Annexure - B FORM - 2 [See Regulation 3] ENGINEER'S CERTIFICATE (To be su bmitted at the time of Registration of Ongoing Project and for Withdrawal of Money from Designated Bank Account) Date:13-04-2023 To, The Mr. Mukesh Dhanraj More, Flat No. A-802, Opal Enclave, Govind Nagar Ring Road, Karmyogi Nagar, Nashik-422009) Subject: Certificate of Cost Incurred for Development ofSKPRIDE having MahaRERA Registration Number P51600016983 (only applicable after Project Registration) being Developed by Mr. Mukesh Dhanraj More Sir, 1. TSandeep Kisan Hatagale have undertaken assignment of Certifying Estimated Cost for S K PRIDE having MahaRERA Registration Number P51600016983 (Only applicable after Project Registration) being Developed by Mr. Mukesh Dhanraj More 2. We have estimated the cost of Civil, MEP and Allied Works required for completion of the apartments & proportionate completion of internal & external workS of the Project as per the specifications mentioned in the Agreement of Sale. Our estimated cost calculations are based on the Drawings/Plans made available to us for the Project under Reference by the Developers / Consultants. The Schedule of Items & Quantity required for the entire work as calculated by Quantity Surveyor* appointed by the Developer/Engineer, the assumption of the cost of material, labour & other inputs made by the Developer, and the Site Inspection carried out by us to ascertain/ confirm the above analysis given to us. under 3. We estimate Total Estimated Cost of completion of the aforesaid Project mentioned reference at Rs. 85,00,000/- (Total of Table A & B) at the time of Registration. The estimated completion of the Total Cost of Project is with reference to the Civil, MEP & Allied Works specifications apartments & proportionate completion of internal & external works, as per the Certificate / mentioned in the Agreement of Sale & for the purpose of obtaining Occupation Completion Certificate for the Building(s) /Wing(s) /Layout /Plotted Development from the being being implemented. the Planning Authority under whose jurisdiction the aforesaid Project is A & B). The 4. The Estimated Cost incurred till date is calculates to Rs. 74,02,882/- (Total of Table Amount of Estimated Cost Incurred is calculated on the basis of input materials / services used & unit cost of these items. 5. The Balance Cost of completion of the Civil, MEP & Allied Works for completion of Apartments & proportionate completion of internal & external works, as per specifications mentioned in Agreement of Sale, of the aforesaid Project is estimated at Rs. 10,97,1 18/- (Total of Table A & B). 6. I Certify that the cost of Civil, MEP & Allied Work for apartments & proportionate internal & external works, as per the specifications mentioned in Agreement of Sale, of the aforesaid Project as completed on the date of this certificate is as given in Table A & B below: TABLE - A Building /Wing / Layout / Plotted Development bearing Number or called (to be prepared separately of each Building/Wing / Layout / Plotted Development of the Real Estate Project) S. No. Particulars Amount (in Rs.) 1 Total Estimated Cost of Building / Wing/Layout / Plotted 85,00,000/ Development as on date of Registration is 2. Cost incurred as on date of Certificate 74,02,882/ 3 Work Done in Percentage (as Percentage of Estimated 87.09% Cost) 4. Balance Cost to be incurred ** (based on Estimated 10,97,118/ Cost) 5 Cost incurred on Additional / Extra ltems not included in NIL the Estimated Cost (Table-C) TABLE - B Internal & External Development Works in respect of Registered Phase S. No. Particulars Amount (in Rs.) 1 Total Estimated Cost of Internal &External Development NIL Works incuding amenities &facilities in the Layout as on date of Registration is 2. Cost incurred as on date of Certificate NIL 3 Work Done inPercentage (as Percentage of Estimated NIL Cost) 4. Balance Cost to be incurred ** ((based on Estimated NIL Cost) 5. Cost incurred on Additional /Extra Items not included in NIL the Estimated Cost (Table-C) Yours faithfully, Signature &Name (Sandeep Kisan Hatagale ) with Stamp of Engineer [Not less than Bachelor's Degree Holder or cquivalent as per Section 2(u) of the Act! Local Authority License Number (if applicable) Agreed &Accepted by: Signature of Promoter Name: Mr. Mukesh More Date:14-04-2023 Note: 1. The scope of work is to complete Registered Real Estate Project as per drawings approved from time to time as per specifications mentioned in the Agreement to Sale. 2. (") Quantity Survey can be done by the office of Engineer or can be done by an independent Quantity Surveyor, who's Certificate of Quantity Calculated, can be relied up on by Engineer. In case of independent quantity surveyor being appointed by Developer, the name has to be mentioned at the place marked (") & in case quantity are being calculated by office of Engineer, the name of person in the office of Engineer, who is responsible for the quantity calculatedshould be mentioned at the place marked ("). 3. (*") Balance Cost to be incured (4) may vary from difference between Total Estimated Cost (1) &actual Cost incurred (2) due to deviation in quantity required / escalation of cost etc. As this is an Estimated Cost any deviation quantity required for the Development of Real Estate Project will result in an amendment of the cost incurred/ to be incurred. 4. Al components of work with specifications are indicative ¬ exhaustive 5. Please speciĆ­y if there are any deviations /qualifications. Example: Any deviation in input material used from specifications in Agreement of Sale. TABLE - C List of Extra / Additional/Deleted Items considered in the Cost (Which were not parts of the original Estimate of Total Cost) S. No. List of Extra / Additional /Deleted Items Amount (in Rs.) 1. 2.