RAVINDRA PATIL & ASSOCIATES CONSULTING ENGINEERS & PLANNERS 1, '5hri', shreeji Park, D'5ouza colony, Near Gangapur police statjon, college Road, Nashik-5. Ph : (0253) 231 1 648, Cell :94222 5i 548 FORM I (See Regulation 3) ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project and for withdrawal of Money from Designated Account) Date: 1611012017 To, Shree Builders & Contractors, I Prathamesh Residency, Behind Ved Mandir, Nashik Subject: Certificate of Percentage of Completion of Construction Work of Shree Ravi Residency having MahaRERA Registration Number - P51600010553 (only applicable after project registration) being developed by Shree Builders & Contractors Sir, I Mr. Ravindra S Patil have undeftaken assignment as Licensed Surveyor of certifying Percentage of Completion of Construction Work Shree Ravi Residency having MahaRERA Registration Number - P51600010553 (only applicable after project registration) being developed by Shree Builders & Contractors. Based on Site Inspection. With respect to Layout I each of the Building/Wing of the aforesaid Real Estate Project. I certify that as on the date of this certificate, the Percentage of Work done for each of the building/Wing of the Real Estate Project under MahaRERA is as per Table A herein below. The percentage of the work executed with respect to each of the activity of the entire phase is detailed in Table B. Table A Shree Ravi Residencv Percentage Sr. of Actual work done Tasks /Activity No (as on the date of (2) (t) certificate) (3) I Excavation r00 2 Basements (if any) 100 3 Podiums (if any) NA 4 PI nth 100 5 Stilt Floor t00 6 Slabs of Super Structure r00 7 Internal walls, Internal Plaster, Floorings, Doors and r00 Windows within Flats/Premises 8 Sanitary Fittings within the FlatiPremises 100 9 Staircases, Lifts Wells and Lobbies at each Floor level 100 Overhead and Underground Water Tanks r0 The external plumbing and external plaster, elevation, r00 completion of terraces with waterproofing of the Building/Wing, ll Installation of lifts, water pumps, Fire Fighting Fittings t00 and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, Compliance to conditions of environment ICRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of sale. Any other activities TABLE-B Percentage of Sr. Proposed Actual Work done Common areas and Details No. (Yes/I.{o) (as on the date of Facilities (2) (s) (l) (3) certificate) @l I f nternal Roads & NO Footpaths 2. Water Supply YES 100 FROM NMC a Sewerage (chamber, YES r00 Septic Tank and Soak lines, Septic Tank, STP) Pit 4. Storm Water Drains NA 5. Landscaping &. Tree NA Planting 6. Street Lighting NO 7. Community Buildings NA 8. Treatment and disposal NA of sewage and sullage water 9. Solid Waste NA management & Disposal 10. Water conservation/ YES 100 Rain Water Rain water harvesting Harvesting ll Energy management NA 12. Fire protection and fire NA safety requirements Percentage of Sr. Proposed Actual Work done Common areas and Details No. (Yes/I.{o) (as on the date of Facilities (2) (s) (l) (3) certificate) (4) t3. Electrical meter room, YES 100 Electrical Meter Box sub-station receiving station 14. Others (option to add NA more) Jra Patil & Associates U+ Engineer (Reg. No. 341) , Ravindra S. Patil Licensed Engineer (License No.34l) Date: l6/1012017 Place : Nashik For Quarter October to December 2017 Agreed and Accepted by: eb Signature of Promoter Name: Sanjay Manak Patil