Ar. Sumit M Kumath New Lines ln Architecture Annexure A FORM 1 [See Regulation 3] ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project & for Withdrawal of Money from Designated Account) Date: 5.01 .2022 To, M/S Shweta lnfrastructure & Housing (l) Pvt. Ltd. Samraat Head Quarters, A33, Street-7, Satpur, Tal. & Dist. Nashik - 422 007 Subject: cedificate of Percentage of completion of construction work of "samraat Apna Ghar Phase-l "of the Project situated on Survey No. 4gl1l2 Shiwar Gangapur, Nashik having Maha RERA Registration Number psI600020299 being Developed by M/S Shweta lnfrastructure & Housing (l) plrt. Ltd. Sir, I / we have undertaken assignment as Architect of certifying percentage of completion of construction work of "samraat Apna Ghar phase-t "of the Project situated on survey No.4gl112 shiwar Gangapur, Nashik having Maha RERA Registration Number P51600020299 being Developed by M/s Shweta lnfrastructure & Housing (l) Pvt. Ltd. Based on the Site lnspection, with respect to the Layout i each BuildingA/r/ing of the aforesaid Real Estate Project, I certify that as on date of this Certificate, the Percentagebf Work Done for each of the BuildingA//ing of the Real Estate Project under MahaRERA is as per Table-A herein below. The percentage of work executed with respect to each of the activity of entire phase is detailed in Table-B. ffiq gl .+s' 1 S$---iz Mumbai Pune Goa Unit 88, znd floor, G-28, Shirine Garden, B-ro5, Milroc Woods, 78, Business Bay, Shri Majithia lnd Estate, Parihar Chowk, Aundh Old Goa, Hari Narayan Kute Chembur-88. Pu ne-o7 Panjim-oz. Marg, Nashik-oz Mobile: 9594 z8o 767. E-mail sur^,r itkumain rDom aii.ccm Table A Building –A –Wing A1 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 100 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 85% Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 80 % Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 90 % The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 85 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 60 % Table A Building –A –Wing A2 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100% 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 100% Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 80 % Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 70 % Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 80 % The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 85 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 60% Table A Building –A –Wing A3 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 100% Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 80% Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 70 % Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 85 % The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 80 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 60% Table A Building –B –Wing B1 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 100 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 100 % Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 100 % Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 100 % The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 100 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100% Table A Building –B –Wing B2 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 100 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 100 % Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 100% Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 100 % The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 100 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100% Table A Building –B –Wing B3 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 100% Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 100 % Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 100 % Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 100 % The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 100 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100% Table A Building –C –Wing C1 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 40 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 0% Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 0% Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 0% The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 0% Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0% Table A Building –C –Wing C2 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 40 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 0% Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 0% Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 0% The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 0% Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0% Table A Building –C –Wing C3 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 25 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 0% Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 0% Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 0% The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 0% Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0% Table A Building –D –Wing D1 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 100 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 75% Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 50 % Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 90 % The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 70% Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 50% Table A Building –D –Wing D2 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100% 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 100 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 75 % Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 50 % Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 85 % The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 70 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 50% Table A Building –E –Wing E1 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100% 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 100 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 70 % Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 70 % Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 75 % The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 80 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 60% Table A Building –E –Wing E2 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 100 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 70% Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 70 % Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 75 % The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 75 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 50% Table A Building –E –Wing E3 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 100 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 60 % Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 65 % Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 70 % The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 80 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 50% Table A Building –E –Wing E4 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 100 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 80 % Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 80 % Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 85 % The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 75 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 50% Table A Building –E –Wing E5 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 100 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and 6 Windows to each of the Flat/Premises 85 % Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 Flat/Premises 80 % Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases 8 and Lifts, Overhead and Underground Water Tanks 85 % The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofing of the Building/Wing, 80 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing 10 to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 50% TABLE-B Internal & External Development Works in Respect of the entire Registered Phase Sr. Proposed Percentage No Common areas and Facilities, Amenities (Yes/No) of Work done Details Internal Paved 1 Internal Roads & Footpaths Yes 50% Driveways 50% To be obtain 2 Water Supply Yes from NMC Sewerage (chamber, lines, Septic Tank, 50% Proposed 3 STP) Yes 4 Storm Water Drains Yes 50% Proposed 5 Landscaping & Tree planting Yes 50 % Proposed 6 Street Lighting Yes 0% Proposed 80 % Proposed, Electrical meter room, sub-station, receiving Substation 7 station Yes complete 100% Proposed 8 Aggregate area of recreational open space Yes Garden 9 Open Parking Yes 0% Proposed 80 % Club & 10 Community Buildings Yes Gymnasium Treatment and disposal of sewage and 0% 11 sullage water Yes STP proposed 0% Ghantagadi Nashik Municiple 12 Solid Waste management & Disposal Yes corporation 0% Rain water 13 Water conservation, Rain water harvesting Yes Harvesting 50% Use Of CFL & 14 Energy management Yes LED Lighting 15 Fire protection and fire safety requirements Yes Oo/o Proposed Yours Faithfully, AR. SUMIT KUMATH Reg: CA/2003132323 kq Signature of Prornffer, Name: M/S Shweta lnfrastrucutre & Housing (l) Pvt. Ltd. Date: 5.01 .2022