Ar. Tapasya Bendale Res: 6, Blue Berry Apartment, Bhavanjali Nagar Off.: Gangapur Road, Nashik-13. Contact:- 955292987, 0253-2418080 Reg.No:-CA/2004/33306 Email:- tapasyabendale@yahoo.com Date:20.01.18 ARCHITECT'S CERTIFICATE To, M/S Shweta Infrastructure & Housing (I)Pvt.Ltd. Samraat House, Tagore Nagar, Opp. Ambedkar Nagar, Nashik-Pune Highway, Tal. & Dist. Nashik, 422 006. Subject: Certificate of Percentage of Completion of Construction Work of Samraat Symphony Project 02,Building 1- Wing D,[ Maha RERA Registration Number P51600002742] of the Project situated on Plot No. 84, S. No. 899/1+899/2/1+899/3/1/84, Nashik Shiwar,demarcated by it’s a boundaries(latitude and longitude of the end points)6.00 Mt Wide Road(19.958338, 73.771772) to the North, Samraat Symphony Completed Project 03(19.958070, 73.771389)to the South,S.No.898(19.9583287, 73.771989) to the East and Samraat Symphony Project 01(19.958229, 73.771791)to the West of Tal. & Dist. Nashik,PIN422009, admeasuring 973.49 Sq. Mt. area being developed by M/S Shweta Infrastructure & Housing (I) Pvt. Ltd. Sir, I Ar. Tapasya H. Bendale, have under taken assignment as an Architect of certifying Percentage of Completion of Construction Work of Samraat Symphony Project 02, Building 1- Wing D, of Project situated on Plot No. 84, S. No. 899/1+899/2/1+899/3/1/84, Nashik Shiwar, admeasuring 973.49Sq. Mt.area being developed By M/S Shweta Infrastructure & Housing India Pvt. Ltd. Following technical professionals are appointed by Owner/ Promoter:- (i) Smt. Tapasya H. Bendale as an Architect (ii) Shri. Jayant Inamdar (STRUDCOM, Pune) as Structural Consultant (iii) Shri. Sharadchandra Rao (ECEPH, Mumbai)as MEP Consultant Based on Site Inspection, with respect to each of the Building / Wing of the aforesaid Real Estate Project, I certify that as on the date of this certificate, the Percentage of Work done for each of the building / Wing of the Real Estate Project is as per table A herein below. The percentage of the work done executed with respect to each of the activity of the entire phase is in Table B. 1 Ar. Tapasya Bendale Res: 6, Blue Berry Apartment, Bhavanjali Nagar Off.: Gangapur Road, Nashik-13. Contact:- 955292987, 0253-2418080 Reg.No:-CA/2004/33306 Email:- tapasyabendale@yahoo.com Table A Building 1– Wing D Sr. Percentage No Tasks /Activity of work done 1 Excavation 100% 2 Plinth 100 % 3 Podium 100 % 4 Stilt Floor 100 % 5 8 number of Slabs of Super Structure 80 % Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows 0% 6 to each of the Flat/Premises 0% 7 Sanitary Fittings within the Flat/Premises, Electrical Fittings within the Flat/Premises 0% Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and 8 Lifts, Overhead and Underground Water Tanks The external plumbing and external plaster, elevation, completion of terraces with 0% 9 waterproofing of the Building/Wing, Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO 0% NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, 10 plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 2 Ar. Tapasya Bendale Res: 6, Blue Berry Apartment, Bhavanjali Nagar Off.: Gangapur Road, Nashik-13. Contact:- 955292987, 0253-2418080 Reg.No:-CA/2004/33306 Email:- tapasyabendale@yahoo.com TABLE-B Internal&ExternalDevelopmentWorksinRespectoftheentireRegisteredPhase - Sr. Proposed Percentage No Common areas and Facilities, Amenities (Yes/No) of Work done Details Internal Paved 1 Internal Roads & Footpaths Yes 80% Driveways 70% To be obtain 2 Water Supply Yes from NMC 3 Sewerage (chamber, lines, Septic Tank, STP) Yes 70% Proposed 0% 4 Storm Water Drains Yes Proposed 0% Proposed on Podium & 5 Landscaping & Tree planting Yes Periphery 6 Street Lighting Yes 0% Proposed 80% Club & 7 Community Buildings Yes Gymnasium Treatment and disposal of sewage and sullage 70% 8 water Yes STP 100% Ghantagadi, Nashik Municiple 9 Solid Waste management & Disposal Yes corporation 100 % Rain water 10 Water conservation, Rain water harvesting Yes Harvesting 11 Energy management Yes 0% LED Lighting 0% Fire Fighting System, Lighting 12 Fire protection and fire safety requirements Yes arrester Electrical meter room, sub-station, receiving 80% 13 station Yes Substation ready 14 Aggregate area of recreational open space NA N.A. NA 15 Open Parking Yes 75% Proposed Yours Faithfully, Ar. TAPASYA H. BENDALE. 3