FORM - 1 (See Regulation 3) ARCHITECT’S CERTIFICATE (To be submitted at the time of Registration of Ongoing project and for Withdrawal of Money from Designated Account) Date: 26/03/2026 To, M/s. Sai Samarth Construction Through its Partner Mrs. Aher Sandhya Kailas, and others Office No. 01, Sai Samarth Park Opp. Guru Govind Singh School, Rane Nagar, Nashik, Maharashtra, 422 009 Subject: Certificate of percentage of completion of construction work of “Aai Residency” having MahaRERA Registration Number P51600077976 being developed by M/s. Sai Samarth Construction. Sir, We M/s Kapil Thakkar & Associates have undertaken the assignment as Architect/Licensed Surveyor of certifying percentage of Completion of Construction work of the “Aai Residency” having MahaRERA Registration Number P51600077976 being developed by M/s. Sai Samarth Construction. Based on site Inspection, with respect to the layout/each of the building/wing of the aforesaid Real Estate project. I certify that as of the date of this certificate, the percentage of work done for each of the buildings/wings of the Real Estate project under MahaRERA is as per table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. Table A Layout/Building Aai Residency Sr. No. Task/Activity Percentage of actual work done (As on the date 04/01/2019) (1) (2) (3) 1. Excavation 100% 2. Basements (if any) NA 3. Podiums (If any) NA 4. Plinth 100% 5. Stilt Floor 100% 6. Slabs of Super Structure 100% 7. Internal Walls, Internal Plaster, Floorings, Doors, and Windows 100% Within Flats /Premises 8. Sanitary Fittings Within the Flat/Premises 100% 9. Staircases, Lifts Wells, and Lobbies at each Floor level overhead 100% and Underground Water Tanks 10. External plumbing and external Plaster, Elevation, completion of 100% terraces with waterproofing of the building/wing. 11. Installation of Lifts, Water pumps, Fire Fighting Fittings and 100% Equipment as per CFO NOC, Electrical Fittings, Mechanical Equipment, Compliance to conditions of environment / CRZ NOC, finishing to entrance Lobby/s, plinth Protection, paving of areas appurtenant to Building/Wing, Compound wall and all other requirements as may be required to complete the project as per specifications in the agreement of sale. Any other activities. Table B Common Areas (Internal & External Development Works) in respect of the registered phase /Project number Sr. No. Common areas and Proposed Percentage of Details Facilities, Amenities (Yes/No) Actual Work Done (As on date 04/01/2019) (1) (2) (1 (1) (2) (3) (4) (5) 1. Internal Roads and No NA NA Footpaths 2. Water Supply Yes 100% Borewell and Water Connection After Completion 3. Sewerage (Chamber, Lines, Yes 100% No STP Septic Tank, STP) 4. Storm Water Drains No NA NA 5. Landscaping &Tree Planting Yes 100% Only Tree Planting 6. Street Lighting No NA NA 7. Community Buildings No NA NA 8. Treatment and Disposal of No NA NA Sewage and Sullage water 9. Solid Waste Management & No NA NA Disposal 10. Water Conservation/Rain Yes 100% Only Rain Water Harvesting Water harvesting 11. Energy Management No NA NA 12. Fire Protection and Fire No NA NA Safety Requirements 13. Electrical meter room, Sub- Yes 100% Only Electrical Meter Box Station, Receiving station 14. Others (Option to Add more) No NA NA Yours Faithfully For, Shriniwas Consultant Mr. D. B. Gavhane Licenses No. 352 Agreed and accepted by: For, M/s. Sai Veer Construction Signature of Promoter Name: Mr. Sudhir Subhash Ghule Designation: Proprietor Date: 26/03/2026