.= FORM 1 [See Regulation 3] ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing project and for withdrawal of Money from Designated Account) Date:26102t2O19 To, The Nirmit Buildtech, Nashik Subject : Certificate of Percentage of Completion of Construction Work of Residential phase Building of the Phase I of the Project " TowN seuARRE RES|DENT|AL ,, [MahaREM - Registration Number P51600012559 I situated on the Plot bearing CTS No. 6138/ Survey No. 108/8, demarcated by its boundaries Sampat Dhotre's Plot to the North, 12 mtr wide road to the South, S.No.108 remaining part to the East, 30 mtr Peth Road to the West of Division Nashik, Village Nashik, District Nashik PIN - 422003 admeasuring 3637.10 sq.mts. area being developed by Land Owner Vinod Chhajed & others being developed by Nirmiti Buildtech. Sir,. I Sagar Kabre, Partner of Kabre Consultants, have undertaken assignment as Architect of certifying Percentage of Completion of Construction Work of the RESIDENTIAL Building Phase ll of project ,, ] TOWN SQUARRE" [MahaREM Registration Number P516OOOi2559 situated on the Ptot bearing CTS No. 6138/ Survey No. 108/8, demarcated by its boundaries Sampat Dhotre's Plot to the North, 12 mtr wide road to the south, s.No.'108 remaining part to the East, 30 mtr peth Road to the west of Division Nashik, Village Nashik, District Nashik PIN - 422003 admeasuring 3637.10 sq.mts. area being developed by Land Owner Vinod Chhajed & others being developed by Nirmiti Buildtech. 1- Following technical professionals are appointed by Owner / Promoter :- (r) Shri. Sagar Kabre, Partner Kabre Consultants as Architect; (t) Shri. Milind Rathi as Structural Consultant (iv) Shri Bhushan Sarda as Engineer Based on Site Inspection, with respect to each of the Buildingruing of the aforesaid Real Estate Project, I certify that as on the date of this certificate, the Percentage of Work done for each of the buildingMing of the Real Estate Project as registered yrde number P51600012559 under MahaREM is as per table A herein below. The percentage of the work executed with respect to each of the activity of the entire ohase is detailed in Table B. TABLE-A Building Part-A (A Wing Flat no- 6t7 t8t9t 1 2t 1 3t 1 4t 1 51 1 81 19 t 201 21 t 231 24t 25126t 27 t 28 t 29 I 301 ( B wi ng F lat no- I I 1 0 I I 5l 1 6 I 21 I22l 261 27 I 28l29ls Sr. No. Tasks /Activity Percentage of work done (1) (2) (3) 1. Excavation N.A. 0 number of Basement(s) and Plinth ''l number of Podiums 0% 4. Stilt Floor N.A. 5 number of Slabs of Super Structure 1Q0o/o o. lnternal Walls, Internal Plaster, Floorings within 5oo/o Flats/Premises, Doors and Windows to each of the FlaUPremises. 10o/o 7 Sanitary Fittings within the Flat/Premises, Electrical Fittings within the Flat/Premises. 8 Staircases, Lifts Wells and Lobbies at each Floor 0yo level connecting Staircases and Lifts, Overhead and Underground Water Tanks. g The extemal plumbing and external plaster, 0yo elevation, completion of terraces with waterproofing of the Building/Wing' 10. Installation of lifts, water pumps' Fire Fighting 0% Fittings and Equipment as per CFO NOC' Electrical fittings to Common Areas, electro' mechanical equipment, Compliance to condi- tions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing' Comoound Wall and all other requirements as may oe required to obtain Occupation i ComPletion Certificate' TABLE.B Internal and Externar Deveropment works in respect of the entire Registered phase. S.No. Common areas Proposed Percentage of Details and Facilities, (YesiNo) Work done Amenities (1) (2) (3) (4) (5) 1. Internal Roads & Footh-oaths. No 1. Water Supply Yes Sewarage (chamber, lines, Septic Tank, STp). Yes 50% 4. Storm Water Drains Landscaping& Tree Planting. Yes 6. Street Lighting No 7. Community Buildings No 8. Treatment and disposal of No sewage and sullage water. 