202, Second Floor, Roongta Arcade, 0pp. Kulkarni Garden, Sharanpur Road, Nashik-422001. Ph 0253 - 2232575. e-mail jadhavpankoj02@gmail.com Ar. Pankaj Jadhav Annexure A FORM I (See Regulation 3) ARCHITECTtS CERTI FICATE (To be submif ted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account) Date: 27/05/2023 To, VIVA HIGHWAYS LIMITED S. No 113/2 3rd Floor, Ashoka Business Enclave, Wadala Road, Nashik-4220010 Subject: Certificate of Percentage of Completion of Construction Work of Project Atharva Heights having MahaRERA Registration Number P51600015843 (only Application after project Registration) being developed by Viva Highways Limited Sir, I/We have undertaken assignment as Architect /Licensed Surveyor of certifying Percentage of Completion of Construction Work of Atharva Heights having Maha RERA Registration Number P51600015843 being developed by Viva Highways Limited. Based on Site inspection, with respect to Layout / each of the Building/Wing of the aforesaid Real Estate Project. I certify that as on the date of this certificate, the Percentage of Work done for each of the building/Wing of the Real Estate Project under MahaRERA is as per Table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. Ar. Pankaj P. Jadhav B. Arch. CA/2014/64783 Office No. 202, Rungta Arcade Apartment Opp. Kulkarni Garden, Sharanpur Road, Nashik-422 005 TABLE-A Layout/Building/Wing Number 'Wing A' (to be prepared separately for each Layout/Building /Wing of the Project) Percentage of Actual Work Sr. Done Tasks / Activity No (as on date of the (I) Certificate) (3) 1. Excavation 100% RCC-1 00%.waterproofing- 2. Basements (if any) 100%,Fnishing-0% 3. Podiums (if any) - 4. Plinth 100% RCC-90%,waterproofing- 5 Stilt Floor %,Finishing-10% 6. SlabsofSuperStructure 100% internal walls, internal Plaster, Floorings, doors and Infernal wall-i 00%, Internal plaster- 7. windows within Flats/Premises 85%, Flooring-40%. Doors & windows within flat/premises-i 0%. 8. Sanitary Fittings within the Flats/Premises 10% Staircases. lifts Wells and Lobbies at each Floor level Staircase-90%, Lift wells & lobbies at Overhead and Underground Water Tanks each floor level-90%. Overhead 9 water tank-25%, Underground water tank-95%. External plumbing and external plaster, elevation, External plumbing-25%, External completion of terraces with waterproofing of the plaster-7%, elevation, completion 10 of terraces with waterproofing of Building/wing, the Building /wing-0% Installation of lifts, water pumps, Fire Fighting Fittings and Installation of lifts commertial-80%. Equipment as per CFO NOC, electrical fittings, water pumps-0%. Fire Fighting mechanical equipment, compliance to Fittings and Equipment as per CFO Conditions of environment /CRZ NOC. Finishing to NOC, electrical fittings. mechanical entrance lobby/s. plinth protection, paving of areas equipment, compliance to appurtenant to Building/Wing. Compound Wall Conditions of environment /CRZ and all other requirements as may be required to NOC-Comrnertial-90% & residential- complete project as per 20%. Finishing to entrance Iobby/s- Specifications in agreement of Sale. Any other activities. 25%. plinth protection- NA, paving of areas appurtenant to 11 Building/Wing -0%. Compound Wall -90% and all other requirements as may be required to complete project as per Other activities (terrace garden with jogging track, community hall, garbage chute, rainwater harvesting, ground and basement parklng)-0%. Ar. Pan P. Jadhav B. Arch. CA/2014/64 783 Office No. 202, Rungta Arcade Apartment Opp. Kulkarni Garden, SharanoUr Road. Nashik-422 005 TABLE-A Layout/Building/Wing Number Wing B' (to be prepared separately for each Layout/Building /Wing of the Project) Percentage of Actual Work Sr. Done Tasks / Activity (as on date of the No (2) Certificate) (I) (3) 1. Excavation 100% RCC-100%,waterprooflng- 2. Basements (if any) 100%, Finish ing-0% 3. Podiums (if any) - 4. Plinth 100% RCC- 5. Stilt Floor 1 00%,waterproofingo%,Finishing-0% 6. Slabsof SuperStructure 100% internal walls, internal Plaster, Floorings, doors and internal walls-100%, internal Plaster- 7. windows within Flats/Premises 80%. Floorings-0%, doors and windows within Flats/Prernises-0% 8. Sanitary Fittings within the Flats/Premises 5% Staircases. lifts Wells and Lobbies at each Floor level Staircase-85%, Lift wells & lobbies at Overhead and Underground Water Tanks each floor level-42%, Overhead 9 water tank-0%, Underground water tank-95%. External plumbing and external plaster, elevation, External plumbing-0%. external completion of terraces with waterproofing of the plaster-0%. elevation, completion 10 of terraces with waterproofing of Building/wing. the Building/wing-0% Installation of lifts, water pumps, Fire Fighting Fittings and Installation of lifts-0%. water pumps- Equipment as per CFO NOC, electrical fittings. 0%, Fire Fighting Fittings and mechanical equipment, compliance to Equipment as per CFO NOC. Conditions of environment /CRZ NOC. Finishing to electrical fittings, mechanical entrance lobby/s. plinth protection. paving of areas equipment, compliance to appurtenant to Building/Wing. Compound Wall Conditions of environment /CRZ and all other requirements as may be required to NOC-25%. Finishing to entrance complete project as per lobby/s-0%. plinth protection-NA. Specifications in agreement of Sale. Any other activities, paving of areas appurtenant to Building/Wing-0%. Compound Wall 11 90%. and all other requirements as may be required to complete project as per Specifications in agreement of Sale. Other activities (terrace garden with jogging track, community hail, garbage chute, rainwater harvesting, ground and basement parking)-0%. Ar. Pankaj P. Jadhav B. Arch. CA/20].4/64783 Office No. 202, Rungta Arcade Apartment Opp. Kulkarni Garden, Sharanpur Road, Nashik-422 005 TABLE- B Common Areas (Internal and External Development Works) in respect of the Registered Phase! Project Number- P51600015843 Sr. No Common areas and Proposed Percentage of Details (1) facilities (Yes I No) Actual Work Done (s) (2) (3) (As on date of the Certificate) (4) 1. Internal Roads & No Footpaths 2. Water Supply Yes 30% 3. Sewerage (Chamber, Yes 10% lines, Septic tank, SIP) 4. Storm Water Drains Yes 10% 5. Landscaping & Tree Yes 0% Planting 6. Street Lighting No - 7. Community Buildings Yes Community hail at wing A 8. Treatment and disposal Yes 35% of sewage and sullage water. 9. Solid Waste Yes 10% management & Disposal 10. Water conservation / No - Rain water harvesting 11. Energy management No - 12. Fire protection and lire Yes 30% safety Requirements 13. Electrical meter room, Yes 15% sub-station, receiving station. 14. Others (Option to Add Yes 0% more): Driveway Yours Faithfully, For, Ar. Pankaj Jadhav Agreed and Accepted by For, Viva Highways Limited Mr. Anup S. Katarlya Architet CA/204/64783 Director Ar. Pankaj P. Jadhav DIN: 08574432 B. Arch. CA/2014/64783 Office No. 202, Rungta Arcade Apartment Opp. Kulkarni Garden, Sharanpur Road, Nashik.422 005