BEFORE THE MAHARASHTRA REAL ESTATE REGULATORY AUTHORITY MUMBAI 1. COMPLAINT NO: CC001000000000065 Ujwala Yewale 2. COMPLAINT NO: CC001000000000064 Samfu Pradhan Compiainants Versus M/s. ShreePrakash Creative Buildcon J.V. MahaRERA Regn. No. P51600007163 Respondent Corum: Shri. Gautam Chatterjee, Chairperson, MahaRERA Complainant no. 1 was represented by Mr. Sudhir Yewale, Authorised representative. Compiainant no. 2 did not appear. Respondent was represented by Mr. Mrunal B. Pandya, Adv. Order Augtst 29,2018 1. The Complainzmts have purchased apartments in the Respondenf s project'Le Regalia Phase II BLDG E AND F' sihlated at Nashik via registered agreements for sale. The Complainants alleged that the date of possession as stipulated by the said agreements is long over and the respondent has failed to hand over the possession till date. Therefore, they prayed that the Respondent be directed to pay them interest for the delay in han.-iing over possession. 2. In Complaint no: CC001000000000032, MahaRERA has already decided the reasonable date for handing over possession as June 30, 2018. 3. In view of the above facts, the Respondent is liable to pay interest to the Complainants from |uly 1,,2018 nll the actual date of possessiory on the entire amount paid by the Complainants to the Respondent. The said interest shall be at the rate as prescribed under Rule 18 of the Maharashtra Real Estate (Regulation and Development) (Registration of Real Estate Projects, Registuation of Real Estate Agents, Rate of Interest and Disclosures on Website) Rules, 2017. 4. Consequmtly, the matters are hereby disposed of. Chatterjee) MahaRERA 2/2