SAGAR S. SHAH B.E.(Civil) M.I.E., FJ.V. Cell:9422247125 F.27433 E-mail: er.sagarshah@gmail.com Approved Valuer Consulting Engineer 54, Sahajeevan Colony, Visemala, College Road, Nashik 422 005 - ENGINEER'S CERTIFICATE (FORM2) To, Date: 14/08/2021 ANAND BUILDERS & DEVELOPERS 22, Sai Anand Rajpal Colony, Campound,, Makhmalabad Naka, Panchawati, Nashik 422003 Subject: Certificate of Cost Incurred for Development of SAI ARVIND Work of 1 Building situated on APARTMENT for Construction the Plot No. 4/5 (latitude and longitude of the end points) 12.00 Mbearing Survey No. 45/1/B/1 demarcated by its boundaries wide road to the North, Adj S. No. 45 to the Plot No. 6 to the East, Open Space to the West of Division NASHIK, Village Makhmalabad, TalukaSouth, District NASHIK, PIN 422003 NASHIK, BUILDERs & DEVELOPERS. admeasuring 177.11 Sq. Mtrs. area being developed by ANAND Ref: MahaRERA Registration Number P51600022144 Sir, I Er. R. K. Singh have undertaken assignment of certifying Estimated Cost for the Subject Real Estate Project proposed to be registered under MAHARERA, being 1 Building situated on the Plot No. 4/5 bearing Survey No. 45/1/B/1of Division NASHIK, Village Makhmalabad, Taluka NASHIK, District NASHIK, 422003 admeasuring 1 177.11 Sq. Mtrs. PN area being developed by ANAND BUILDERS & DEVELOPERS. Following technical professionals are appointed by Owner / Promoter :- (i) Ar. Hrishikesh K. Pawar Architect (ii) Er. R.K. Singh as Structural Consultant . We have estimated the cost of the completion to obtain Certificate, of the Civil, MEP and Allied works, of the Building Occupation Certificate/ Completion of the calculations are based on the Drawings/plans made available to us for the project. Our estimated cost Developer and Consultants and the Schedule of items and quantity for theproject under reference by the entire work as calculated by Er. R. K. Singh quantity Surveyor* appoi d by Developer/Engineer, and the assumption material, labour and other inputs made by developer, and the site inspection carried of out by us. the cost of AGAR Consulting i nginer Approved Valuer F-27433 ASHI 2. We estimate Total Estimated Cost of completion of the SAI ARVIND APARTMENT of the aforesaid project under reference as Rs. 4,49,75,000/- (In words Rupees Four Crores Forty Nine Lakhs Five Thousand Only) ( Total of Table A MEP and allied works and B). The estimated Total Cost of project is with referenceSeventy to the Civil, required to be completed for the purpose of obtaining occupation certificate completion certificate for the building from the Nashik under whose jurisdiction the aforesaid Municipal Corporation being the Planning Authority project is being implemented. 3. The Estimated Cost Incurred till date is calculated at Rs. amount of Estimated Cost Incurred is 4,49,75,000/- (Total of Table A and B). The calculated on the base of amount of Total Estimated Cost. 4. The Balance cost of Completion of the Civil, MEP and Allied works of the Building of the subject to obtain Occupation Certificate / Completion Certificate from Nashik Municipal Corporation (planning project Authority) is estimated at NIL ( Total of Table A and B). 5. I certify that the Cost of the Civil, MEP and allied work for the aforesaid Project as this certificate is as given in Table A and B below: completed on the date of TABLE A SAI ARVIND APARTMENT Sr. No. Particulars Amounts Total Estimated cost of the building Rs. 4,49,75,000/ as on 12.08.2019 date of Registration is Cost incurred as on 14/08/2021 Rs. 4,49,75,000/- (based on the Estimated cost) Work done in Percentage 100% as Percentage of the estimated cost) Balance Cost to be Incurred NIL Based on Estimated Cost) Cost Incurred on Additional /Extra Items as on Nil 14/08/2021 not included in the Estimated Cost (Annexure A) Consing ISH A p p r o v e dV a l u e r / F-27433 ASHI TABLE BB SAI ARVIND APARTMENT Sr. No. Particulars Amounts Total Estimated cost of Internal &External Nil Development Works including amenities and Facilities in the layout as on 12.08.2019 date of Registration is Cost incurred as on 14/08/2021 Nil based on the Estimated cost) Work done in Percentage Nil as Percentage of the estimated cost) Balance Cost to be Incurred Nil Based on Estimated Cost) Cost Incurred on Additional /Extra Items Nil as on 14/08/2021 not included in the Estimated Cost (Annexure A) RS Yours Faithfully Consulting Pproved Civil Valuer/i} Engineer P27433 Er. R. K. Singh ASH Signature of Engineer * Note 1. The scope of workisto complete entire RealEstate Project as per drawings approved from time to time so as to obtain Occupation Certificate /Completion Certificate. 2. As this is an estimated cost, any deviation in quantity required for development of the Real estate Project will result in amendment of the cost incurred/to be incurred. 3. All components of work with specifications are indicative and not exhaustive. Annexure A List of Extra / Additional Items executed with Cost (which were not part of the original Estimate of Total Cost) NIL