Table A Building C – Wing D Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Podium 0% 4 Stilt Floor 100 % 5 15number of Slabs of Super Structure 100 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 100 % Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 100% Staircases, Lifts Wells and Lobbies at each Floor level connecting 8 Staircases and Lifts, Overhead and Underground Water Tanks 100% The external plumbing and external plaster, elevation, completion of 9 terraces with waterproofing of the Building/Wing, 100% Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 95%