FORM - 2 A [see Maha-RERA order No.5 of 2018) ENGINEER'S CERTIFICATE FOR QUATITY ASSURANCE (site supervisor's certificate) (To be uploaded quarterly) To. The MIs Ahirrao Bulldcon Pvt. Ltd. Flat No. 04. Yatin Apartment, N.D. Patel Road. Nashik 42200 1. Quality Assurance Certificate (Certificate No. ABPL 01/2018 for the quarter ending Oct 18 - Dec 18) Subject: Certificate for quality of materials used and quality of Construction and workmanship for the Work of Swanandl Blossom No. of Building 01 of the Project situated on the plot bearing Survey No 96/3 Final plot no. 1+2 demarcated by its boundaries Colony Road to the Xorth Open Space 10 the East Colony Road to the West Adj. Sr. No. 95 to the South to the west of Division Nashik Village Nashlk Taluka Nashik District Nashik PIN 422013 admeasuring 550.31 Sq. Mtr. Area being developed by M/s Ahirrao Buildcon Pvt. Ltd. Reference: Maha-RERA Registration No. PSl600012647 Sir, 1/ We Arnol Shashikant Ahirrao have undertaken an assignment of supervision of this real estate project. Our Responsibility: To carry out the work in accordance with the development approved permission and as plan and submit certificate of supervision of work and to carry out material testing in-situ or in the authorized laboratory and to ensure quality of work and workmanship as per prescribed specifications. and as per NBC and or other relevant code of practice. 1. Material Testing: 1/ We, have applied following mandatory checks on the basic materials. used in the construction. i) Cement- It has been tested for its fineness. soundness. setting time. compressive strength etc. as per IScode 3535: 1986or as per other relevant IS/85INBC code, or per industry standards and its results are within the permissible limits. ii] Coarse Aggregate - It has been tested, for deleterious materials, clay lumps. crushing value. impact value as per IS 2430: 1986or as per other relevant IS/BS/NBC code or as per industry standards and its results are within the permissible limits. iii) Bncks! Blocks - They have been tested for water absorption. crushing strength etc. as per IS 5454:1978 or as per other relevant IS/85/NBC code or as per industry standards and its results are within permissible limits. iv) Concrete /Ready-mlx Concrete- It has been tested for compressive strength for various periods as 456:2000 and IS 1199 or as per other relevant [SIBS/NBCcodes. as per industry standards and its results are within permissible limits. v) Steel for Concrete - It has been tested as code or as per IS2062:2011 or as per other relevant Is/Bs/NBC per industry standards for tensile strength, elongation and gauge length etc. and its results are within permissible limits. vi) Testing of Other Materials - Other materials like sand, crushed sand, floor tiles, fixtures and fittings. pipes and sanitary fittings etc. (List out all items) used in this project conform to relevant IS/BS/NBC code or as per standards laid down by the industry for a particular material. 2. Workmanship: - I I we hereby certify that work has been carried out under our supervision. We further certify that workmanship and quality is satisfactory and up to the mark and the work has been acceptable within the permissible limits of deviations as per relevant code of practice. 3. Electrical Materials and Workmanship: - Works of all the electrical wirlngJ connections I lift installation electrical installations have been carried out under authorized Iregistered electrical engineer and its records has been maintained, The materials used conform to the relevant l.SI B.SI National Building codes or as per industry standards. 4. Structural Engineer: - Promoters has engaged structural engineer Mr. Amol Shashikant Ahirrao having Licenses No. -NA-- having Office NO.02532S09600 Cell No.94239630S4 The structural design of building(s) in this project has been done under his supervision. He has checked the soil report before laying PCC for foundation in consultation with soil consultant. The form work and concrete mix design have been done as per Is 10262:2009 or as per other relevant codes as applicable. His periodic checks and certificates for STABILITY and SAFETY have been kept on record. 5. Preservation of Records: - Record of all test results of this project have been properly kept in the prescribed formats and will be preserved at least up to the defect liability period or for the period as required by any other provision of law. 6. Please specify materials or any other item of work which were not conforming to the standard specifications and which were not rejected. i) --NA-- _ ii) _ iii) _ Signature of Engineer (Site Supervisor) Kame: Amol Shashikant Ahirrao License No (ifany) -NA- Phone No. 9423963054 Place: Nashik