AR.MANISH JADHAV ARCHITECTS 3,SURHUD SOCIETY, RAMDAS COLONY CANADA CORNER,NASHIK-2 PH.-(0253)3554219 CELL-9422263711 jadhav.manish744@gmail.com FORM 1 [ see Regulation 3] ARCHlTEcrS CERTIFICATE 0'0 be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account) To, Date 31/03/2021 Mr. Nitin DayalalKothari, 27, Swastik,Chauhan Nagar,Tapovan Road, Tapovan,Panchvati,Nashik - 422003. Subject: Certificate of Percentage of Completion of Construction Work of Monsoon Mist No. of Building one of the Project PS1600019135situated in Mauje Pardevi Shiwar on the Plot bearing Survey No./GAT No. 279/1/2 &: 30/3S/C-Part, Plot No. 01 Hissa No. 04 demarcated by its boundaries demarcated by its boundaries 24 Mts Road to the North 12Mts Road to the South Plot No. 04 &: Amenity Plot to the East 12 Mts Road to the west of Division Nashik Village Pardevi Taluka Igatpuri District Nashik PIN 422402. Total Plot Area 8,843.60 Sq. Mtr. having a Total Approved Area for Construction 15,380.33 Sq. Mts. Out of Total Approved Area 3,408.99 Sq. Mts. proposed for a building Monsoon Mist. And Balance Area is 11,971.34Sq. Mts. willbe utilizing for another project in future which is duly authorized by the Promoter of the proposed project being developed by Mr. Nitin Dayalal Kothari. Sir, 1/ We Manish Jadhav have undertaken assignment as Architect /Licensed Swveyor of certifying Percentage of Completion of Construction Work of the Monsoon Mist BuDding of the Project in Mauje Pardevi Shiwar, situated on the plot bearing Survey No./GAT No. 279/1/2 and 30/3S/C-Part Final Plot No. 01 Hissa No. 04 of Division Nashik Village Pardevi Taluka 19atpuri District Nashik PIN 422402 admeasuring 3,408.99 Sq. Mts. area being developed as a project Monsoon Mist by Mr. Nitin Dayalal Kothari. 1. Followingtechnical professionals are appointed by Owner / Promoter :-- (i) M/s/ShriISmt. Manish Jadhav as L.S. I Architect ; (ii) MIs IShri I Smt. Vijay B.Amesure as Structural Consultant (iii) M/s /Shri / Smt. as MEP Consultant (iv) MIs IShri I Smt. Sandip Jain as Site Supervisor Based on Site Inspection, with respect to the Building of the aforesaid Real Estate Project, I certify that as on the date of this certificate, the Forty Percentage of Work done for the building of the Real Estate Project as registered vide number PSI600019135 under Maha-RERAis as per table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed inTable B. hvaG.uDay ••••• TABLE-A Building Monsoon Mist Sr. Tasks / Activity Percentage of No. (2) work done (3) (1) 1 Excavation 100% 2 One Number of Plinth 10096 3 number of Podiums -NA- 4 Stilt Floor -NA- 5 Five number of Slabs of Super Structure 7096 Internal Walls, Internal Plaster, Floorings within Flats/Premises1 Doors and 6 Windows to each of the Flat/Premises. 9% 1-. Sanitary Fittings within the Flat/Premises, Electrical Fittings within the 7 0% FlatLPremises. r- Staircases, lifts Wells and Lobbies at each Floor level connecting Staircases and 8 Liftst Overhead and Underground Water Tanks. 30% The external plumbing and external plaster, elevation, completion of terraces 9 with waterproofina of the BuildilWWing. 0% Installation oflifts, water pumps, Fire Fighting Fittings and Equipment 88 per CFO Noc, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance 10 to conditions of environment ICRZ Noc, Finishing to entrance lobby/s, plinth 0% protection, paving of areas appurtenant to Building/Wing,Compound Wall and all other requirements as may be required to obtain Occupation I Completion Certificate. TABLE-B Internal and External Development Works in respect of the entire Registered Phase. Sr. Common areas and Facilities, Amenities Proposed Percentage of Details No. (2) (Yes/No) Work done (5) (1) (3) (4) 1 Internal Roads & Footpgths YES 50% Under Development 2 Water Supply YES 0% Under Construction 3 Sewerage (chamber, lines, Septic Tank, STP). YES 0% Under Construction 4 Storm Water Drains NO --NA- 5 Landscaping &Tree Planting_. YES 6% Under Construction 6 Street Lighting YES 50% Under Development 7 Community Buildimts NO -NA- 8 Treatment and disposal of sewage and Soak Pit Under sullage water. YES 096 Development 9 Solid Waste management & ....... . .1 NO NA- 10 Water conservation, Rain water harvesting. YES 096 Under Construction 11 Energy management NO -NA- 12 - Fire protection and fire safe~uirements. NO -NA- 13 Blectrical meter room, sub-station, receiving station. YES 096 Under Construction 14 YES 096 Under Construction 15 Others (Option to Add more). ,~ ~~A.() - Name ofLS/ Archi~t.. ~....-v0W8 Faitbfu lly, H PRABHAICARJAD HAV (License No. CA/2016/75326)