Ar. ShitalWalunj Ar. DhiraiWalunj # +91 9890191058 # +91 90114 36516 Bes, No.: CP/20i 0148551 Reg. No.: CA/2005/36699 architectur€ r interior r landscape designers ARCHITECTS Form 1 (See Regulation 3) ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing project and for Withdrawal of Money from Designated Account) Date:16.04.2026 To, K B Rohamare Housing Private Limited, 25, Vitthal Charani, Opp Big Bazar, College Road, Nashik 422005. Subject: Certificate of percentage of completion of construction work of "Manomay Natures Paradize" having MahaRERA Registration Number: P51600014558 being developed by K B Rohamare Housing Private Limited. Sir, We Ar.Dhiraj Walunj have undertaken assignment as Architect/Licensed Surveyor of certifying percentage of Completion of Construction work of the "Manomay Natures Paradize" having MahaRERA Registration Number: P51600014658 being developed by K B Rohamare Housing private Limited. Based on site Inspectiory with respect to layout/each of the building/wingof the aforesaicl Real Estate project. I certify that as on the date of this certificate, the percentage of work done for each of the building/wing of the Real Estate project under MahaRERA is as per table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in table B. (Dhiraj T. ltuaiunj) B.eRcn-cn lzoosl3669e *,.nhffi*,, Office No. 308, Business Court, ln front of lndco Park Apartment, Govind Nagar; Nashik- 422001. Email ' ,rrtrritriffiiffi Table A Layout/Building/Wing No Lily Studio Wing- A, B, C & D Sr. No. Tasly'Activity Percentage of actual work done (As on 31.03.20261 (1) (2) (3) 1. Excavation 100% 2. Basements (if any) J. Podiums (If any) 100% 4. Plinth 100Yo 5. Stilt Floor 100% 6. Slabs of Super Structure 100% 7. Internal Walls, Internal Plaster, Floorings, Doors and Winclows 100% Within Flats /Premises 8. Sanitary Fittings Within the Flat/Premises 25% 9. Staircases, Lifts Wells and Lobbies at each Floor level overhead 100% and Unclerground Water Tanks 10. External plumbing and external Plaster, Elevation, completion of 50% terraces with waterproofing of the building/wing. 11. Installation of Lifts, Water pumps, Fire Fighting Fittings and 25% Equipment as per CFO NOC, Elechical Fittings, Mechanical Equipmen! Compliance to conditions of environment / CRZ NOC, finishing to entrance Lobby /s, plinth Protectiory paving of areas appurtenant to Building/Wng, Compound wall and all other requirements as may be required to complete the project as per specifications in agreement of sale. Any other activities. Layout/Building/Wing No Daffodil Row Bungalow- 37 to 42 Sr. No. Tasly'Activity Percentage of actual work done (As on 31..03.2026) (1) (2\ (3) 1. Excavation 100'/. 2. Basements (if any) J. Podiums (If any) 4. Plinth 100% 5. Stilt Floor 100% 6. Slabs of Super Structure 100% 7. Internal Walls, Internal Plaster, Floorings, Doors and Windows 700% Within Flats /Premises B. Sanitary Fittings Within the Flat/Premises 100% 9. Staircases, Lifts Wells and Lobbies at each Floor level overhead 100% and Underground Water Tanks 10. External plumbing and external Plaster, Elevatiory completion of 100% terraces with waterproofing of the building/wing. 11,. Installation of Lifts, Water pumps, Fire Fighting Fittings and 100% Equipment as per CFO NOC, Electrical Fittings, Mechanical Equipmen! Compliance to conditions of environment / CRZ NOC, finishing to entrance Lobby / s, plinth Protection, paving of areas appurtenant to Building/l{ing, Compound wall and all other requirements as may be required to complete the project as per specifications in agreement of sale. Any other activities. (Dhirai T. Walunj) a.nncH-cR 1200s136699 o,,n$$,"'., Layout/Building/Wing No Daffodil Row Bungalow- 43 to 48 Sr. No. Tasly'Activity Percentage of actual work done (As on 37.03.2026\ (1) (2) (3) 1. Excavation 1.00% 2. Basements (if any) J. Podiums (If any) 4. Plinth 100% 5. Stilt Floor 100% 6. Slabs of Super Structure 100% 7. Internal Walls, Internal Plaster, Floorings, Doors and Winclows 100% Within Flats /Premises 8. Sanitary Fittings With.in the Flat/Premises 1.00% 9. Stuit.