Annexure A FORM 1 [See Regulation 3] ARCHITECT’S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account) Date: 31/03/2022 To, Mr. Vijay Marutirao Raut Office:- S. No. 578/B/2, Raut Farm, Dhatrak Phata, Adgaon Shivar, Nashik -422 003. Subject : Certificate of Percentage of Completion of Construction Work of “YASHODA GARDEN” having MahaRERA Registration Number P51600022051 being developed by Mr. Vijay Marutirao Raut. Sir, I have undertaken assignment as Architect/Licensed Surveyor Sunil Bhor & Associates of Certifying Percentage of Completion of Construction Work of “YASHODA GARDEN” having MahaRERA Registration Number P51600022051 being developed by Mr. Vijay Marutirao Raut. Based on Site Inspection, with respect to each of the Building/Wing of the aforesaid Real Estate Project , I certify that as on the date of this certificate, the Percentage of Work done for each of the building/Wing of the Real Estate Project as registered vide number P51600022051 under MahaRERA is as per table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. Page 1 of 3 TABLE-A Layout / Building / Wing Number ‘1’ (To be prepared separately for each Layout/Building/Wing of Project) S. No. Tasks / Activity Percentage of Actual Work Done (As on date of the Certificate) (1) (2) (3) 1. Excavation 100% 2. Basements (if any) No 3. Podiums (if any) No 4. Plinth 100% 5. Stilt Floor 100% 6. Slab of Super Structure 100% 7. Internal Walls, Internal Plaster, Floorings, Doors, windows 100% within Flats / Premises 8. Sanitary Fittings within Flats / Premises 100% 9. Staircases, Lift Wells & Lobbies at each Floor Level 100% Overhead and Underground Water Tanks 10. External Plumbing & External Plaster, Elevation, Completion 100% of Terraces, with waterproofing of the Building / Wing 11. Installation of Lifts, Water Pumps, Fire Fighting Fittings and 100% Equipments as per CFO NOC, Electrical Fittings, Mechanical Equipments, Compliance to conditions of Environment / CRZ NOC, Finishing to Entrance Lobby/s, Plinth Protection, Paving of Areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete Project as per specifications to Agreement of Sale, Any other Activity TABLE-B Common Areas (Internal & External Development Works) in respect of the Registered Phase / Project Number S. No. Common Areas & Facilities Proposed Percentage of actual Work Details (Yes / NO) Done (As on date of Certificate) (1) (2) (3) (4) (5) 1. Internal Roads & Footpaths NO --- 2. Water Supply Yes 100% 3. Sewerage (Chamber, Lines, Septic Yes 100% Tank, STP) 4. Strom Water Drains Yes 100% 5. Landscaping & Tree Planting NO --- 6. Street Lighting NO --- Page 2 of 3 7. Community Buildings NO --- 8. Treatment & Disposal of Sewage and NO --- Sullage Water 9. Solid Waste Management & Disposal No --- 10. Water Conservation / Rainwater Yes 100% Harvesting 11. Energy Management NO --- 12. Fire Protection & Fire Safety NO --- requirements 13. Electrical Meter Room, Sub-Station, NO --- Receiving Station 14. Others (Option to Add more) NO --- Yours Faithfully, ER. SUNIL DATTU BHOR L.S./ Architect (License No. PELR102) Agreed & accepted by: Signature of Promoter Name: Mr. Vijay Marutirao Raut Date: Page 3 of 3