6r. Sumit M Kumath Ar. Bansri S. Kumath New Lines ln Architecture Annexure A F'ORM 1 [See Regulation 3] ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project & for Withdrawal of Money from Designated Account) Date: 5.01 .2022 To, M/S Shweta Infrastructure & Housing (t) pvt. Ltd. Samraat Head Quarters, A33, Street-7, Satpur, Tal. & Dist. Nashik - 422 002 Subject: Certificate of Percentage of Completion of construction work of ,,samraat Apna Ghar Phase-ll "of the project situated on survey No. 50/2 shiwar Gangapur, Nashik, having Maha RERA Registration Number psl600020657 being Developed by M/s shweta lnfrastructure & Housing (l) pvt. Ltd. Sir, I i we have undertaken assignment as Architect of certifying percentage of completion of construction work of ,,samraat Apna cnjr ftrase-lt "oithe Project situated on survey No. 50/2 shiwar Gangapur, Nashik, having Maha RERA Registration Number ps1600020657 being Devetoped by M/s shweta lnfrastructure & Housing (l) pvt. Ltd. Based on the Site lnspection, with respect to the Layout / each BuildingAffing of the aforesaid Real EstateProject, I certify that as on date of this Certificate, the perce-ntage"of Work Done for each of the BuildingA//ing of the Real Estate Project under MahaRERA is iJ per Table-A herein below. The percentage of work executed with respect to each of the activity oi entire phase is detailed in Table-B. Mumbai Pune Goa Unit 8B, znd floor, G-28, Shirine Garden, B-ro5, Milroc Woods, Majithia lnd Estate, Parihar Chowk, Aundh Old Goa, Hari Narayan Kute Chembur-88. Pu ne-o7 Panjim-oz. Marg, Nashik-oz Mobile: 9594 z8o 767. E-mail : sumrtk:main @ gmai,.c rr-., Table A Building –F –Wing F1 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 100 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 100% Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 100 % Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 100 % The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 100 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100 % Table A Building –F –Wing F2 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100% 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 100% Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 100 % Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 100 % Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 100 % The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 100 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100% Table A Building –G –Wing G1 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 75% Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 0% Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 0% Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 0% The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 0% Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0% Table A Building –G –Wing G2 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 90 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 00 % Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 00 % Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 00 % The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 00 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 00% Table A Building –G –Wing G3 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 100 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 50 % Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 15% Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 10 % The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 00 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 00% Table A Building –G –Wing G4 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 100% Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 50 % Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 20 % Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 20 % The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 00 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 00% Table A Building –H –Wing H1 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 20 % 3 Number of Podiums NA 4 Stilt Floor 00 % 5 8 number of Slabs of Super Structure 00 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 00 % Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 00 % Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 00 % The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 00 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 00% Table A Building –H –Wing H2 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 00 % 3 Number of Podiums NA 4 Stilt Floor 00 % 5 8 number of Slabs of Super Structure 00 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 00 % Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 00 % Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 00 % The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 00 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 00% Table A Building –H –Wing H3 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 80 % 3 Number of Podiums NA 4 Stilt Floor 00 % 5 8 number of Slabs of Super Structure 00 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 00 % Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 00 % Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 00 % The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 00 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 00 % Table A Building –H –Wing H4 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 80 % 3 Number of Podiums NA 4 Stilt Floor 00 % 5 8 number of Slabs of Super Structure 00 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 00 % Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 00 % Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 00 % The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 00% Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 00% Table A Building –H –Wing H5 Percentage Sr. of work No Tasks /Activity done 1 Excavation 30 % 2 Plinth 00% 3 Number of Podiums NA 4 Stilt Floor 00 % 5 8 number of Slabs of Super Structure 00 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 00 % Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 00 % Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 00 % The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 00 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 00 % TABLE-B Internal & External Development Works in Respect of the entire Registered Phase Sr. Proposed Percentage No Common areas and Facilities, Amenities (Yes/No) of Work done Details Internal Paved 1 Internal Roads & Footpaths Yes 10% Driveways 50% To be obtain 2 Water Supply Yes from NMC Sewerage (chamber, lines, Septic Tank, 50% Proposed 3 STP) Yes 4 Storm Water Drains Yes 00% Proposed 5 Landscaping & Tree planting Yes 00 % Proposed 6 Street Lighting Yes 0% Proposed 80 % Substation Electrical meter room, sub-station, receiving complete, 7 station Yes Proposed 100% Proposed 8 Aggregate area of recreational open space Yes Garden 9 Open Parking Yes 0% Proposed 100 % Club & 10 Community Buildings Yes Gymnasium Treatment and disposal of sewage and 0% 11 sullage water Yes STP proposed 0% Ghantagadi Nashik Municiple 12 Solid Waste management & Disposal Yes corporation 0% Rain water 13 Water conservation, Rain water harvesting Yes Harvesting 5oo/o Use Of CFL & 14 Energy management Yes LED Lighting 15 Fire protection and fire safety requirements Yes 0% Proposed Yours Faithfully, AR. SUMIT KUMATH Reg: CA/2003132323 {{**oro of Promoter, Date. 5.01 .2022