Ar. ShitalWaluni Ar. DhiraiWalunj # +91 9890191058 # +91 90114 36516 Reg. No.: CAi201 0/48551 Reg. No.: CA/2005/36699 architectur€ r interior r landscape designers ARCHITECTS Form 1 (See Regulation 3) ARCHITE CT'S CERTIFICATE ffo be submitted at the time of Registration of Ongoing project and for Withdrawal of Money from Designated Account) Date:23.07.2026 To, K B Rohamare Housing Private Limited, 25, VitthalCharani, Opp Big Bazar, College Road, Nashik 422005. Subject: Certificate of percentage of completion of construction work of "Manomay Natures Paradize"having MahaRERA Registration Number:P5l500014658being developed by K B Rohamare Housing Private Limited. Sir, WeDhirajWalunj&ShitalWalunjhave undertaken assignment as Architect/Licensed Surveyor of certifying percentage of Completion of Construction work of the"Manomay Natures Paradize"having MahaRERA Registration Number:P51600014658being developed by K B Rohamare Housing Private Limited. I Basecl on site Inspection, with respect to layout/each of the building/wng of the aforesaicl Real Estate project. I certify that as on the clate of this certificate, the percentage of work done fo- each of the building/wing of the Real Estate project under MahaRERA is as per table A herein below.The perceniage of the work executed with respect to each of the activity of the entire phase is cletailed in table B. [?[Ui-j.I,]H8,',"[g] Autho Office No. 308, Business Court, ln front of lndco Park Apartment, Govind Nagar, Nashik - 422 001 . Email : vastumitras@gmail.com Table A Layout/Building/Wing NoLily Studio Wing-A,B,C&D Sr. No. Task/Activity Percentageof acfual work done (As on 30.06.2026) (1) (2) (3) 1,. Excavation 100% 2. Basements (if any) J. Podiums (If any) 100% 4. Plinth 100% 5. Stilt Floor 100% 6. Slabs of Super Structure 1,00% 7. Internal Walls,lnternal Plaster, Floorings, Doors and Windows 700% Within Flats /Premises B. Sanitary Fittings Within the Flat/Premises 2s% 9. Staircases, Lifts Wells and Lobbies at each Floor level overhead 100% and Underground Water Tanks 10. External plumbing and external Plaster, Elevatiory completion 50% ofterraces with waterproofing of the building/wing. 11. Installation of Lilts, Water pumps,Fire Fighting Fittings and 25% Equipment as per CFO NOC, Electrical Fittings, Mechanical Equipment,Cpmpliance to conditions ofenvironment / CRZ NOC, finishing to entrance Lobby /s,plinthProtection, paving of areas appurtenant to Building/l{tng,Compound wall and all other requirements as may berequired to complete the project as per specifications in agreement of sale. Any other activities' Signatory Layout/Building/Wing NoD#fodil Row Bungalow- 37 to 42 Sr. No. Task/Activity Percentageof actual work done (As on 30.06.2025) (1) (2) (3) 1. Excavation 100% 2. Basements (if any) J. Podiums (If any) 4. Plinth 100% 5. Stilt Floor 100% 6. Slabs of Super Structure 700% 7. Internal Walls,Internal Plaster, Floorings, Doors and Windows 700% Within Flats /Premises B. Sanitary Fittings Within the Flat/Premises 100% 9. Staircases, Lifts Wells and Lobbies at each Floor level overhead 100% and Underground Water Tanks 10. External plumbing and external Plaster, Elevatiory completion 100% ofterraces with waterproofing of the building/wing. 11. Installation of Lifts, Water pumps,Fire Fighting Fittings and 100% Equipment as per CFO NOC, Electrical Fittings, Mechanical Equipment,Compliance to conditions ofenvironment / CRZ NOC, finishing to entrance Lobby/s,plinthProtection, paving of areas appurtenant to Building/Wing,Compound wall and a1l other requirements as may berequired to complete the project as per specifications in agreement of sale. Any other activities. [PJk'J,tt[#l,"'.tl] ou.nN'iiienatory Layout/Buitding/Wing NoDaffodil Row Bungalow- 43 to 48 3r. No. Task/Activity Percentageof actual work done (As on 30.06.2026) (1) (2) (3) 1. Excavation 100% 2. Basements (if any) J. Podiums (If any) 4. Plinth 100% 5. Stilt Floor 700% 6. Slabs of Super Structure 1.00% 7. Internal Walls,Internal Plaster, Floorings, Doors and Windows 100% Within Flats /Premises 8. Sanitary Fittings Within the Flat/Premises 700% 9. Staircases, Lifts Wells and Lobbies at each Floor level overhead 700% and Underground Water Tanks 10. External plumbing and external