Form 1 (See Regulation 3) ARCHITECT'S CERTIFICATE (To be submitted at the time of Regishation of Ongoi project and for Withdrawal of Money from Designated Date:75.70.2024 To, K B Rohamare Housing Private Limited, 25, Vitthal Charani, Opp Big Bazar, College Road, Nashik 422005. Subject: Certificate of percentage of completion of work of "Manomay Natures Paradize" having MahaRERA Registration Number : 4658 being developed by K B Rohamare Housing Private Limited. Srr, r / we Dhiraj walunj & shital walunj have undertaken assignment as rchitect/Licensed Surveyor of certifying percentage of Completion of Construction work of the Natures Paradize" having MahaRERA Registration Number :P51600014658 being developed by B Rohamare Housing Private Limited. Based on site Inspection, with respect to layout/each of the buitding/ of the aforesaid Real Estate project. I certify that as on the date of this certificate, the percentage of work done for each of the building/wing of the Real Estate project under MahaRERA is as per table A herein below. The percentage of the work executed with respect to each of the activity of the entire is detailed in table B. [:^[t'f+L]lll,',Hi] ,",, Office No. 308, Business court, ln front of lndco park Apartment, Govind Nagar, Nashik - ^,,hf. 001. Email : vastumitras@gmail.com Table A Layofi/ Building/Wing No Lily Studio Wing- A, B,C & D Sr. No. Tasly'Activity Percentage of actual work done (As on 30.09.2024) (1) (2) (3) 1,. Excavation 100% 2. Basements (if any) J. Podiums (lf any) 700y, 4. Plinth 100% 5. Stilt Floor 100% 6. Slabs of Super Structure 700% 7. Internal Walls,Internal Plaster, Flooring+ Doors and W ndows 100% Within Flats /Premises 8. Sanitary Fittings Within the Flat/Premises nc. o/ LJ /O 9. Staircases, Lifts Wells and Lobbies at each Floor level or, :rhead 100% and Underground Water Tanks 10. External plumbing and external Plaster, Elevation, coml letion of 50% terraces with waterproofing of the building/wing. l-t. Installation of Lifts, Water pumps, Fire Fighting Fittings and 25o/" Equipment as per CFO NOC, Electrical Fittings, Mechan ical Equipments, Compliance to conditions of environment ,CRZNOC, 7 Finishing to entrance Lobby/s, plinth Protection, Paving of areas appurtenant to Building/\Yng, Compound wall and all other requirements as may be required to complete the project as Per specilications in agreement of sale. Any other activities. aluni) [:^[['iil-}Il,',ttl 36699 \$sr Auth6'r\sed SignatorY Layout/Building/Wing No Daffodil Row Bunglow- J7 to 42 Sr. No. Tasly'Activity Percentage of acfual work done (As on 30.09.2024) (1) (2) (3) 1. Excavation 700% 2. Basements (if any) 3. Podiums (lf any) 4. Plinth 100% 5. Stilt Floor 100% 6. Slabs of Super Structure 100% 7. Internal Walls,Internal Plaster, Flooring+ Doors and Windows ).00% Within Flats /Premises 8. Sanitary Fittings Within the Flat/Premises 100% 9. Staircases, Lifts Wells and Lobbies at each Floor level overhead 700% and Underground Water Tanks 10. External plumbing and external Plaster, Elevation, completion of 1.00,/, terraces with waterproofing of the building/wing. 11. Installation of Lifts, Water pumps, Fire Fighting Fittings and 100% Equipment as per CFO NOC, Electrical Fittings, Mechanical Equipments, Compliance to conditions of environment / CRZ NOC Finishing to entrance Lobby/ s, plinth Protection, Paving of areas appurtenant to Building/Wng, Compound wall and all other requirements as may be required to complete the project as per specifications in agreement of sale. Any other activities. Layout/Building/Wing No Daffodil Row Bunglow- 43 to 48 Sr. No. Tasly'Activity Percentage of actual work done (As on 30.0e.2024) (1) (2) (3) (Dhirai T. Walunj) e.lncH-cA/2005i 36699 \DNU( Autholi\ed SignatorY 1. Excavation 7000/" 2. Dasements (rJ any) J. Podiums (lf any) 4. Plinth 100% 5. Stilt Floor 1,00% 6. Slabs of Super Structure 100% 7. Internal Walls,Internal Plaster, Floorings, Doors and W indows 1.00% Within Flats /Premises 8. Sanitary Fittings Within the Flat/Premises 1,00% 9. Staircaseg Lifts Wells and Lobbies at each Floor lev overhead 700% Underground Water Tanks 10. External plumbing and external