9. Solid Waste management & Disposal_ No 10. Water conservation, Rain water harvesting. Yes 11. Energy management No 12- Fire protection and Fire Yes 0o/o Safety requirements 13. Electrical meter room, sub- No Station, receiving station. 14. Others (Option to Add more). Yours Faithfully, KABRb C]\ISULTANTS qrciilects l4terior Designers S 96 Sehyadri Houss Kabre. iilico irrc,e rrimb.t Boad hasftk-z Ph '2319077 Partner, Kabre Consultants. Architect (License No.CA/2000/25830 ) TABLE-A Bui f di ng Part-B (A Wi ng F lat no-1 I 2J3l 41 5l'l Ol 1 I I 1 61 17 l22l Sr. No. Tasks /Activity Percentage of work done (2) (3) (1) 1 Excavatton 50% ?. O number of Basement(s) and Plinth 3 Podiums 1 number of ooA 4 Stilt Floor N'A' 5. 6 nunlber of Slabs of Super Structure 50o/o 6. lnternal Walls' Internal Plaster, Floorings within 50o/o Flats/Premises' Doors and Windows to each of the FlaUPremises. 7 Sanitary Fittings within the Flat/Premises, 30' Electrical Fittings within the FlaUPremises' 8. Staircases' Lifts Wells and Lobbies at each Floor 0% level connecting Staircases and Lifts, Overhead and Underground Water Tanks The external plumbing and external plaster' 30% 9. elevation, completion of terraces with waterproofing of the BuildingAlVing 10. Installation of lifts, water pumps' Fire Fighting 0% Fittings and Equipment as per CFO NOC' Electrical fittings to Common Areas' electro' mechanical equipment, Compliance to conol- tions of environment /GRZ f{OC' Finishing to entrance lobby/s, plinth protection' paving of areas appurtenant to Building/Wing' Compound V/all and all other requirements / as may oe requlred to obtain Occupation ComPletion Certificate' TABLE-A Bu i ld i n g Part_C ( B Wi ng F tat no -1 t 2t S t 6t 1 1 t 1 2t 1t t I gt 23t 241 Sr. No. Tasks /Activity Percentage of work done (1) (2) (3) 1. Excavation OYo z. 0 number of Basement(s) and Plinth J. 1 number of Podiums 0o/o 4. Stilt Floor N.A. 6 number of Slabs of Super Structure 0% o. Internal Walls, Internal Plaster, Floorings within Oa/o Flats/Premises, Doors and Windows to each of lhe FlaUPremises. 7. Sanitary Fittings within the FlaVPremises, OYo Electrical Fittings within the FlaUPremises. Staircases, Lifts Wells and Lobbies at each Floor 0% level connecting Staircases and Lifts, Overhead and Underground Water Tanks. The external plumbing and external plaster, 0% elevation, completion of terraces wrth waterproofing of the Building^/ving. 10. Installation of lifts, water pumps, Fire Fighting lyo Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to condi- tions of environment /CRz NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to BuildingMing, Compound Wall and all other requirements as may be required to obtain Occupation / Comoletion Certif icate. TABLE-A Building part_ D (B Wing Ftat no-3t4t7t8t13t14t1gt2}t2ill Sr. No. Tasks /Activity (1) Percentage of work done (2) (3) 1. Excavation 2. 0% 0 number of Basement(s) and plinth 2 1 number of podiums 4. 0% Stilt Floor N.A. 6 number of Slabs of Super Structure 0o/o o. lnternal Walls, lnternal plaster, Floorings within 0o/o Flats/Premises, Doors and Windows to each of the FlaUPremises. 7. Sanitary Fittings within the FlaVpremises. 0% Electrical Fittings within the FlaVpremises. Staircases, Lifts Wells and Lobbies at each Floor 0% level connecting Staircases and Lifts, Overhead and Underground Water Tanr