Bhushan Shintre 'Gumsmruti' Near Utsav Garden, Nashikroad. FORM.2 [See Regulation 3] ENGINEER'S CERTIFICATE Date: 26 107 12017. The,,sAIRAJ Builders And Devel0per s", 61'.7, Third Fioor, vedant Plaza, Tidke col0ny, Trimbak Road, Nashik 4zz}Oz,Maharashtra. Subject: certificate of cost Incurred for Development of sairaj sky court Apartments, The project situated on the Plot. No.2+3+6+7, Sr.No. 773 , demarcated by its norndaries ( latitude &longitude of the endpoints) On or towards EAST 6.00 Mtrs Wide ColonY Road On or towards WEST 18.00 Mtrs Wide DP Road On or towards SOUTH Plot No. 1 and 8 On or towards NORTH Plot No. 4 and 5 of Division, Nashik village, NashikTaluka, District Nasik 422002, admeasuring 4105.10 Sq. Mtrs on which building Sairaj Sky Court Apartments is being constructed and developed by "SAIRAJ Builders And Developers"' I Bhushan Shintre, have und.ertaken assignment of certifying Estimated Cost for the Subject Real Estate Project proposed, to be registered under MahaRERA, being situated on Plot. No.2+3+6+7, Sr.No. 773, ofDivision, Nashik Village, NashikTaluka, District Nashik 422002, admeasuring 4105.10 Sq. Mtrs on which building Sairaj Sky Court Apartments is being constructed and developed by "SAIRAJ Builders And Developers". 1. Following technical professionals are appointed by owner / Promoter :- (il M/s/shri/smt Ravi Amrutkar & Associate as L.S. / Architecti (iil Nqlslshri/smt Reliable Consultants (Prop Sanjeev Patei) as StructuralConsultant (iiil urs /shrilsmt Mr.Amol Bhalerao Quantity Surveyor* 2. We have estimated the cost of the completion to obtain Occupation Certificate/Completion Certificate, of the Civil, MEP and Altied works, of the Building(s) of the project. Our estimated cost calculations are based on the Drawings/plans made available to us for the project under quantity for the entire reference by the Developer and Consultants and. the Schedule of items and work as calculated by Mr. Amol Bhalerao quantity Surveyor* appointed by Developer/Engineer, I project 3. We estimate Total Estimated Cost of completion of the building(s) of the aforesaid under reference as Rs.10,30,45,000/--( Total of Table A and B)' The estimated Total Cost of project is with ref'erence to the Civil, MtrP and allied works required to be completed for the purpose of obtaining occupation certifi cate I completion certificate for the building(s) from under whose jurisdiction the theNashik Municipai Corporation, being the Planning Authority I aforesaid project is being implemented' of Table A 4. The Estimated Cost Incurred till date is calculated at Rs. 6,67,16,554/'-(Total and. B). The amount of Estimated cost Incurred is calculated' on the base of amount of Total Estimated Cost. of 5. The Balance cost of Completion of the Civil' MEP and Allied works of the Building(s) from the subject project to obtain Occupation Certificate / Completion Certificate Of estimate date Rs.3,6 3,28,4461-'(Total Nashik Municipal corpor.ation (Planning -\uthoritl-) is Table A and B). aforesaid Project as 6. I certifY that the Cost of the Civil, MEP and allied work for the completed on the date of this certificate is as given in Table A and B below : TaeLPA Sairaj Sky Court APartments Particulars Amounts Sr. No (z) (s) (r) Total Estimated cost of the building/wing Rs. 10,10,45,000/--- as on-date of Registration is Rs. 6,67, L6,55U--' Cost incurred as on (based on the Estimated cost) 66.03 % Work done in Percentage (as Percentage of the estimated cost ) Rs.3,43,28 ,4461-- Balance Cost to be Incurred (Based on Estimated Cost) Cost Incurred on Additional ,{Extra Items Rs. NIL as on-not included in the Estimated Cost (AnnexureA) Tael-o B (to be prepared fbr the entire registered phase of the ReaI Estate Project) Particulars Amounts Sr. No. (s) (r) (z) Tota1 Estimated cost of the Internal and External Rs. 20,00,000/-' Development Works including amenities and Facilities in the laYout as o date of Registration i s (3) (2) (1) Rs. NIL / Cost incurred as on io;;"" the Estimated cost)' 0.00 % O*") Work done in Percentage cost)' of the estimated i;;;;"tage Rs.20,00,000/'-' - Incurred' Balance Cost to be Cost)' tUr*"4'." Estimated Rs. NIL /Extra ltems Cost Incurred on Additional includ'ed in not ('q'""""r" N' li""il ;t*;t" Jco't Yours Faithfully' ,z'>L - Signature of Engineer' W (License No R'?i"'[f ! 3P:'tlJfi A-522364'5') * Note: from Estate project as per drawings approved to complete entire Real 1. The scope of work isO""rrpution Certlticate/Completion Certificate' time to time so "r;;;;i' u" relied' upon by the Engineer' 2.