BHUSHAN HARESHWAR SARDA B.E.(ClVlL) CONSULTING CIVIL ENGINEER Flat No.7, Sancheti heights Canada Corner, Nashik-422005. Mob :9822010744. Form - 2 See Resulation 3 6l2sl2OL8 ENGI NEER'S CERTI FICATE (To be submitted the time of Registration of Ongoing and for withdrawal of Money from designated Account Project wise) To, Nirmiti Buildtech partnership firm through its partner Shri. Yashpal Tatiya of Nashik. Subject:- Certificate of cost lncurred for Development of "TOWN SQUARRE - RESIDENTIAL" Project for Construction of Residential Building of the Second Phase (Maha RERA Registration ltlo. P51600012559) situated on the plot bearing Survey No. 108/8, Nashik Shivar & CTS No. 5138, Final Plot No. -- demarcated byitsboundaries(latitudeandlongitudeoftheendpoints) totheNorthSampatDhotrePlot totheSouth 12M wide road to the East Remaining Part of S.No.108 to the West 30M wide Road of Div. Nashik Village Nashik, Tal. Nashik, Dist Nashik, PIN 422003, Admeasuring 3637.10 Sq.mt area being developeC by Nirmiti Buildtech partnership firm through its partner's 1. Shri. Yashpal Abhay Tatiya 2. Deepak Balasaheb Dharrao. Ref :- MahaRERA Registration Number P51600012559 Sir, I Mr. Bhushan Sarda have undertaken assignment of certifying Estimated costforthe reai estate "TOWN SQUARRE - RESIDENTIAL" Project for Construction of Commercial Building of the Second Phase (Maha RERA Registration No. P51500012559) situated on the plot bearing Survey No. 108/8, Nashik Shivar & CTS No.6138,Final PlotNo.--- demarcatedbyitsboundaries(latitudeandlongitudeoftheendpoints) tothe North Sampat Dhotre Plot to the South 12M wicie road to the East Remaining Part of S.No.108 to the West 30M wide Road of Div. Nashik Village Nashik, Tal. Nashik, Dist Nashik, PIN 422003, Admeasuring 3637.10 Sq. mt area being developed by Nirmiti Buildtech partnership firm through its partner 1. Shri. Yashpal Abhay Tatiya 2. Deepak Balasaheb Dharrao. 1. Following technical professionals are appointed by Owner/Promoter:- (i) Shri Sagar Kabre as Architect (ii) Shri Milind Rathi as Structural consultant (iii) M/s Shri/Smt as MEP Consultant (iv) tvl/s Shri/Smt --.- as Quantity Surveyor 2. We have estimated the cost of the completion to obtain Occupation Certificate/Completion Certificate, of the Civil, MEP & Allied work, of the buildings of the project. Our estimated cost calculations are based on the drawings / plans made available to us for the project under reference by the developer and Developer & Consultants & The Schedule of items and quantity for the entire work as calculated by ------ quantity Surveyor * appointed by Developers/ Engineer, and the Assumption of the cost of material, labour & Other inputs made by Developer, & the site inspection carried out by us. 3. We estimate total estimated cost of completion of the buildings of the aforesaid project under reference as Rs. 5,30,00,000/- (Total of Table A & B). The Estimated total cost of project is with reference to the civil, MEP & allied works required to be completed for the purpose of obtaining occupation certificate & Completion Certificate for the buildings from Nashik Municipal Corporation, being the planning Authority under whose jurisdiction the aforesaid project is being impiemented. 4. The estimated Cost incurred till date is calculated at Rs. 1,85,00,000/ the amount of estimated cost incurred is calculated on the base of amount of total estimated cost. 5. The balance cost of Completion of the civil, MEP & allied works of the building of the subject project to obtain occupation certificate and Completion Certificate from Nashik Municipal Corporation is estimate at Rs. 4,45,00,000/- 6. I certify that the cost of the civil, MEP & Allied work for the aforesaid project as compieted on the date of the certificate is as given in the table A & B below. Table A Building called Town Squarre - Commercial Phase I (To be prepared separately for each building /wing of the Real Estate Project) Sr. Particulars Amount No. L Total Estimated Cost of the commercial building wing as on3LlO7l20t7 dated of 63,000,000 registration is Cost incurred as on 31/05/2018 (based on the estimated cost) 18,500,000 Work done in Percentage (as percentage of the estimated cost) ?,9.37% Balance Cost to be lncurred (based on estimated cost) 44,500,000 Cost lncurred on Additional/Extra ltems as on ----------- On not included in the NIL Estimated Cost (Annexure A) Table B (To be prepared separately for each building /wrng of the Real Estate Project) Sr. Particulars Amount No. 1 Total Estimated Cost of the lnternal and External Development works including amenities and facilities in the layout as on 3LlO712017 dated of registration is Cost incurred as on 3U05/2018 (based on the estimated cost) Work done in Percentage (as percentage of the estimated cost) O.OOo/o Balance Cost to be lncurred (based on estimated cost) Cost lncurred on Additional/Extra ltems as on ----------- On not included in the Nlt Estimated Cost(Annexure A) Yours Faithfully, (Licence No. _) Note:-1) Thescopeofwork istocompletedentirereal estateprojectasperdrawingsapprovedfromtime to time so as to obtain occupation certificate /Completion certificate. 2) Quantity Survey can be done by office of engineer can be done by an independent Quantity Surveyor, whose certificate of quantity calculated can be relied upon by the engineer. ln case of inclependent quantity surveyor being appointed by Developer, the name has to be mentioned at the place marked and in case quantity are being calculated by office of Engineer the name of ihe person in the office of engineer, who is responsible for the quantity calculated should be mentioned at the plane marked. 3) The estimated cost includes all labour, material, equipment and machinery required ro carry out entire work. 4) Asthisisanestimatedcost,anyDiv.inquantityrequiredfortheDevelopment ofthereal estateproject will result amendment of the cost incurred /to be incurred. 5) All Components of work with specification are indicative and not exhaustive. Annexure A List of Extra / Additional ltems executed with Cost (which were not part of the original Estimate of Total Cost) Ntt