Plaster, Elevatiory com rletion of 100% terraces with waterproofing of the building/wing. 11.. Installation of Lifts, Water pumps ,Fire Fighting Fittings and 1.000/" Equipment as per CFO NOC, Electrical Fittings, Mechan Lical Equipments, Compliance to conditions of environment 7/ CRZNOC Finishing to entrance Lobby / s, plinth Protection, Paving ; of areas appurtenant to Building/Wng, Compound wall and all other requirements as may be required to complete the projecl: as Per specifications in agreement of sale. Any other activities. Layout/Building/Wing No Daffodil Row Bunglow- 49 to 54 Sr. No. Tasly'Activity Percentage of acfual work done (As on 30.09.2024) (1) (2) (3) 't. Excavation 1,00% 2. Basements (if any) J. Podiums (If any) 4. Plinth 100% 5. Stilt Floor 0% 6_ Slabs of Super Structure 50% 7. Internal Walls,Internal Plaster, Floorings, Doors and Wi 100% Within Flats /Premises (Dhiral T. Waluni) B.A(CH-CA/zoosl366e9 8. Sanitary Fittings Within the Flat/premises 1000/, 9. Drarrcases/ Llrts we[s and Lobbies at each Floor level overhead 700% Underground Water Tanks 10. r,xternal plumbmg and external Plaster, Elevation, completion of 700% terraces with waterproofing of the building/wing. 1'1.. Installation of Lifts, Water pumps, fire fighting fittings and 700% Equipment as per CFO NOC, Elechical Fittings, Mechanical Equipments, Compliance to conditions of environment / CRZNoc Finishing to entrance Lobby/ s, plinth protection, paving of areas appurtenant to Building/t{tng, Compound wall and all other requirements as may be required to complete the project as per -specifications in agreement of sale. Any other activities. Layout/Building/Wing No Daffodil Row Bunglow- 31to 36 Sr. No. Tasly'Activity Percentage of actual work done (As on 30.09.2024) (1) (2) (3) 1. Excavation 1,00% 2. Basements (if any) J. Podiums (If any) 4. Plinth 1,00% 5. Stilt Floor 0% 6. Slabs of Super Structure 50% 7. Internal Walls, Internal Plaster, Flooring+ Doors ard Wildo*s 0% Within Flats /Premises 8. Sanitary Fittings Within the Flat/Premises 0% 9. Staircases, Lifts Wells and Lobbies at each Floor level overhead 0Yo Underground Water Tanks 10. External plumbing and external Plaster, Elevatiory completion of 0% terraces with waterproofing of the building/wing. 11. Installation of Lifts, Water pumps, Fire Fighting Fittings and 0% Equipment as per CFO NOC, Electrical Fittings, Mechanical Equipments, Compliance to conditions of environment / CRZ NOC Finishing to entrance Lobby /s, plinth Protection, Paving of areas appurtenant to Buildin9/Wng, Compound wall and all other requirements as may be required to complete the project as per specifications in agreement of sale. Any other activities. l, .. I ) -cAJ l0 Table B Common Areas (Internal & External Development Works) 1n of the registered phase /project number Sr. No. Common areas and Proposed Percenti ge of Details Facilities, Amenities (Yey'I.{o) ActualI fork Done (As on 30.09.20 t4) (1) (2) (3) (41 (s) 1,. Internal Roads and Yes 95 /. Footpaths 2. Water Supply Yes 50 J. Sewerage (chamber, Lines, Yes 45 Septic Tank, STP) 4. Storm Water Drains No 50 5. Landscaping &Tree Planting Yes 80 6. Sheet Lighting Yes 00 7. Community Buildings No 00' 8. Treatrnent and Disposal of No 25 Sewage and Sullage water 9. Solid Waste Management & No 00 Disposal t0. Water Conservation/ Rain Yes 15 Water harvesting t1. Energy Management No 001 12. Fire Protection and Fire No 001 Safety Requirements 13. Electrical meter room, Sub. Yes 00: Station, Receiving station 14. Gymnasium, Library, Art & craft Yes 75', Room, Sport Court, & Lawns t5. Amphitheater, Open Gy*, & Play Yes 95',, Area, Jogging Track. (Dhirairi T. Walu Waluni) -.tAi zoos/rsogg i.nncnrtry2oos/35 Authorl' 16. Swimming Pool, Activity D"cL, Yes o/ 7 /o Spa Room t7. Skating Area, Turff Cricket court Yes 10 )% t4. Others (Option to Add more) Yours Faithft Faithtully (Dhiral raj T, T. Walunj) :H-Cry200s l35qee B.ARCH.C,4/ \NK rorlsed Slgnatory\ Afthorlsed DHIRAJ U WAl WALUNJ (License ie No. IB. ARCH- CA/2005/96699) Agreed red and Accepted by: For, K IB Rohamare Housing Private Limited Signah nfure of Promoter Le: Amit Ramesh Rohmare Name: Date:15 15.10.2024