Table A Building –A –Wing A1 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 100 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows 40% 6 to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical Fittings within the Flat/Premises 0% Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, 8 Overhead and Underground Water Tanks 0% The external plumbing and external plaster, elevation, completion of terraces with 9 waterproofing of the Building/Wing, 10 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance 10 lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0% 2 Table A Building –A –Wing A2 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100% 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 100% Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows 30 % 6 to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical Fittings within the Flat/Premises 0% Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, 8 Overhead and Underground Water Tanks 0% The external plumbing and external plaster, elevation, completion of terraces with 9 waterproofing of the Building/Wing, 10 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance 10 lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0% 3 Table A Building –A –Wing A3 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 100% Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows 30% 6 to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical Fittings within the Flat/Premises 0% Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, 8 Overhead and Underground Water Tanks 0% The external plumbing and external plaster, elevation, completion of terraces with 9 waterproofing of the Building/Wing, 05 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance 10 lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0% 4 Table A Building –B –Wing B1 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 100 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows 85 % 6 to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical Fittings within the Flat/Premises 50 % Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, 8 Overhead and Underground Water Tanks 80 % The external plumbing and external plaster, elevation, completion of terraces with 9 waterproofing of the Building/Wing, 80 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance 10 lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0% 5 Table A Building –B –Wing B2 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 100 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows 90 % 6 to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical Fittings within the Flat/Premises 50% Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, 8 Overhead and Underground Water Tanks 70 % The external plumbing and external plaster, elevation, completion of terraces with 9 waterproofing of the Building/Wing, 80 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance 10 lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0% 6 Table A Building –B –Wing B3 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 100% Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows 90 % 6 to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical Fittings within the Flat/Premises 50 % Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, 8 Overhead and Underground Water Tanks 75 % The external plumbing and external plaster, elevation, completion of terraces with 9 waterproofing of the Building/Wing, 80 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance 10 lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0% 7 Table A Building –C –Wing C1 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 20 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows 0% 6 to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical Fittings within the Flat/Premises 0% Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, 8 Overhead and Underground Water Tanks 0% The external plumbing and external plaster, elevation, completion of terraces with 9 waterproofing of the Building/Wing, 0% Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance 10 lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0% 8 Table A Building –C –Wing C2 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 83 % 3 Number of Podiums NA 4 Stilt Floor 0% 5 8 number of Slabs of Super Structure 0% Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows 0% 6 to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical Fittings within the Flat/Premises 0% Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, 8 Overhead and Underground Water Tanks 0% The external plumbing and external plaster, elevation, completion of terraces with 9 waterproofing of the Building/Wing, 0% Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance 10 lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0% 9 Table A Building –C –Wing C3 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 80 % 3 Number of Podiums NA 4 Stilt Floor 0% 5 8 number of Slabs of Super Structure 0% Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows 0% 6 to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical Fittings within the Flat/Premises 0% Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, 8 Overhead and Underground Water Tanks 0% The external plumbing and external plaster, elevation, completion of terraces with 9 waterproofing of the Building/Wing, 0% Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance 10 lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0% 10 Table A Building –D –Wing D1 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 100 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows 60% 6 to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical Fittings within the Flat/Premises 0% Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, 8 Overhead and Underground Water Tanks 0% The external plumbing and external plaster, elevation, completion of terraces with 9 waterproofing of the Building/Wing, 20% Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance 10 lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0% 11 Table A Building –D –Wing D2 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100% 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 100 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows 60 % 6 to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical Fittings within the Flat/Premises 0% Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, 8 Overhead and Underground Water Tanks 0% The external plumbing and external plaster, elevation, completion of terraces with 9 waterproofing of the Building/Wing, 30 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance 10 lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0% 12 Table A Building –E –Wing E1 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100% 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 100 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows 50 % 6 to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical Fittings within the Flat/Premises 0% Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, 8 Overhead and Underground Water Tanks 0% The external plumbing and external plaster, elevation, completion of terraces with 9 waterproofing of the Building/Wing, 0% Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance 10 lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0% 13 Table A Building –E –Wing E2 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 100 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows 50% 6 to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical Fittings within the Flat/Premises 0% Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, 8 Overhead and Underground Water Tanks 0% The external plumbing and external plaster, elevation, completion of terraces with 9 waterproofing of the Building/Wing, 0% Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance 10 lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0% 14 Table A Building –E –Wing E3 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 100 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows 35 % 6 to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical Fittings within the Flat/Premises 0% Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, 8 Overhead and Underground Water Tanks 0% The external plumbing and external plaster, elevation, completion of terraces with 9 waterproofing of the Building/Wing, 0% Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance 10 lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0% 15 Table A Building –E –Wing E4 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 100 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows 40 % 6 to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical Fittings within the Flat/Premises 0% Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, 8 Overhead and Underground Water Tanks 0% The external plumbing and external plaster, elevation, completion of terraces with 9 waterproofing of the Building/Wing, 0% Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance 10 lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0% 16 Table A Building –E –Wing E5 Percentage Sr. of work No Tasks /Activity done 1 Excavation 100 % 2 Plinth 100 % 3 Number of Podiums NA 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 100 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows 40 % 6 to each of the Flat/Premises 7 Sanitary Fittings within the Flat/Premises, Electrical Fittings within the Flat/Premises 0% Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, 8 Overhead and Underground Water Tanks 0% The external plumbing and external plaster, elevation, completion of terraces with 9 waterproofing of the Building/Wing, 10 % Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance 10 lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0% 17