BEIORE THE MAHARASHTRA REAL ESTATE REGULATORY AUTHORITY MUMBAI COMPLAINT NO. CC001000000000094 Dattatay Khedekar Complainant Versus M/s. ShreePrakash Creative Buildcon J.V MahaRERA Regn. No. P51600007163 Respondent Corum: Shri Gautam Chatterjee, Chairperson, MahaRERA Complainant was hirrself plesent. Respondent did not appear. Order (Ex-parte) May 16, 2019 1. The Complainant has stated that he had booked an apartment in the Respondent,s proiect,Le Regalia Phase II BLDG E AND I' situated at Nashik in 2012. The Complainant stated that therea-fter he cancelled the said booking, however, the Respondent is yet to refund the amount paid. Therefore, he prayed that the Respondent be directed to refund the amount paid with interest. 2. The Respondent u,,as not present on the date of headn& despite service oI notice. 3- On review of the Respondent's regishation webpage it is observed that the extended project registration granted under the provlsions of srtion 6 of the Real Estate (Regulation and Development) Act, 2016 has also lapsed on December 31, 2018. 4. During the cource of the hearin& it was explained to the Complainant tlat since the prorect registation has iapsed and the project is still incomplete, the only way forward wouid be to protect the right of the allottees and enable them to form an Association so as to exploie the 1/2 possibfity of invoking the provisions of section 7/8 of the said Act to take the proiect towards completion. At this stage, when the project is at a stand-still, it would not be proper to create further charge on the project in the nature of allowing refuld of money to any allottee, from the dedicated RERA account specially created as a ringed fenced account for the purPose of completion of the project. 5. In view of the above facts, the Respondent is directed to handover the list o{ allottees oI the said proiect to the Complainant within 30 days {Iom the date of the said Order, to enable the allottee6 to take an hJormed decision pe aining to drc said proiect. The allottees arc advised to ploceed u]rder Section 7/8 of the Act as per the MahaRERA Order no. 8/2019 dated March 29, 2019 on Revocation of Re8istration of Projecl 6. The Respondent rnay seek the approval of the association of allottees for order under Section 7(3) of the said Act, as per MahaRERA Order no 7/2019 dated February 8,2019 on Revocation of Regishation of Project for reviving and completing the said project. 7. Consequently, the matter is hereby disposed of utam Chatterjee) NIaIaRERA 2/2