(*)Quantitysurvey"ul.b",donebyofficeofEngineerorCanb.ed.onebyanind.epend.ent certificatJ-oi-o"u"'*' "ur"'iut*a "ut the name has to be Quantity srrrrr"yor,'whosequantity. surveyor being urn"*a"a by Devel0per, by office of Engineer' In case of independ.ent u"lt'g calculated' (.1 u.ra ,r, .u." q,rurrtitv u*" calculated mentioned at the ,#;;;"a *h; ;-;";poisible for the quantitv ,1" the name of the ;;;;;, -rr, place"ffi;;i;reir,""r, marked (*)' 'red to at the shouldbe mentioied --:^1 ^^,,inrnent 8rr 3.Theestimatedcostinclud'esalllabour,material,equipmentandmachineryrequl carry out entire work' of the ,. - : in quantity requlre d. for development cost' any deviation 4. As this is an estimated RealEstateprojectwillresultinam".rJ*",'torthecostincurred/tobeincurred' S.Allcomponentsofworkwithspecificationsareindicativeandnotexhaustive. Annexure A ltems executed with Cost List of Extra/Ad'd'itional the original Estimate of Total Cost) (which were not part of Bhushan Shintre 'Gumsmruti' Near Utsav Garden, Nashikroad. FORM.2 [See Regulation 3] ENGINEER'S CERTIFICATE Date: 26 107 12017. The,,sAIRAJ Builders And Devel0per s", 61'.7, Third Fioor, vedant Plaza, Tidke col0ny, Trimbak Road, Nashik 4zz}Oz,Maharashtra. Subject: certificate of cost Incurred for Development of sairaj sky court Apartments, The project situated on the Plot. No.2+3+6+7, Sr.No. 773 , demarcated by its norndaries ( latitude &longitude of the endpoints) On or towards EAST 6.00 Mtrs Wide ColonY Road On or towards WEST 18.00 Mtrs Wide DP Road On or towards SOUTH Plot No. 1 and 8 On or towards NORTH Plot No. 4 and 5 of Division, Nashik village, NashikTaluka, District Nasik 422002, admeasuring 4105.10 Sq. Mtrs on which building Sairaj Sky Court Apartments is being constructed and developed by "SAIRAJ Builders And Developers"' I Bhushan Shintre, have und.ertaken assignment of certifying Estimated Cost for the Subject Real Estate Project proposed, to be registered under MahaRERA, being situated on Plot. No.2+3+6+7, Sr.No. 773, ofDivision, Nashik Village, NashikTaluka, District Nashik 422002, admeasuring 4105.10 Sq. Mtrs on which building Sairaj Sky Court Apartments is being constructed and developed by "SAIRAJ Builders And Developers". 1. Following technical professionals are appointed by owner / Promoter :- (il M/s/shri/smt Ravi Amrutkar & Associate as L.S. / Architecti (iil Nqlslshri/smt Reliable Consultants (Prop Sanjeev Patei) as StructuralConsultant (iiil urs /shrilsmt Mr.Amol Bhalerao Quantity Surveyor* 2. We have estimated the cost of the completion to obtain Occupation Certificate/Completion Certificate, of the Civil, MEP and Altied works, of the Building(s) of the project. Our estimated cost calculations are based on the Drawings/plans made available to us for the project under quantity for the entire reference by the Developer and Consultants and. the Schedule of items and work as calculated by Mr. Amol Bhalerao quantity Surveyor* appointed by Developer/Engineer, I project 3. We estimate Total Estimated Cost of completion of the building(s) of the aforesaid under reference as Rs.10,30,45,000/--( Total of Table A and B)' The estimated Total Cost of project is with ref'erence to the Civil, MtrP and allied works required to be completed for the purpose of obtaining occupation certifi cate I completion certificate for the building(s) from under whose jurisdiction the theNashik Municipai Corporation, being the Planning Authority I aforesaid project is being implemented' of Table A 4. The Estimated Cost Incurred till date is calculated at Rs. 6,67,16,554/'-(Total and. B). The amount of Estimated cost Incurred is calculated' on the base of amount of Total Estimated Cost. of 5. The Balance cost of Completion of the Civil' MEP and Allied works of the Building(s) from the subject project to obtain Occupation Certificate / Completion Certificate Of estimate date Rs.3,6 3,28,4461-'(Total Nashik Municipal corpor.ation (Planning -\uthoritl-) is Table A and B). aforesaid Project as 6. I certifY that the Cost of the Civil, MEP and allied work for the completed on the date of this certificate is as given in Table A and B below : TaeLPA Sairaj Sky Court APartments Particulars Amounts Sr. No (z) (s) (r) Total Estimated cost of the building/wing Rs. 10,10,45,000/--- as on-date of Registration is Rs. 6,67, L6,55U--' Cost incurred as on (based on the Estimated cost) 66.03 % Work done in Percentage (as Percentage of the estimated cost ) Rs.3,43,28 ,4461-- Balance Cost to be Incurred (Based on Estimated Cost) Cost Incurred on Additional ,{Extra Items Rs. NIL as on-not included in the Estimated Cost (AnnexureA) Tael-o B (to be prepared fbr the entire registered phase of the ReaI Estate Project) Particulars Amounts Sr. No. (s) (r) (z) Tota1 Estimated cost of the Internal and External Rs. 20,00,000/-' Development Works including amenities and Facilities in the laYout as o date of Registration i s