*es, Lifts Wells and Lobbies at each Floor level overhead 1.00% and Underground Water Tanks 10. Plaster, Elevation, comPletion of 100Yo terraces with waterproofing of the building/wing. 11. I"sta1l'ation of Lifts, Water PumPS, Fire Fighting Fittings and 100% Equipment as per CFO NOC, Electrical Fittings, Mechanical Equipment, Compliance to conditions of environment / CRZ NOC, finishing to entrance Lobby/s, plinth Protection, paving of areas appurtenant to Building/Wn1, Compound wall and all other requirements as may be required to complete the project as Per specifications in agreement of sale. Any other activities. i ulhirai T. Walunj) d.nncn-cn/ 2oos/36699 o,,,k"N,*,.,, Layout/Building/Wing No Daffodil Row Bungalow- 49 to 54 Sr. No. Tasly'Activity Percentage of actual work done (As on 3-t.03.2026) (1) (2) (3) 1,. Excavation 100% 2. Basements (if any) J. Podiums (If any) 4. Plinth 100% 5. Stilt Floor 0% 6. Slabs of Super Structure 50% 7. Internal Walls, Internal Plaster, Floorings, Doors and Windows 100v, Within Flats /Premises 8. Sanitary Fittings Within the Flat/Premises 100% 9. Staircases, Lifts Wells and Lobbies at each Floor level overhead 100% and Underground Water Tanks 10. External plumbing and external Plaster, Elevation, completion of 700% terraces with waterproofing of the building/wing. 11. Installation of Lifts, Water pumps, Fire Fighting Fittings and 100% Equipment as per CFO NOC, Electrical Fittings, Mechanical Equipment Compliance to conditions of environment / CRZ NOC, finishing to entrance Lobby/ s, plinth Protection, paving of areas appurtenant to Building/Wng, Compound wall and all other requirements as may be required to complete the project as per specifications in agreement of sale. Any other activities. iDhirai T. Walunj) -{.N9< B.nncH -tp./ 2 oo s/-366ee Authorlse&*ignatorY Layout/Building/Wing No Daffodil Row Bungalow- 31to 36 Sr. No. Tasly'Activity Percentage of actual work done (As on 37.03.2026) (1) (2) (3) 1. Excavation 100% 2. Basements (if any) J. Podiums (lf any) 4_ Plinth 100% 5. Stilt Floor 0% 6. Slabs of Super Structure 50% 7. Internal Walls, Internal Plaster, Floorings, Doors and Windows 0% Within Flats /Premises 8. Sanitary Fittings Within the Flat/Premises 0% 9. Staircases, Lifts Wells and Lobbies at each Floor level overhead 0% and Unclerground Water Tanks 10. External plumbing and external Plaster, Elevation, completion of 0% terraces with waterproofing of the building/wing. 11. Installation of Lifts, Water pumps, Fire Fighting Fittings and 0% Equipment as per CFO NOC, Electrical Fittings, Mechanical Equipment, Compliance to conditions of environment / CRZ NOC, finishing to entrance Lobby/s, plinth Protection, paving of areas appurtenant to Building/Wng, Compound wall and all other requirements as may be required to complete the project as per specifications in agreement of sale. Any other activities. Table B Common Areas (Internal & External Development Works) in respect of the registered phase /project number Sr. No. Common areas and Proposed Percentage of Details Facilities, Amenities (Yes/No) Actual Work Done (As on 31.03.2026) (1) (2) (3) (4) (s) 1. Internal Roads and Yes 95% Footpaths 2. Water Supply Yes 50% J. Sewerage (chamber, Lines, Yes 45% Septic Tank, STP) 4. Storm Water Drains No 50% 5. Landscaping &Tree Planting Yes B0% 6. Street Lighting Yes 00% 7. Community Buildings No 00% B. Treatment and Disposal of No 25% Sewage and Sullage water 9. Solid Waste Management & No 00% Disposal 1.0. Water Conservation/ Rain Yes 75% Water harvesting t1. Energy Management No 00% 12. Fire Protection and Fire No 00% Safety Requirements r3. Electrical meter room, Sub- Yes 00% Statiory Receiving station 14. Gymnasium, Library, Art & craft Yes 75% Room, Sport Court, & Lawns 15. Amphitheater, Open Gy*, & Play Yes 95% Area, Jogging Track. 16. Swimming Pool, Activity Deck, Yes 15% Spa Room 17. Skating Area, Turff Cricket court Yes 100% 14. Others (Option to Add more) (Dhiraj T. Walunj) \x B.ARCH-CA 1200s136699 Authorlsed $!natory Yours Faithfully (Dlriraj T. Walunj) s,nRcn-ca 200s136699 \N-- Authorlsed SignatorY AT.DHIRA] WALUNJ (License No. B. ARCH- CA/2005/36699) Agreed and accepted bY: For, K B Rohamare Housing Private Limited CI N : U45202MH201 OPT C203998 K.B.ROHAMAHE H()USING I '.I-TD. e 3'!uuo*0'< DIRECTOR Name: Amit Ramesh Rohmare Designation: Director Date: 1.6.04.2026 Place: Nashik