Plot No. 15 bearing Survey. No. 391N5/1 demarcated by its boundaries (latitude and longitude of the end points) 18.00 M.W. Road to the North, 9.00 M.W. Road to the South, Plot. No. 14 to the East, S.No. 39/A/6 to the West, of Division Nasik, Village Wadala Taluka Nashik, District Nashik, PIN 422001 admeasuring 630.04 Sqm. Mtrs .area being developed by Mis. Jay Padmavati Builders Partnership Firm Th. Partner Shri. Prasanna V. Kankaraj & Other. 1. Following technical professionals are appointed by Owner I Promoter:- (i) Shri Ashok Jamdar as Licensed Engineer; (ii) Shri Ashok Jamdar as Structural Consultant Based on Site Inspection, with respect to each of the Buildings of the aforesaid Real Estate Project, I certify that as on the date of this certificate, the Percentage of Work done for each of the building of the Real Estate Project as registered vide number P51600022190under RERA is as per table A herein below. The percentage of the work executed with respect to each of the major activity of the Building / Wing and Overall Percentage of the work done with respect to each Building I Wing is detailed in the Table B. Table A "PADMA-VISHWA DREAM SQUARE" 1 Building Sr. No. Tasks / Activity Percentage 1 Excavation 100% 2 1 number of Plinth 100% 3 o number of Podiums N.A. 4 o Stilt Floor 100% 5 4 number of Slabs of Super Structure 100% 6 Internal Walls, Internal Plaster, Floorings within the Flat / Premises, 100% Doors and Windows to each of the Flat / Premises 7 Sanitary Fittings within the Flat / Premises, Electrical Fittings within 100% the Flat / Premises. 8 Staircases, Lifts Wells and Lobbies at each Floor level connecting 80% Staircases and Lifts, Overhead and Underground Water Tanks 9 External Plumbing and External Plaster, Elevation, Completion of 80% Terraces with Waterproofing of the Building / Wing 10 Installation of Lifts, Water Pumps, Fire Fighting Fittings and j Equipment as per CFO NOC, Electrical Fittings to Common Areas, Electro, Mechanical Equipment, Compliance to conditions of Environment / CRZ NOC, Finishing to Entrance Lobby/s, Plinth 50% Protection, Paving of areas appurtenant to Building / Wing, Compound Wall and all other requirements as may be required to obtain Occupation / Completion Certificate. TABLE - B "PADMA-VISHWA DREAM SQUARE" 1 Building Internal & External Development Works in Respect of the project Propose Percentag Common Roads and Sr. No. d e of Work Details Facilities, Amenities (Yes/No) done 1 Internal Roads and Footpaths No 0 NA 2 Water Supply Yes 0 Will be supplied by NMC 3 Sewerage (Chamber, Lines, Yes 0 Septic Tank, Will do Septic Tank, STP) before obtaining completion • • 4 Storm Water Drains No 0 NA 5 Landscaping and Tree Planting No 0 NA 6 Street Lighting Yes 0 By NMC 7 Community Buildings No 0 NA 8 Treatment and Disposal of No 0 NA Sewage and Salvage Water - No 9 Solid Waste Management and 0 NA Disposal 10 Water Conservation and Rain Yes 0 Will be completed before Water Harvesting obtaining completion 11 Energy Management No 0 NA 12 Fire protection and Fire Safety No 0 NA Requirements I 13 Electrical Meter Room, Sub- Yes 0 No separate room I Station, Receiving Station 14 Others (Option to add more) Licensed Engineer Er. Ashok Jamdar R.No - PElR121 Lie. No - 134199