ARCH BRIJMOHANSINGH THAKUR H.NO.2-9-101, NAZAR LALLII, TILAK PATH, CHHATRAPATI SAMBHAJI NAGAR Aanexure A FORM I [See Regulation 3] ARCHITECT'S CERTIFICATE (To be submitted at the time of Registration of Ongoing Project & for Withdrawal of Money from Designated Account) Date: 09-01-2025 To, PREM ll'IFRASTRUCTU RES, SHOP i{O 8, NAIK PLAZA, VASANT NAGAR, JAWAHAR COLONY, AUM}'IGABAD Subject: Certificate of Percentage of Completion of Construction Work of P-9 VILLAS having MahaREM Registration Number P51500078512 being developed by PREM INFRASTRUCTURES. (For oct to Dec 2024 oTR) Sir, l/We ARCH BRIJM0HANSINGH THAKUR have undertaken assignment as Architect / Licensed Surveyor of Certifying Percentage of Completion of Construction Work of P-9 VILLAS having MahaREM Registration Number P51500078512 being developed by PREM l1'IFRASTRUCTURES. Eased on the Site lnspection, with respect to the Layout / each BuildingMing of the aforesaid Real Estate Project, I certify that as on date of this Certificate, the Percentage of Work Done for each of the BuildingMing of the Real Estate Project under MahaREM is as per Table-A herein below. The percentage of work executed with respect to each of the activity of entire Phase is detailed in Table-B. TABLE.A Number P-9 VILLAS S. No. Tasks / Activity Percentage of Actual Work Done (As on date of the Certificate) fi) (21 (3) 1 Excavation 100Y0 2 X number of Basement(s) and Plinth 100% r) X number of Podiums 4 Stilt Floor 5 X number of Slabs of Suoer Structure 60% 6 lnternal walls, lnternal Plaster, Floorings within 0o/o Flats/Premises, Doors and Windows to each of the FlaUPremises 7 Sanitary Fittings within the FlaVPremises, Electrical Fittings 1Yo within the FlaUPremises ARCH BRIJMOHANSINGH THAKUR HXO.2-9-101, NAZAR LALLII, TILAK PATH, CHHATRAPATI SAMBHAJI NAGAR 8 Staircases, Lifts Wells and Lobbies at each Floor level lYo connecting Staircases and Lifts, Overhead and Underground Water Tanks. 9 The external plumbing and external plaster, elevation, 0o/o completion of terraces with waterproofing of the Building/\tring 10 lnstallation of lifts, water pumps, Fire Fighting Fittings and lYo Equipment as per CFo NoC, Etectrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ N0C, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to BuildingMing, Compound Wall and all other requirements as may be required to 0btain Ogcupation /Completion Certificate TABLE.B Common Areas nternal & External Works) P-9 VILLAS S. No. Common Areas & Facilities Proposed Percentage Details (Yes / N0) of actual Work Done (As on date of Ceilificate) (1) (21 (3) (4) (s) 1 lnternal Roads & Footpaths NO N.A. 2. Water Supply YES 20Yo FROM BORE-WELL Sewerage (Chamber, Lines, Septic YES 0o/o DMINAGE LINE TILL Tank, STP) . CORPOMTION LINE 4. Strom Water Drains NO N.A. 5. Landscaping & Tree Plantino NO N.A, 6. Street Lighting NO N.A. 7. Community Br!ildings NO N.A, 8. Treatment & Disposal of Sewage and NO N.A. Sullage Water L Solid Waste Management & Disposal NO N.A. '10. Water Conservation / Rain Water YES 0% MIN WATER HARVESTING Harvesting AS PER NORMS 11. Energy ManaQeme!t NO N.A. 12. Fire Protection & Fire Safety NO N.A. requirements 13. Electrical Meter Room, Sub-Station, NO N.A. Receiving Station 14. others (option to Add more) NO N.A. ARCH BRIJMOHANSINGH THAKUR H.NO.2-9-101, NAZAR LALLII, TILAK PATH, CHHATRAPATI SAMBHAJI NAGAR Yours faithfully, ARCH BRIJMOHANSINGH THAI(UR Signature & Name (lN BLOCK LETTERS) of Land Surveyor / Architect License Number Agreed &Accepted by: Signature of Promoter Name: PREM Date: 09-01-2025 PREH II{FMSTRUCTURES rl,.h/fu-r.-- PROPRIETOR