Plaster, Elevatioru completion 100% ofterraces with waterproofing of the building/wing. 11. Installation of Lifts, Water pumps,Fire Fighting Fittings and 700% Equipment as per CFO NOC, Electrical Fittings, Mechanical Equipment,Compliance to conditions ofenvironment / CRZ NOC, finishing to entrance Lobby / s,plinthProtection, paving of areas appurtenant to Building/Wing,Compound walland all other requirements as may berequired to complete the project as per specifications in agreement of sale. Any other activities. (Dhirai T. Walunj) B. nncr --ce,l 2 Po sl 36699 \$x tuthoiluEd Signatory Layout/Building/Wing NoDaffodil Row Bungalow- 49 to 54 Sr. No. Task/Activity Percentageof acfual work done (As on 30.06.2026) (1) (2) (3) 1. Excavation 700y" 2. Basements (if any) J. Podiums (If any) 4. Plinth 700% 5. Stilt Floor 0% 6. Slabs of Super Structure 50% 7. Internal Walls,Internal Plaster, Floorings, Doors and Winclows 700% Within Flats /Premises B. Sanitary Fittings Within the Flat/Premises 740% 9. Staircases, Lifts Wells and Lobbies at each Floor lerrul o,rurt 1,00% and Underground Water Tanks "*i 10. External plumbing and external Plaster, Eleration, corrrpletior, 700% ofterraces with waterproofing of the building/wing. 11. Installation of Lifts, Water pumps,Fire Fighting Fittings and 700% Equipment as per CFO NOC, Electrical Fittings, Mechanical EquipmenlCompliance to ccnditions ofenvironment / CRZ NqC, finishing to entrance Lobby /s,plinthProtection, paving of areas appurtenant to Building/\Nng,Compound wall and all other requirements as may berequired to complete the project as per specifications in agreement of sale. Any other activities. (Dhiraj T. Walunj) B.ARCH-CA/200s/36699 \$\k Authofu Signatory Layout/Building/Wing NoDaffodil Row Bungalow- 31to 35 Sr. No. Task/Activity Percentageof actual work done (As on 30.06.2026) (1) (2) (3) 1. Excavation 700% 2. Basements (if any) J. Podiums (If any) 4. Plinth 100% 5. Stilt Floor 0% 6. Slabs of Super Shucture 50Yo 7. Internal Walls,Internal Plaster, Floorings, Doors and Windows 0% Within Flats /Premises B. Sanitary Fittings Within the Flat/Premises 0% 9. Stuir.ur"s, Lilts Wells and Lobbies at each Floor level overhead 0% and Underground Water Tanks 10. External plumbing and external Plaster, Elevation, completion 0% ofterraces with waterproofing of the building/wing' 1"1. Installation of Lifts,Water pumps,Fire Fighting Fittings and 0% Equipment as per CFO NOC, Electrical Fittings, Mechanical EquipmenlCompliance to conclitions ofenvironment / CRZ NOC, finishing to entrance Lobby/s,plinthProtection, paving of areas appurtenant to Building/Wing,Compound wall and all other requirements as may berequired to complete the project as per specifications in agreement of sale. Any other activities. Dhiraj T. WalunJ) -cA/200s/36699 Signatory Table B Common Areas (Internal & External Development Works)in respect of the registered phase /project number r.No. Common areas and Proposed Percentage of Actual Details Facilities, Amenities (Yes/No) Work Done (As on 30.06.2026) 1) (2) (3) (4) (s) 1,. Internal Roads and Yes 95% Footpaths 2. Water Supply Yes 50% J. Sewerage (chamber, Lines, Yes 45% Septic Tank, STP) 4. Storm Water Drains No 50% 5. Landscaping &Tree Planting Yes B0% 6. Street Lighting Yes 00% 7. CommunityBuildings No 00"/: 8. Treatrnent andDisposal of No 25% Sewage andSullage water 9. Solid WasteManagement & No 00% Disposal 0. Water Conservation/ Rain Yes 75% Waterharvesting t1. EnergyManagement No 00% 12. Fire Protectionand Fire lrlo 00% SafetyRequirements r3. Electrical meterroom, Sub- Yes 00% Station, Receiving station t4_ Gymnasium,Llbrary, Art & craft Yes 75% Room, Sport Court, & Lawns 5. Amphitheater, Open Gy*, & PIay Yes 95Yo Area, jogging Track. t6. Swimming Pool, Activity Deck, Yes 1,5% (Dhiri ri T. Walunr) Spa Room B.ARC} lsp,12soS1t069e rh$K r Skating Area, Turff Cricket court Yes 1.00% t7. t4. Others (Option toAdd more) Yours FaithfullY ";;".wK,, [3FJiiIi,][f,Ltti] DHIRAJ WALUNIJ (License No. B. ARCH- CA/2005/36699) Agreed and accePted bY: For, K B Rohamare Housing Private Limited CIN : U45202MH201 OPT C203998 K.B.BOHAMAfiE H(IUSING I' ,T.LTD., f 3-!o\rowr'a'< DIRECTOB Name: Amit Ramesh Rohmare Designation: Director Date:23.07.2026 Place: Nashik