Table A Building –F –Wing F1 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 100 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 100% Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 100 % Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 100 % The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 100 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100 % Table A Building –F –Wing F2 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100% 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 100% Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 100 % Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 100 % Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 100 % The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 100 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100% Table A Building –G –Wing G1 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 100% Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 78% Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 10 % Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 70 % The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 12 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0% Table A Building –G –Wing G2 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 100 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 75 % Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 10 % Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 64 % The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 75 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 00% Table A Building –G –Wing G3 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 100 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 85 % Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 35% Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 70 % The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 50 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 00% Table A Building –G –Wing G4 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 100% Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 100 % Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 30 % Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 80 % The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 100 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 00% Table A Building –H –Wing H1 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 25 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 00 % Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 00 % Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 00 % The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 00 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 00% Table A Building –H –Wing H2 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 25 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 00 % Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 00 % Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 00 % The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 00 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 00% Table A Building –H –Wing H3 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 37 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 00 % Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 00 % Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 00 % The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 00 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 00 % Table A Building –H –Wing H4 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 37 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 00 % Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 00 % Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 00 % The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 00% Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 00% Table A Building –H –Wing H5 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100% 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 37 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 00 % Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 00 % Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 00 % The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 00 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 00 % TABLE-B Internal & External Development Works in Respect of the entire Registered Phase II Sr. Proposed Percentage No Common areas and Facilities, Amenities (Yes/No) of Work done Details Internal Paved Yes 70% 1 Internal Roads & Footpaths Driveways To be obtain Yes 80% 2 Water Supply from NMC Sewerage (chamber, lines, Septic Tank, Yes 80% Proposed 3 STP) Yes 100% Proposed 4 Storm Water Drains Landscaping & Tree planting Yes 00 % Proposed 5 6 Street Lighting Yes 50% Proposed Substation Electrical meter room, sub-station, receiving Yes 80 % complete, 7 station Proposed Proposed Yes 0% 8 Aggregate area of recreational open space Garden No 0% NA 9 Open Parking Club & Yes 100 % 10 Community Buildings Gymnasium Treatment and disposal of sewage and Yes 75% STP proposed 11 sullage water NMC Yes 50% 12 Solid Waste management & Disposal Ghantagadi Rain water Yes 50% 13 Water conservation, Rain water harvesting Harvesting Use Of CFL & Yes 50% 14 Energy management LED Lighting