RAVINDRA PATIL & ASSOCIATES CONSULTING ENGINEERS & PLANNERS 1, '5hri', Shreeji Park, D'5ouza Colony, Near Gangapur Police Station, College Road, Nashik-5. Ph : (0253) 23 1 1 648, Cell :94222 51548 FORM 1 (See Regulation 3) ARCH ITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account) Date: 18107/2019 To, Shree Builders & Contractors, I Prathamesh Residency, Behind Ved Mandir, Nashik Subject: Certificate of Percentage of Completion of Construction Work of Shree Ravi Residency having MahaRERA Registration Number -P51600010553 (only applicable after project registration) being developed by Shree Builders & Contractors Sir, I Mr. Ravindra S Patil have undertaken assignment as Licensed Surveyor of certifying Percentage of Completion of Construction Work Shree Ravi Residency having MahaRERA Registration Number -P51600010553 (only applicable after project registration) being developed by Shree Builders & Contractors. Based on Site Inspection. With respect to Layout leach of the Building/Wing of the aforesaid Real Estate Project. I certify that as on the date of this ceftificate, the Percentage of Work done for each of the building/Wing of the Real Estate Project under MahaRERA is as per Table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. Table A Shree Ravi Residencv Percentage Sr. of Actual work done Tasks /Activity No (as on the date of (2) (l) certificate) (3) I Excavation 100 2 Basements (if any) r00 a J Podiums (if any) NA 4 Plinth 00 5 St t Floor 00 6 Slabs of Super Structure 00 7 Internal walls, Internal Plaster, Floorings, Doors and r00 Windows with in Flats/Prem ises 8 Sanitary Fittings within the Flat/Premises r00 9 Staircases, Lifts Wells and Lobbies at each Floor level r00 Overhead and Underground Water Tanks l0 The external plumbing and external plaster, elevation, 100 completion of terraces with waterproofing of the Building/Wing, ll Installation of lifts, water pumps, Fire Fighting Fittings 100 and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, Compliance to conditions of environment ICRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of sale. Any other activities TABLE-B Comrnqn Areas (lnternal & Erternal Develonment works) in Respect of the Registered Phase/proiect n u m ber Percentage of Sr. Proposed Actual Work done Common areas and Details No. (Yes/|.{o) (as on the date of Facilities (2) (s) (l) (3) certificate) (4) I Internal Roads & NO Footpaths 2. Water Supply YES 100 FROM NMC J. Sewerage (chamber, YES 100 Septic Tank and Soak lines, Septic Tank, STP) Pit 4. Storm Water Drains NA 5. Landscapin g &. Tree NA Planting 6. Street Liehtins NO 7. Community Buildings NA 8. Treatment and disposal NA of sewage and sullage water 9. Solid Waste NA management & Disposal 10. Water conservation/ YES r00 Rain Water Rain water harvesting Harvesting ll Energy management NA 12. Fire protection and fire NA safety requirements Percentage of Sr. Proposed Actual Work done Common areas and Details No. (Yes/|.{o) (as on the date of Facilities (2) (s) (l) (3) certificate) (1) t3. Electrical meter room, YES r00 Electrical Meter Box sub-station receiving station 14. Others (option to add NA more) For Rqlindra Patil & Associates W, S. PATIL ^',INDRA Engineer (R.eg. No. 341) , Ravindra S. Patil Licensed Engineer (License No.34l) Date: 18/07/2019 Place : Nashik For Quarter July to September 2019 Agreed and Accepted by: Signature of Promoter Name: Sanjay Manak Patil